Courseiva

PK0-005 · domain

scenario questions

Practise CompTIA Project+ PK0-005 scenario questions practice questions — original exam-style scenarios with answer choices, explanations, and analysis of common mistakes.

954 questions253 easy420 medium281 hard

Focused practice

Practice scenario questions questions

Scored sessions drawing only from this domain — pick a length below.

Start 20-question practice test →

What this domain covers

What to know about scenario questions

scenario questions questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Watch out for

Common scenario questions exam traps

  • ▸Answering from memory before reading the full scenario.
  • ▸Missing a constraint such as cost, availability, security, scope or command context.
  • ▸Choosing a broad answer when the question asks for the most specific fix.
  • ▸Ignoring why the wrong options are tempting.

Question index

All scenario questions questions (954)

Click any question to see the full explanation, or start a practice session above.

1

A project manager is closing out a project that delivered a new customer portal. The sponsor wants to ensure that lessons from this effort improve future projects and that the product is properly handed over. Which TWO activities should the project manager perform as part of closing the project? (Choose two.)

Medium
2

Which THREE of the following are responsibilities of a project manager? (Select THREE).

Hard
3

In a project, the critical path has a duration of 100 days. Activity X on the critical path has a duration of 10 days and can be crashed to 7 days at an additional cost of $3,000. What is the crash cost per day for Activity X?

Hard
4

During project execution, the project manager notices that the team is struggling with communication, and key stakeholders are not receiving timely updates. Which THREE documents should the project manager review to improve the situation? (Select THREE).

Hard
5

A project manager is tracking remaining work over the course of a sprint to see if the team is on pace to complete all committed stories. Which agile artifact should the project manager use?

Easy
6

Which THREE of the following are generally considered to be part of the project management process groups?

Hard
7

During a phase gate review, the review board determines that the project does not yet meet the exit criteria for the current phase. What is the most likely outcome?

Hard
8

A project manager is using a schedule compression technique that adds resources to critical path activities to shorten the project duration. Which technique is being used?

Hard
9

A project manager is using a predictive life cycle for a software development project. What is a key characteristic of this approach?

Hard
10

Which stakeholder role is typically responsible for providing resources and support for the project?

Easy
11

During project execution, a key stakeholder requests additional features that were not originally approved. The project manager is concerned about scope creep. Which type of project constraint is most directly impacted by scope creep?

Hard
12

A project manager has just received formal approval to proceed with a new payroll system project. The sponsor asked for a document that formally names the project manager and gives authority to apply organizational resources to project activities. Which document should the project manager reference?

Easy
13

A project manager is estimating the cost of a software development project. Using data from a similar past project, she adjusts for size and complexity. Which estimation technique is she using?

Medium
14

The project manager receives a defect report for CI-103. The team identifies that a new requirement necessitates updating CI-103. According to the configuration management process, what should the project manager do FIRST?

Medium
15

A project team is working on a software development project and needs to track changes to requirements, design documents, and source code. They want to ensure that all team members can access the latest versions and that changes are logged with the author and timestamp. Which type of tool should the project manager implement to meet these needs?

Medium
16

A project manager is reviewing the risk register and notices a risk with a probability of 0.4 and an impact of $80,000. The project manager decides to purchase insurance to cover the potential loss. Which risk response strategy is being applied?

Hard
17

During project execution, a team member identifies a potential risk that was not included in the risk register. The project manager logs it and begins the risk assessment process. Where should this risk be recorded?

Hard
18

A project has an issue where a key deliverable fails quality inspection. The project manager escalates to the project sponsor, but the issue remains unresolved. Which THREE actions should the project manager take according to issue management best practices?

Hard
19

Which TWO documents are typically created during the project initiating phase?

Easy
20

Which project management tool displays project tasks against a timeline and shows dependencies?

Easy
21

A project is being executed in a matrix organization. The project manager discovers that a functional manager is reassigning a key team member to another project without notice. What should the project manager do first?

Hard
22

A project manager is leading the deployment of a new customer-facing mobile application that will use a RESTful API. The API will be hosted on a public cloud and must handle sensitive user data. The project sponsor is concerned about security and wants to ensure that the API uses a standard protocol for authorization and that tokens are not easily compromised. Which approach should the project manager recommend?

Hard
23

A project manager is leading a software development project and needs to track the progress of tasks, identify critical path activities, and visualize dependencies. Which tool should the project manager use?

Easy
24

A project manager is developing a quality management plan for a manufacturing project. The project manager needs to identify TWO tools or techniques that are used to plan quality management. Which two should the project manager use? (Choose two.)

Medium
25

A project manager is using a Kanban board to manage workflow. The team wants to limit the amount of work in progress (WIP) to improve flow and reduce bottlenecks. Which metric should the project manager monitor to assess the effectiveness of the WIP limit?

Medium
26

A project team is developing a WBS. Which THREE of the following are characteristics of a well-constructed WBS?

Medium
27

A project team is experiencing frequent scope changes. The project manager wants to ensure that all changes are properly reviewed and approved. Which document should the project manager reference?

Medium
28

You are a project manager for a software development company that uses an Agile methodology with two-week sprints. The team uses Jira for task tracking and Confluence for documentation. During the latest sprint review, stakeholders expressed confusion about the current project status because the burndown chart shows a steady increase in remaining work. Upon investigation, you discover that the development team has been adding new tasks to the current sprint without updating the sprint backlog or adjusting the scope. The product owner is unaware of these additions. The team complains that they are overworked and missing deadlines. Which of the following is the BEST course of action to address the situation?

Medium
29

A project has a CPI of 0.9 and an SPI of 1.1. Which two statements are true? (Select TWO.)

Medium
30

In a RACI matrix, which role is responsible for performing the work?

Medium
31

A project team member is consistently late in completing assigned tasks, affecting the critical path. The project manager should FIRST:

Medium
32

A company is deploying a new VoIP system. Which network infrastructure component is most critical for ensuring voice quality?

Easy
33

A project manager is leading a team to develop a new mobile application. The project has a fixed budget and a strict deadline. During the execution phase, the stakeholder requests additional features that were not originally planned. Which project constraint is most directly affected by this request?

Easy
34

A control chart shows a process with data points fluctuating within the upper and lower control limits, but 8 consecutive points appear on one side of the mean. What does this indicate?

Hard
35

Which THREE of the following are best practices for managing IT infrastructure projects? (Choose three.)

Hard
36

Which of the following is the primary purpose of a feasibility study during the initiating phase?

Medium
37

During the Initiating phase of a construction project, the project manager learns that the sponsoring organization will not commit funding until the document that formally authorizes the project and names the project manager exists. Which document should the project manager produce?

Medium
38

A project manager is leading a data center migration project for a financial services company. The project involves moving 50 servers from an on-premises facility to a co-location data center. The project has a strict deadline of December 31 due to lease expiration. The team has completed 60% of the work with 70% of the budget spent. The project manager notices that the co-location provider has been consistently late in provisioning network circuits, causing delays. Additionally, the team discovered that two servers have incompatible hardware with the new environment, requiring reconfiguration. The project sponsor is pressuring the team to finish on time. What should the project manager do FIRST?

Hard
39

In which type of organizational structure does the project manager have the least authority?

Medium
40

A project manager is leading a software development project that has a fixed budget and strict deadline. During the execution phase, the development team identifies a critical security vulnerability that requires immediate remediation, which will add two weeks to the schedule and increase costs by 10%. What is the BEST course of action for the project manager?

Medium
41

A project manager is preparing for the Closing phase of a project that has been completed successfully. Which TWO activities are part of the Close Project or Phase process? (Choose two.)

Medium
42

Which project scheduling tool displays tasks as horizontal bars on a timeline, shows dependencies between tasks, and can highlight the critical path?

Easy
43

A project manager is overseeing a manufacturing process improvement project. During the monitoring and controlling phase, the project manager notices that the project is two weeks behind schedule due to unexpected machine downtime. The team suggests reducing the amount of testing on the new equipment to recover the schedule. The project sponsor is concerned about meeting the deadline and supports the team's suggestion. What should the project manager do?

Hard
44

A project manager is working in a matrix organization. The project team members report to both the project manager and their functional managers. The project manager has moderate authority and shares resources. This type of matrix is known as:

Medium
45

A project team is developing a new mobile application. During execution, a stakeholder requests additional features that were not in the original scope. The project manager is concerned about scope creep. Which TWO actions should the project manager take to manage this request? (Select TWO).

Easy
46

A project manager is selecting a project from several proposals. The project with the highest Net Present Value (NPV) also has the longest payback period. Which TWO factors should the project manager consider when recommending this project? (Select TWO).

Medium
47

A project manager is reviewing a risk register and wants to document the specific actions that will be taken if a high-probability supplier failure occurs. Which component of the risk register should contain this information?

Hard
48

A project manager is creating a work breakdown structure (WBS) for a software development project. Which technique is most effective for decomposing the project scope into manageable components?

Medium
49

During a quality audit, the project team discovers that 80% of customer complaints are caused by 20% of the defect types. Which quality tool should the project manager use to present this data and prioritize corrective actions?

Hard
50

A project team is experiencing conflicts due to unclear roles and responsibilities. Which document should the project manager refer to in order to clarify team members' roles?

Easy
51

A project manager is analyzing the critical path of a network diagram. Which TWO statements about the critical path are true?

Medium
52

A project manager is estimating costs for a new project using a top-down approach based on historical data from a similar project. Which estimation technique is being used?

Medium
53

A project manager is evaluating two project proposals. Project A has an initial investment of $100,000 and is expected to generate cash flows of $30,000 per year for 5 years. Project B has an initial investment of $50,000 and cash flows of $20,000 per year for 3 years. Using payback period, which project should be selected?

Hard
54

A project team is working on a software development project. The project manager needs to track which team members are assigned to each task. Which document provides this information?

Easy
55

A project team is sharing documents via email but experiencing version confusion. Which tool should the PM implement to improve version control?

Medium
56

A project team discovers a problem that is currently happening and affecting project deliverables. The project manager needs to document this situation. Which document should be used to record this?

Easy
57

Which document contains the deliverables, acceptance criteria, exclusions, assumptions, and constraints for a project?

Easy
58

A project team is using an agile methodology to develop a new feature. The product owner frequently reprioritizes the backlog based on changing customer needs. Which characteristic of agile does this BEST illustrate?

Medium
59

A project manager is using the power/interest grid to classify stakeholders. Which group should be managed most closely because they have high power and high interest?

Medium
60

While monitoring and controlling, the project manager reviews earned value metrics and finds CPI = 0.8 and SPI = 1.1. What does this indicate?

Medium
61

A project manager is overseeing the replacement of aging physical servers with a hyperconverged infrastructure (HCI) solution. During the planning phase, the project manager must identify a risk that could affect the project's ability to meet its schedule. Which action best demonstrates proactive risk management?

Hard
62

A project manager is executing a project and a team member reports that a purchased component does not meet the specifications stated in the procurement agreement. The project manager must document and pursue a remedy. Which TWO activities should the project manager perform? (Choose two.)

Medium
63

A newly assigned project manager is reviewing the document that formally authorizes the existence of a project and grants the project manager authority to apply organizational resources to project activities. Which document is the project manager reviewing?

Easy
64

A project manager is developing a communication plan. The project has team members in three countries with different time zones. Which communication method is most effective for daily status updates?

Hard
65

In a RACI matrix, the person who is ultimately accountable for the completion of a task is denoted by which letter?

Easy
66

During a project, a stakeholder requests additional features that were not in the original scope. The project manager adds these features without formal change control. This is an example of:

Hard
67

A company wants to select a project based on the time it takes to recover the initial investment. Which project selection method should be used?

Easy
68

A multinational company is undertaking a new software implementation project across three regions: North America, Europe, and Asia. The project manager has created a detailed project plan with resources from each region. However, the North American team lead insists on using a different project management methodology than the other regions, claiming it's more efficient. The European team lead is concerned about integration issues. The Asian team lead is neutral. The project manager needs to decide how to proceed. Which approach is BEST?

Hard
69

A project manager is updating the risk register after identifying a new risk. Which TWO fields are typically included in a risk register? (Select TWO).

Medium
70

Which diagram is used in quality management to prioritize the most significant causes of a problem, based on the 80/20 rule?

Medium
71

A project team is conducting a lessons learned session. In which project life cycle phase does this typically occur?

Easy
72

A project manager wants to visualize the sequence of project activities and their dependencies to identify the critical path. Which tool should be used?

Easy
73

A change request is submitted to add a new feature to a project. What is the first step the project manager should take?

Medium
74

A company is implementing a new enterprise resource planning (ERP) system. The project is in the execution phase. The project manager receives a report that during user acceptance testing (UAT), 15 critical defects were found. The defects are related to incorrect calculation logic in the financial module. The testing team estimates that fixing these defects will require two additional weeks of work by the development team. The project sponsor is concerned about the schedule delay and asks the project manager to proceed with the go-live as planned and fix the defects after go-live. The project manager must decide the best course of action. What should the project manager do?

Hard
75

A senior manager is comparing two projects for selection. The manager wants to use a method that considers the time value of money. Which TWO project selection methods incorporate the time value of money?

Medium
76

You are a project manager for a software development project. The team uses a cloud-based project management tool that includes features like task assignment, Gantt charts, and document storage. During a status meeting, a team member reports that they cannot find the latest version of the project schedule. Several team members have been updating the schedule file directly on the shared drive without version control. As a result, the file has multiple conflicting copies. You need to resolve this issue and prevent it from recurring. Which course of action should you take?

Easy
77

A project manager receives a status report showing that the project's SPI is 0.9. What does this indicate?

Easy
78

A project manager is leading a software development project with stable requirements and a fixed budget. The team prefers a sequential approach with clear phases. Which methodology is most appropriate?

Medium
79

A large organization is deploying a new ERP system. The infrastructure team provisions a cluster of virtual machines for the application and a separate database server. During load testing with typical user loads, the database server shows high I/O wait times. The storage administrator confirms that the storage array has sufficient capacity and the disks are healthy. The hypervisor shows no CPU or memory pressure. Which of the following is the most likely cause of the high I/O wait?

Hard
80

Which TWO of the following are components of a project charter?

Medium
81

During the execution phase of a software development project, the team discovers a critical bug that was not identified during planning. The project manager needs to decide how to handle the bug without significantly impacting the project scope and timeline. Which action should the project manager take first?

Medium
82

Order the steps for performing risk management planning.

Medium
83

Using the following risk data, which risk has the highest Expected Monetary Value (EMV)? Risk R01: Probability 30%, Impact $50,000 Risk R02: Probability 50%, Impact $20,000 Risk R03: Probability 80%, Impact $25,000

Medium
84

An organization has multiple projects that are not directly related but are all aimed at achieving the company's strategic goal of expanding into new markets. Which term best describes this collection?

Medium
85

A project team is distributed across three time zones. The project manager needs a tool for real-time collaboration, file sharing, and instant messaging. Which type of tool is MOST appropriate?

Easy
86

Which TWO of the following are key activities performed during the Initiating phase of a project?

Easy
87

A project manager is using a schedule compression technique that adds resources to critical path activities to shorten the project duration. Which technique is being used, and what is its primary trade-off?

Hard
88

Which THREE of the following are commonly recognized project constraints according to the Project Management Body of Knowledge (PMBOK)?

Hard
89

Which THREE tools are commonly used for measuring project performance against the baseline?

Hard
90

A project manager is reviewing the project management plan and notices that an important deliverable's acceptance criteria are missing. The project is currently in the execution phase. What is the best course of action?

Hard
91

Match each acronym to its definition in project management.

Medium
92

An agile team uses a burnup chart to track progress. Which THREE pieces of information are typically shown on a burnup chart?

Medium
93

A project manager is implementing a new enterprise resource planning (ERP) system. The project team is distributed across three time zones, and the project manager needs to ensure that all team members have access to the latest project documents and can collaborate in real time. Which technology solution best meets these requirements?

Hard
94

A project manager is preparing a dashboard for executives. The executives want a single view that shows the project's overall health by combining schedule, cost, and scope performance indicators against thresholds. Which tool should the PM use to present this consolidated status?

Hard
95

A project manager is tracking project performance and notices that the SPI is 0.8 and the CPI is 1.2. What does this indicate about the project?

Hard
96

A project manager is analyzing stakeholders and categorizes a key executive who has high power and high interest. According to the power/interest grid, how should the project manager engage this stakeholder?

Medium
97

During project planning, the project manager creates a network diagram. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. Activities A and B can start immediately. Activity C can start only after Activity A is complete. Activity B has no dependency on others. What is the duration of the critical path?

Medium
98

A project manager needs to break down the project scope into smaller, manageable components. Which tool should they use?

Medium
99

A project has a BAC of $500,000 and a CPI of 0.8. What is the estimate at completion (EAC) assuming the current cost performance will continue?

Hard
100

A project manager has been asked to lead a project that will replace a legacy payroll system. The vendor contract requires a firm completion date tied to a regulatory deadline, and the budget was approved at a fixed ceiling. During the first planning workshop, the sponsor asks the project manager to add a self-service reporting portal that was not part of the approved business case. What should the project manager do FIRST?

Medium
101

A project manager is conducting a risk assessment for an IT infrastructure project that involves migrating critical applications to a new data center. The project manager needs to identify potential risks related to hardware failures, network outages, and data loss. Which TWO risk response strategies are most appropriate for addressing these technical risks? (Choose two.)

Medium
102

A project manager identifies a key stakeholder who has high interest in the project but low power to influence decisions. In the power/interest grid, where should this stakeholder be placed?

Easy
103

During project execution, a team discovers that the actual cost of work performed is $45,000, the planned value is $50,000, and the earned value is $40,000. Which statement is correct?

Medium
104

A project manager uses Monte Carlo simulation to analyze schedule risks. This technique is used to:

Hard
105

Which contract type places the most cost risk on the seller?

Medium
106

A project manager is creating a Work Breakdown Structure (WBS). Which technique is used to break down deliverables into smaller, manageable components?

Medium
107

A project manager is assigned to a new project and needs to document high-level risks, assumptions, and constraints. Which document should the project manager create first?

Easy
108

A project is near completion, but the key stakeholder cannot perform user acceptance testing (UAT) due to prior commitments. What should the project manager do?

Medium
109

A project manager is reviewing dependencies in the project schedule. Which THREE types of dependencies are recognized in project management? (Choose three.)

Hard
110

A project has a dependency where the software must be coded before it can be tested. This is an example of which type of dependency?

Medium
111

Who is typically responsible for providing the project budget and resources, and for resolving issues that are beyond the project manager's authority?

Medium
112

A project manager is assigned to a new project. The sponsor provides a high-level scope and asks for a cost estimate. Which estimation technique should the project manager use at this early stage?

Easy
113

A project manager is using a control chart to monitor the number of defects per day. The chart shows 10 data points within the control limits, but all 10 points are above the mean. What does this indicate?

Hard
114

A project manager is estimating the cost of a software development project. She uses the actual cost of a similar past project and adjusts it for known differences in size and complexity. Which cost estimation technique is she using?

Medium
115

A project manager is reviewing the issue log and notices an issue with high priority that has not been resolved. The project manager has tried to resolve it but cannot. What should the project manager do next?

Medium
116

During the execution phase of a software development project, the team discovers that the database schema needs to be altered to accommodate a new regulatory requirement. The project manager is reviewing the change request. What is the MOST important factor to consider before approving the change?

Medium
117

Which document defines how project information is distributed to stakeholders and who receives what information?

Easy
118

A project manager uses a power/interest grid to categorize stakeholders. Stakeholders with high power and low interest should be managed using which approach?

Medium
119

A project manager is assigned to a project that has poorly defined requirements. Which project management methodology would be most suitable to handle this uncertainty?

Easy
120

During project monitoring and controlling, the project manager calculates the cost performance index (CPI) as 0.8. What does this indicate?

Medium
121

A project manager is conducting a lessons learned session at the end of a project. Which TWO activities are typically performed during project closure? (Select two.)

Medium
122

A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. Which TWO statements are true regarding the project's performance? (Choose two.)

Hard
123

During the Planning phase, a project manager is building the work breakdown structure (WBS) for a construction project. Which TWO characteristics must the WBS satisfy? (Choose two.)

Hard
124

A project has a budget of $100,000 and a duration of 12 months. After 6 months, the project is 50% complete and has spent $60,000. What is the cost variance?

Medium
125

During a quality audit, the team identifies that defects are concentrated in a few areas. The project manager decides to use a Pareto chart. Which TWO statements are true about Pareto charts?

Hard
126

In which project life cycle phase are the key performance indicators (KPIs) typically established to measure project success?

Easy
127

An organization is evaluating two potential projects. Project A has an NPV of $50,000 and a payback period of 2 years. Project B has an NPV of $40,000 and a payback period of 1.5 years. The organization's policy is to select projects with the highest NPV. Which project should be selected?

Medium
128

A project team is using Agile methodology. The product owner frequently changes priorities during the sprint, causing confusion. What is the most appropriate action for the project manager (scrum master)?

Hard
129

A project manager is preparing for the Closing phase of a project that involved an external vendor. Which TWO activities are essential to formally close the project? (Choose two.)

Medium
130

A project manager notices that project costs are consistently exceeding the budget. Which process should the project manager use to address this issue?

Easy
131

Given EV = $80,000 and AC = $90,000, what is the project's cost performance index (CPI) and what does it indicate?

Medium
132

In an agile project, the team is defining the 'Definition of Done' (DoD). Which TWO statements are typically included in a good DoD?

Medium
133

The sponsor asks the project manager to accelerate the project schedule without changing scope. Which technique should the project manager recommend?

Medium
134

Put the steps for managing a change request in the correct order.

Medium
135

A project team is using Jira for agile project management. They want to visualize the flow of work across columns such as 'To Do', 'In Progress', and 'Done'. Which board type should they use?

Medium
136

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, actual cost (AC) is $120,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost performance index (CPI)?

Hard
137

During a project, a critical team member is reassigned to a higher-priority project, leaving the project without sufficient resources. This is an example of a(n):

Hard
138

During a project audit, it is discovered that several deliverables did not meet quality standards. The project manager wants to identify the root causes. Which tool is most appropriate?

Easy
139

Which project document formally authorizes the project and provides the project manager with the authority to apply organizational resources?

Easy
140

A project manager is working on a project with high uncertainty and rapidly changing requirements. Which project life cycle model is MOST appropriate?

Hard
141

A project manager is preparing a stakeholder engagement assessment for a hospital records migration. The sponsor has been supportive but has recently become distracted by another initiative, and the radiology department head actively opposes the new workflow. The project manager wants to move each stakeholder toward the engagement level needed for success. Which TWO actions are MOST appropriate? (Choose two.)

Medium
142

Which TWO of the following are examples of key performance indicators (KPIs) used to measure project success?

Medium
143

A project manager is leading a software localization project with team members in three time zones. The PM notices that decisions made in the weekly status call are frequently reversed by absent team members after the call, and the schedule baseline has slipped twice. Which action should the PM take to improve decision-making and reduce rework?

Hard
144

After a change request is approved, the project manager updates the project baseline. Which document must also be updated to reflect the impact of the change on project risks?

Medium
145

In which Tuckman stage do team members begin to resolve their differences, establish norms, and develop closer relationships?

Easy
146

During project execution, the project manager notices that the team is adding extra features that were not requested by the customer. This is an example of which common project constraint issue?

Medium
147

Which THREE items are considered agile artefacts?

Medium
148

At the end of a project phase, the team holds a meeting to discuss what went well and what could be improved. Which document is produced from this meeting?

Medium
149

An IT project manager is leading a project to upgrade the network infrastructure in a branch office. The project sponsor is concerned about the impact of network downtime on daily operations. The project manager needs to ensure that network availability is maintained during the upgrade. Which of the following should the project manager implement to minimize downtime?

Medium
150

Which TWO are common components of a project management plan? (Choose two.)

Medium
151

A project manager is assigned to a new software development project. During the initiation phase, the project sponsor is hesitant to approve the project charter because the business case does not clearly quantify the expected benefits. The project manager has gathered initial requirements and conducted a feasibility study. What should the project manager do next to move the project forward?

Easy
152

A project manager wants to visually represent the flow of tasks and decision points in a business process. Which tool should be used?

Medium
153

During which phase of the project life cycle is the project charter created and stakeholders initially identified?

Easy
154

During execution, the project manager receives a customer change request to add a significant feature. Analysis shows the change will increase the budget by 15% and extend the schedule by two months. What should the project manager do first?

Hard
155

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.8. What does this indicate about the project?

Hard
156

Which THREE components are typically included in a project management plan?

Hard
157

Which document formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities?

Easy
158

A project has a budget at completion (BAC) of $500,000. After 3 months, the earned value (EV) is $200,000, the actual cost (AC) is $250,000, and the planned value (PV) is $180,000. What is the cost performance index (CPI) and what does it indicate?

Hard
159

A project manager is closing a project. Which TWO activities are typically performed during the project closure phase?

Medium
160

A project manager is leading a project to develop a new mobile application. The project is in the Executing phase. A team member reports that a key feature cannot be completed as specified due to a technical limitation. The project manager needs to evaluate the impact of this issue on the project constraints. Which document should the project manager review first?

Easy
161

A project manager is preparing for the first phase gate review of a new product development effort. The gate requires that predetermined exit criteria be met before the next phase can begin. Which action best demonstrates that the project manager understands the purpose of a phase gate?

Hard
162

A project manager is executing a project when a team member reports that a critical vendor has missed a delivery deadline, threatening the project schedule. Which action should the project manager take FIRST?

Medium
163

A project manager is leading a cross-functional team that is working together for the first time. The team members are polite but hesitant to share ideas. According to Tuckman's stages of group development, which stage is the team currently in?

Easy
164

A project manager identifies a risk that could cause a $50,000 loss with a 20% probability. What is the expected monetary value (EMV) of this risk?

Hard
165

A project manager is planning the installation of a new server that will host a database. The server requires a storage solution that provides high performance and redundancy. The project manager must choose between different RAID levels. Which RAID level should the project manager select to achieve both performance and redundancy?

Easy
166

A project manager is selecting a data center for a new application that requires high availability and disaster recovery. Which type of data center arrangement is most appropriate?

Easy
167

A project manager is developing the communication management plan. Which element should be included to ensure stakeholders receive timely information?

Medium
168

A project manager is reviewing a change request to add a new feature to a software product. The change will increase the project timeline by two weeks and require additional budget. Which of the following should the project manager do first?

Medium
169

In a network diagram using PDM, activity B can start only after activity A has finished. Which dependency type does this represent?

Medium
170

Arrange the phases of the project life cycle in the correct order.

Medium
171

A project manager is assigning stakeholders to quadrants on a power/interest grid. Which stakeholders require the most active management?

Medium
172

During project closure, which three activities should be performed? (Select THREE)

Hard
173

A project manager is preparing a lessons learned document at the end of a marketing campaign project. The sponsor wants to ensure that future projects benefit from the team's experience. Which action should the project manager take to make the lessons learned most useful?

Hard
174

In the stakeholder power/interest grid, stakeholders with high power and low interest should be managed using which strategy?

Easy
175

A server administrator is troubleshooting a failed backup job. The backup software configuration specifies a backup volume by its UUID, but the logs indicate that the specified volume cannot be found. What is the most likely cause of the error?

Medium
176

Which document formally authorizes the project and assigns the project manager?

Easy
177

A project manager needs to compare the planned budget, the actual costs incurred, and the value of work completed to date for a construction project. Which document should the project manager use to obtain this consolidated financial performance view?

Easy
178

During project planning, the project manager is creating a risk register. Which THREE pieces of information are typically included in a risk register? (Select three.)

Medium
179

A project manager has been assigned to deliver a new customer portal. The sponsor wants to know who holds ultimate accountability for the project's success and who can approve changes to the approved budget baseline. Which role should the project manager identify?

Easy
180

A project manager is estimating the cost of a new software development project. She uses the actual cost of a similar past project and adjusts for differences in size and complexity. Which estimation technique is she using?

Medium
181

A project manager is performing schedule compression. The team decides to start a successor activity before its predecessor is fully complete. Which technique are they using, and what is a primary downside?

Hard
182

A project manager is developing a network diagram for a software rollout. Activity D (3 days) can start only after Activity C (2 days) finishes, and Activity E (4 days) can start when Activity C starts. Activities D and E must both finish before Activity F (1 day) begins. What type of dependency exists between Activity C and Activity E?

Medium
183

During project execution, the project manager notices that actual costs are consistently higher than planned. Which process should the project manager use to analyze this variance?

Easy
184

A project manager is leading a project to upgrade the storage area network (SAN) for a hospital's electronic health records (EHR) system. The current SAN is reaching capacity and has performance issues during peak hours. The new SAN must support high availability with synchronous replication between two data centers located 10 km apart. The project budget is tight, and the timeline is aggressive. During a risk assessment, the project manager identifies that the fiber optic cable between the data centers is owned by a third-party provider and has a history of outages. The project sponsor is concerned about meeting the go-live date and asks the project manager to recommend a course of action to mitigate the risk of cable outages affecting the SAN replication. Which of the following is the BEST course of action?

Easy
185

During project planning, the project manager needs to estimate the cost of each work package. Which tool or technique is best suited for this?

Hard
186

Which of the following is NOT a phase in the typical project life cycle?

Easy
187

A project has completed the planning phase and is about to begin execution. However, a key stakeholder raises a concern that a critical requirement is missing. What is the best course of action?

Hard
188

A project manager is leading a construction project. The team identifies a risk that a key supplier may go bankrupt. The project manager decides to purchase insurance to cover potential losses. Which risk response strategy is being used?

Hard
189

A project team is using Jira for an Agile project. Which TWO artefacts are typically managed within Jira for sprint planning and tracking? (Choose two.)

Medium
190

A project has a constraint that a specific software must be used because it is the standard in the organization. The project manager must work within this limitation. What type of constraint is this?

Medium
191

A project manager is analyzing project performance and calculates a cost performance index (CPI) of 0.85 and a schedule performance index (SPI) of 1.10. Which conclusion should the project manager draw from these metrics?

Hard
192

A team uses a tool that clarifies roles by showing who is responsible, accountable, consulted, and informed for each task. Which tool is this?

Medium
193

An organization is deploying a new storage area network (SAN). Which of the following is a key consideration for ensuring high performance?

Easy
194

A project manager is leading a cross-functional team in a matrix organization. The project is experiencing conflicts between team members due to competing priorities from their functional departments. Which THREE techniques should the project manager use to resolve resource conflicts? (Select THREE).

Medium
195

A project manager is using a quantitative analysis technique that runs thousands of iterations of the project schedule to determine the probability of completing the project by a certain date. This technique uses probability distributions for activity durations. Which technique is being described?

Hard
196

A project sponsor proposes increasing the project budget to add a new feature requested by a key stakeholder. What should the project manager do first?

Easy
197

During a project, the project manager receives a change request that would modify the project's scope. According to the integrated change control process, which THREE actions are part of evaluating this change request? (Choose three.)

Medium
198

During a sprint review, the product owner notices that the team completed 30 story points in the previous sprint and 25 in the current sprint. The project manager wants to track the average story points completed per sprint to predict future performance. Which metric should be used?

Medium
199

A project manager is leading a software development project. The team is using an agile approach with iterative cycles. Which project life cycle model best describes this approach?

Hard
200

A project team is working on a software development project. The project manager wants to ensure that all changes to the codebase are reviewed and approved before they are integrated. Which type of tool should be used?

Easy
201

You are managing a network upgrade project for a large corporation. The project involves replacing outdated switches and routers across three data centers. During the execution phase, you discover that one of the key vendors has shipped the wrong model of switches for Data Center B. The correct switches have a lead time of four weeks, which will delay the project by three weeks. The project sponsor is pressuring you to meet the original deadline. The project budget has some contingency reserves. What should you do?

Medium
202

A project manager is leading a team that is implementing a new VoIP system across multiple offices. The project manager needs to ensure that the network infrastructure can support the real-time voice traffic. Which of the following are critical network considerations for VoIP deployment? (Choose two.)

Medium
203

Which THREE are common types of project management documentation? (Choose three.)

Medium
204

In which project management process group is the project charter formally approved, giving the project manager authority to allocate resources?

Medium
205

During which project phase is the project charter created?

Easy
206

A project manager is closing a project that delivered a new customer relationship management system. Which THREE activities are part of the closing process? (Select THREE).

Hard
207

In a precedence diagramming method (PDM) network, a successor activity cannot start until its predecessor activity has started. Which type of dependency does this represent?

Medium
208

A project manager needs to determine the critical path of a project. Which statement about the critical path is true?

Easy
209

A project manager notices that actual costs are significantly higher than planned for the first two months of a six-month project. The project is critical to the organization, and the sponsor is concerned about the budget. What is the BEST course of action for the project manager?

Hard
210

A project manager is building the team for a data-migration project. The sponsor wants to know how the PM will acquire personnel, how team members will be trained and managed, how performance will be appraised, and how the team will eventually be released. In which project management plan component should the PM document these items?

Medium
211

Which project scheduling tool shows activities as bars on a timeline, including dependencies and milestones?

Easy
212

A project manager needs to document the roles and responsibilities of team members for a new project. Which document should the project manager create?

Easy
213

A steering committee is reviewing project performance. Which of the following is a key responsibility of the steering committee?

Hard
214

A project manager is creating a document that identifies all project stakeholders and their interests, influence, and expectations regarding the project. This document is the:

Medium
215

A project is in the planning phase. The project manager is working with the team to break down the project deliverables into smaller, more manageable components. Which process is being performed?

Easy
216

A project is in the monitoring and controlling phase. The project manager is reviewing the earned value metrics: EV = $50,000, PV = $60,000, AC = $55,000. Which of the following statements is correct?

Hard
217

Which TWO of the following are characteristics of a project? (Select TWO).

Medium
218

A project has earned value (EV) of $50,000, planned value (PV) of $60,000, and actual cost (AC) of $55,000. What is the cost performance index (CPI)?

Hard
219

During project execution, the team uses a shared online workspace to collaborate on documents. This is an example of which type of tool?

Easy
220

A project manager is reviewing the risk register and sees that a high-impact risk has a probability of 0.3 and an impact of $50,000. The team implements a response that reduces the probability to 0.1 and the impact remains $50,000. The response cost is $5,000. What is the net expected monetary value (EMV) of implementing the response?

Hard
221

During the planning phase, a team member estimates a task duration as 5-7 days based on a similar past project. Which estimating technique is being used?

Medium
222

A project manager is developing the project schedule and needs to determine the critical path. The network diagram shows: Task A (3 days) and Task B (5 days) start concurrently. Task C (4 days) depends on both A and B. Task D (2 days) depends on C. Task E (6 days) depends on A only and runs in parallel with C and D. What is the duration of the critical path?

Hard
223

Match each communication method to its description.

Medium
224

A project manager uses a tool that shows the sequence of project activities and their dependencies. Which tool is this?

Easy
225

A project manager is evaluating a project proposal. Which TWO of the following criteria are most important for deciding whether to approve the project?

Easy
226

In a network diagram, Activity A has a duration of 5 days, Activity B has 3 days, and Activity C has 4 days. Activity A and B can start simultaneously, but Activity C cannot start until both A and B are complete. What is the critical path duration?

Hard
227

A project manager is planning the implementation of a new network monitoring system across multiple data centers. The project team must ensure that the monitoring traffic does not interfere with production workloads and that the solution can scale as new data centers are added. Which two actions should the project manager take to address these requirements? (Choose two.)

Hard
228

A project manager is preparing a stakeholder engagement approach for a project that will affect several departments. One department head has high influence over funding decisions but currently shows little interest in the project and has not responded to meeting invitations. According to a power/interest classification, how should the project manager treat this stakeholder?

Hard
229

A project manager is overseeing a data center migration. The new infrastructure must support high availability and scalability. Which TWO components are essential for achieving these goals?

Easy
230

During project execution, a key stakeholder requests a new feature that was not included in the scope baseline. What should the project manager do first?

Easy
231

A project manager is assigned to a new project that has a tight deadline. The team members are from different departments and have competing priorities. Which project management process group is the project manager likely to spend the MOST time in during the initial phase of the project?

Easy
232

During project execution, a customer requests a new feature that was not in the original scope. The project manager receives a change request. What is the NEXT step the project manager should take?

Medium
233

A project manager has identified a risk that could cause a $50,000 loss with a 20% probability. What is the Expected Monetary Value (EMV) of this risk?

Easy
234

During a sprint review, the product owner notices that the team has completed 30 story points, but the burndown chart shows an upward trend. What is the most likely cause?

Medium
235

A project manager is using the Delphi technique for risk identification. Which of the following best describes this technique?

Medium
236

A project is in the monitoring and controlling phase. The project manager notices that the cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 1.2. What does this indicate about the project?

Hard
237

A project team is using an Agile approach. During the sprint review, the product owner decides to reprioritize the backlog, moving a high-effort story to the next sprint. What is the primary benefit of this flexibility?

Hard
238

A project has a budget at completion (BAC) of $200,000. After 3 months, the earned value (EV) is $80,000, and the actual cost (AC) is $100,000. What is the estimate at completion (EAC) assuming the cost performance index (CPI) will remain the same for the remainder of the project?

Hard
239

A project manager is closing a project that was terminated early because the business case was no longer viable. The sponsor asks what must still be completed before the project can be formally closed. Which of the following should the project manager do?

Medium
240

A project manager needs to ensure that the IT infrastructure project complies with industry standards for data security. Which document should the project team reference?

Medium
241

A project manager is leading a project in an organization that uses a hybrid methodology. The team follows a predictive approach for requirements gathering and design, but uses iterative sprints for development. Which life cycle best describes this project?

Hard
242

A project team is adding extra features to a deliverable that were not requested by the customer, in an effort to improve the product. This practice is known as:

Easy
243

A project manager is building the team for a regulatory compliance project with a fixed external deadline. The organization uses a strong matrix structure. The project manager needs to secure a senior security architect who is also in high demand on other initiatives. Which action is MOST likely to obtain this resource commitment?

Medium
244

A project to upgrade network switches. Which TWO factors should the project manager consider when selecting switches? (Choose two.)

Easy
245

A software development team uses short, time-boxed iterations, daily stand-up meetings, and a prioritized backlog. Requirements are expected to evolve throughout the project. Which project management methodology is being used?

Medium
246

A project manager has just received formal sign-off on the project charter from the sponsor. The project involves a new CRM system for a mid-sized company. What is the most appropriate immediate next step in the project life cycle?

Medium
247

A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?

Medium
248

During project selection, an organization evaluates multiple projects using financial methods. Which THREE of the following are commonly used financial project selection methods? (Select THREE).

Hard
249

A project manager is planning a system migration with a fixed regulatory deadline. The sponsor asks how the team will know whether the project remains on track to finish by that date without waiting for the final status report. Which planning artifact should the project manager produce to answer this?

Medium
250

During project execution, a vendor is hired to provide specialized services. The contract is structured so that the vendor is paid for all allowable costs plus a fixed fee. Which type of contract is this?

Hard
251

A project manager is initiating a new project and needs to identify the key stakeholders. Which document typically provides the initial list of stakeholders and their roles?

Easy
252

Which TWO of the following are primary responsibilities of the project manager? (Select two.)

Medium
253

Which TWO of the following are typically included as phases in a project life cycle according to the Project Management Institute (PMI)?

Easy
254

A project manager is creating a document that formally authorizes the project and assigns the project manager. This document includes the business case, high-level scope, and budget constraints. What is this document called?

Easy
255

During a network upgrade project, a technician accidentally disconnects a critical switch, causing an outage. The project manager needs to update the issue log and communicate with stakeholders. Which communication method is most appropriate for notifying senior management of the outage?

Medium
256

A project manager is tracking issues and their resolution status. Which document should the manager use to record and monitor these issues?

Medium
257

You are the project manager for a cloud migration project at a mid-sized company. The project team consists of internal IT staff and a third-party vendor responsible for data transfer. During a weekly status meeting, you discover that the vendor has been using an unauthorized tool to accelerate data transfer, which violates the security policy outlined in the project charter. The vendor claims the tool is necessary to meet the aggressive timeline. The project sponsor is concerned about security but also about schedule delays. You need to take the most appropriate action to address this issue while maintaining project control. Which action should you take?

Medium
258

Which TWO tools are commonly used for project scheduling and displaying task dependencies? (Select TWO)

Medium
259

A project manager is managing an IT infrastructure upgrade project. The project plan includes a detailed schedule, resource assignments, and a risk register. The project manager uses a spreadsheet to track risks, but the spreadsheet has become large and difficult to maintain. Team members are not consistently updating risk information, and some risks have been ignored. The project manager wants to adopt a more effective risk management tool that encourages regular updates and provides risk scoring. Which tool should the project manager implement?

Hard
260

A project manager is analyzing the impact of a proposed change on the project's schedule, cost, and quality. After the analysis, the change request is reviewed by a group of stakeholders who decide whether to approve it. This group is known as the:

Medium
261

A project manager is using schedule compression techniques to meet a deadline. Which THREE statements about fast-tracking and crashing are correct?

Hard
262

A project sponsor asks for a report showing the planned vs. actual cost performance. Which project document contains the necessary data to create this report?

Medium
263

During project execution, a stakeholder requests additional features that were not in the original scope. The project manager identifies this as scope creep. What is the best action for the project manager to take?

Medium
264

Based on the change request log exhibit, what should the project manager do next regarding the change requests?

Easy
265

A project manager is reviewing a control chart and notices several data points outside the upper control limit (UCL). Which type of variation do these points indicate?

Hard
266

A project manager reviews the following risk register: R1 (Vendor delay) has a probability of 0.8 and an impact of 0.6; R2 (Resource shortage) has a probability of 0.6 and an impact of 0.5; R3 (Technical failure) has a probability of 0.6 and an impact of 0.6; R4 (Scope creep) has a probability of 0.7 and an impact of 0.5. Which risk should the project manager prioritize for active monitoring and response?

Hard
267

A project manager is leading a project to implement a new enterprise resource planning (ERP) system. The project is in the Closing phase. The project manager has verified that all deliverables have been accepted by the customer and all invoices have been paid. However, the project manager realizes that the lessons learned repository has not been updated. Which of the following should the project manager do?

Hard
268

A project manager is leading an infrastructure refresh that introduces a new enterprise resource planning (ERP) system. The project sponsor asks which document formally authorizes the project and gives the project manager the authority to apply organizational resources to project activities. Which document should the project manager reference?

Easy
269

Which THREE documents are typically part of the project management plan?

Medium
270

A project team is distributed across three time zones. The project manager notices that communication breakdowns are causing delays. Which communication method should the project manager implement to improve collaboration and ensure information is stored for future reference?

Medium
271

A project manager is moving a project from Planning into Executing. The sponsor asks which activities formally mark the transition and enable the team to begin producing deliverables. Which TWO activities should the project manager identify? (Choose two.)

Hard
272

A project manager wants to analyze the project schedule to identify the longest path of dependent tasks. Which technique should be used?

Hard
273

A project team is identifying risks using a technique that involves a group of experts answering questionnaires anonymously to avoid bias. Which risk identification technique is being used?

Medium
274

A project manager is assigned to a project with a fixed deadline, a fixed budget, and a scope that cannot be reduced. During planning, the team discovers that meeting all three constraints simultaneously is not feasible with current resources. What is the MOST appropriate action for the project manager to take?

Medium
275

A project manager is closing out a project that was terminated early by the sponsor due to shifting business priorities. The deliverables were only partially completed, and several contracts remain open. What should the project manager do FIRST?

Medium
276

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $120,000, and the actual cost (AC) is $150,000. What is the estimate to complete (ETC) assuming the project will continue to perform at the same cost efficiency?

Hard
277

In a network diagram, if Activity B cannot start until Activity A is complete, what type of dependency is this?

Medium
278

A project manager is performing quality control on a software development project. The team has completed coding and is now testing the software. The project manager wants to identify the root cause of defects that are being found during testing. Which TWO tools or techniques should the project manager use? (Choose two.)

Hard
279

A project has three activities: Activity A (5 days), Activity B (7 days), Activity C (4 days). Activity B depends on A. Activity C depends on B. What is the total float for Activity B?

Hard
280

A project manager is leading an infrastructure modernization effort that will take 14 months. The organization has a limited capital budget, but the project sponsor has secured approval to deliver a small, working subset of the highest-priority network upgrades within the first four months. The remaining upgrades will be delivered in later releases based on available funding. Which project life cycle best fits this approach?

Medium
281

A project manager is preparing for the project closure phase. Which three activities should the project manager perform? (Select THREE).

Hard
282

A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What does this indicate?

Hard
283

A project manager is evaluating whether to proceed with a project that has a net present value (NPV) of -$10,000, an internal rate of return (IRR) of 4%, and a payback period of 3 years. The company's required rate of return is 6%. What should the project manager recommend?

Hard
284

Which TWO of the following are examples of project constraints? (Select TWO).

Medium
285

A project to migrate on-premises email to a cloud-based service is nearing completion. After the final cutover, some users report that emails sent to certain domains are not being delivered. The project team checks the mail servers and finds no errors. The project manager reviews the DNS records and discovers that the MX records were not updated to point to the new service. What should the team do first?

Medium
286

A project sponsor asks the project manager to accelerate the schedule. Which TWO schedule compression techniques could the project manager consider?

Hard
287

Which risk response strategy involves taking action to reduce the probability or impact of a risk?

Easy
288

A project manager is managing an agile project. The team uses iterative development and daily stand-up meetings. Which of the following is a key principle of agile project management?

Easy
289

A project manager is setting up a shared repository for project artifacts. The PM wants to ensure that team members can find the latest approved version of each document and that changes are controlled. Which TWO practices should the PM implement? (Choose two.)

Medium
290

Which TWO of the following are risk identification techniques commonly used in project management? (Choose two.)

Easy
291

During the planning phase, the project manager wants to define the project scope in detail. Which document should be created?

Easy
292

A project manager is preparing the team charter for a newly formed project team that includes members from three departments and two external partners. The organization has a history of unresolved interpersonal friction on cross-departmental efforts. Which action BEST reflects the purpose of a team charter in this situation?

Easy
293

A project manager is leading a project to develop a new mobile application. The project is in the Planning phase. The project manager is identifying and documenting the high-level risks that could affect the project. Which two of the following should the project manager include in the risk register? (Choose two.)

Hard
294

Who is responsible for providing the project with resources and removing obstacles that are beyond the project manager's control?

Easy
295

During project closing, which activity is performed to formally obtain acceptance of the project deliverables from the sponsor or customer?

Medium
296

A project manager needs to assign tasks to team members. Which document provides the detailed breakdown of work packages?

Easy
297

A project manager is developing the project charter for a new payroll system. The sponsor asks which document will formally authorize the project and give the project manager authority to apply organizational resources. Which document should the project manager reference?

Easy
298

A project manager is reviewing the project charter for a new data migration project. The charter authorizes the project and names the project manager, but the project manager notices that the success criteria and high-level budget are vague. The sponsor is eager to start work immediately. What should the project manager do before proceeding with detailed planning?

Medium
299

Which TWO of the following are outputs of the project initiation phase?

Medium
300

A project is behind schedule. The project manager decides to start the next phase before the previous phase is fully complete, overlapping activities. This technique is known as:

Hard
301

During project planning, the project manager decomposes the project scope into smaller, more manageable components. What is the resulting document called?

Medium
302

A project manager is leading a software development project in a matrix organization. The project manager shares resources with functional managers. In this type of organizational structure, which of the following BEST describes the project manager's authority?

Medium
303

A project manager is closing a project. Which TWO activities should be performed during project closure? (Select two.)

Medium
304

Which THREE of the following are characteristics of a project as defined by PMI?

Hard
305

A project manager is working on a construction project and needs to calculate the total float for a non-critical path activity. The activity has an early start of day 5, late start of day 10, early finish of day 15, and late finish of day 20. What is the total float?

Hard
306

A project manager notices that the project is behind schedule. The planned value (PV) is $50,000, earned value (EV) is $40,000, and actual cost (AC) is $45,000. What is the schedule performance index (SPI) and what does it indicate?

Hard
307

A project manager is evaluating potential IT infrastructure projects. Which two project selection methods consider financial return? (Choose two.)

Easy
308

A project manager has been authorized to lead a new customer-portal replacement effort. Before any detailed scheduling begins, the PM needs to formally document the measurable outcomes the portal must achieve, the boundaries of what will and will not be delivered, and the acceptance criteria the customer will use. Which document should the project manager produce FIRST to capture these items?

Easy
309

A project manager is two weeks into a six-week infrastructure upgrade when the data center landlord announces mandatory electrical maintenance that will shut down power to the racks for 48 hours during week four. The PM has float of only three days on the critical path. Which document should the PM update to record this external constraint and its potential effect on the schedule?

Medium
310

A project manager is overseeing the implementation of a new customer relationship management (CRM) system. The vendor requires access to the company's internal network to install and configure the software. Which of the following is the BEST practice to ensure security while allowing vendor access?

Hard
311

Which document formally authorizes a project and provides the project manager with the authority to apply organizational resources?

Easy
312

Order the steps for effective stakeholder communication.

Medium
313

During the planning phase, which three documents are typically created? (Select THREE.)

Medium
314

An organization is launching a project to design a brand-new autonomous delivery vehicle. The technology is unproven, requirements will emerge through prototyping, and the customer expects frequent demonstrations. Which approach should the project manager recommend?

Medium
315

A project manager is leading a small software development project and wants to create a document that lists all project stakeholders, their roles, and their contact information. Which document should the project manager create?

Easy
316

A project team is using planning poker to estimate user stories. What is the purpose of this technique?

Medium
317

A project manager is reviewing the procurement process. Which document is used to invite vendors to submit a proposal for a project?

Hard
318

A project manager is leading a project to deploy a new customer relationship management (CRM) system for a sales team of 50 users. The vendor offers both an on-premises and a cloud-based option. The project sponsor is concerned about the total cost of ownership and wants to avoid large upfront capital expenditures. Which cloud service model should the project manager recommend?

Easy
319

A project manager is developing the risk management plan. Which of the following is the primary purpose of this plan?

Hard
320

During the planning phase, a team identifies a risk that could cause a 10% increase in project cost if it occurs, with a 20% probability. What is the expected monetary value (EMV) of this risk?

Hard
321

A project team is decomposing the project scope into work packages. Which of the following best describes the purpose of a Work Breakdown Structure (WBS)?

Hard
322

A project is 40% complete. The earned value (EV) is $80,000, planned value (PV) is $100,000, and actual cost (AC) is $90,000. What is the cost performance index (CPI) and schedule performance index (SPI)?

Hard
323

During project execution, a key stakeholder requests a change that will affect the project scope. The project manager assesses the impact and finds it will increase costs by 15% and delay the schedule by two weeks. What is the FIRST action the project manager should take?

Medium
324

A project manager is assigned to a new project. The project charter has been approved. Which of the following is the NEXT step?

Easy
325

A company is initiating a project to develop a new mobile application. The project manager needs to secure approval and funding. Which project role is primarily responsible for providing the necessary resources and championing the project?

Easy
326

A project manager is calculating the estimate to complete (ETC) for a task using earned value management. The task has a budget at completion (BAC) of $10,000, earned value (EV) of $4,000, and actual cost (AC) of $5,000. Assuming the work will continue at the planned rate, what is the ETC?

Medium
327

In which project life cycle phase are project risks identified and a risk management plan created?

Medium
328

Which document formally defines the deliverables, acceptance criteria, exclusions, assumptions, and constraints of a project?

Easy
329

A project sponsor wants to formally close a project. Which of the following documents should the project manager prepare to obtain sign-off that the project is complete?

Easy
330

During a sprint review, the team notes that the remaining work is not decreasing as expected. Which agile artefact would best help visualize the trend of remaining work over the sprint duration?

Medium
331

A project manager is using an issue log to track problems. During a weekly status meeting, a team member reports a new issue that has already caused a one-day delay. The project manager adds it to the issue log. What is the NEXT step?

Hard
332

A project manager is closing a project. Which TWO activities are typically performed during the closing phase?

Medium
333

A project manager needs to communicate project progress to stakeholders who have low power and high interest. Which of the following is the most appropriate communication method?

Medium
334

A project manager is reviewing the project constraints. The triple constraint traditionally includes scope, time, and cost. However, quality is also often considered a constraint. Which TWO of the following are part of the triple constraint? (Select TWO).

Medium
335

Refer to the exhibit. A project manager is reviewing the security configuration of a project's cloud storage. Which of the following is the MOST significant security risk?

Medium
336

A project manager at a marketing firm is using Microsoft Project to manage a campaign launch. The project has 15 tasks with several dependencies, including finish-to-start and start-to-start. Team members update their task progress daily. After a week, the project manager notices that some tasks are not reflecting updated finish dates even though dependencies are marked as complete. For example, Task 4 (Design finalization) has a finish-to-start dependency on Task 3 (Concept approval), which was completed three days ago, but Task 4's start date remains unchanged, causing the entire schedule to appear delayed. The project manager has verified that all task links are correctly set in the software. What should the project manager do first?

Easy
337

A project team is creating a WBS. They ensure that every deliverable and work package is included and that the sum of the work at the lower levels equals the total work at the higher levels. Which principle are they applying?

Easy
338

A project manager is leading a project that uses a hybrid methodology. The project has a fixed deadline but the requirements are expected to evolve. Which approach best describes how the PM should handle the project?

Hard
339

A project manager is leading a hybrid project that combines waterfall planning with iterative execution. Which of the following is a key challenge in managing such a project?

Hard
340

A project manager is planning a new data center build. The organization requires high availability and low latency for critical applications. Which infrastructure component should be prioritized to meet these requirements?

Easy
341

A project manager is using a predictive approach for a regulatory compliance project. Midway through execution, a newly published regulation invalidates a design assumption documented in the project management plan. The project manager wants to handle this in a way that preserves traceability and keeps the baseline accurate. What should the project manager do FIRST?

Hard
342

A project manager is evaluating the cost performance of a project. Which TWO earned value metrics should be used to determine if the project is over budget?

Hard
343

During the Planning phase of a construction project, the project manager learns that a required environmental permit will take twelve weeks to obtain, while the site preparation activity is scheduled to start in four weeks. The permit is mandatory before site preparation can begin. What should the project manager do FIRST?

Medium
344

Which TWO of the following are key characteristics of a project? (Select TWO).

Medium
345

A project manager needs to determine the project's success criteria before the project is initiated. Which document should contain these criteria?

Medium
346

A project manager documents a change request and updates the change log. Which step of integrated change control is being performed?

Medium
347

A project manager is performing quantitative risk analysis. Which THREE of the following techniques are commonly used? (Select three.)

Hard
348

A project manager is leading a software development project. The team is consistently delivering work late, causing schedule delays. The project manager suspects the initial duration estimates were too optimistic. What is the best action to improve future estimation accuracy?

Medium
349

A project team member consistently misses deadlines and produces low-quality work. The project manager wants to address the issue without demotivating the team member. What is the appropriate first step?

Medium
350

A project manager uses a quantitative risk analysis tool that runs thousands of simulations to determine the probability of completing the project by a certain date. Which technique is being used?

Hard
351

A marketing project manager is responsible for launching a new product. The project manager has created a project charter, a stakeholder register, and a high-level schedule. The sponsor has approved the charter. The project manager needs to develop a detailed project plan. According to best practices, what should the project manager do next?

Easy
352

A project manager is leading a small software development project. The team is co-located and has daily stand-up meetings. The project sponsor requests a weekly status report. Which communication method is the project manager using for the daily stand-ups?

Easy
353

A project is in the executing phase. The project manager notices that the actual cost is consistently higher than planned, and the schedule is behind. After analyzing the situation, the project manager decides to fast-track some tasks. What is the primary impact of fast-tracking?

Medium
354

Match each risk response strategy to its description.

Medium
355

Refer to the exhibit. Based on the risk register, which risk should receive the highest priority for response?

Medium
356

A project team is identifying risks using a SWOT analysis. Which THREE of the following are categories examined in a SWOT analysis? (Select THREE).

Medium
357

A project is experiencing scope creep because stakeholders are requesting additional features without formal change control. What is the best course of action for the project manager to prevent this?

Medium
358

During project execution, a stakeholder requests a new feature that was not originally included in the scope. The project manager records the request and evaluates its impact on the triple constraint. What should the project manager do next?

Easy
359

A project manager is leading the implementation of a new enterprise resource planning (ERP) system that will be hosted in a private cloud. The project sponsor wants to ensure that the infrastructure meets the following requirements: high availability, data redundancy, and the ability to recover from a site failure. Which two components should the project manager include in the project plan? (Choose two.)

Hard
360

A project manager identifies a risk that a critical vendor may not deliver on time. The project manager decides to document the risk and monitor it closely, but does not take any proactive action. This is an example of which risk response?

Hard
361

A project manager is analyzing the project schedule and notes that two activities, design and development, are currently scheduled sequentially. To accelerate the schedule, the project manager considers overlapping the activities. Which TWO of the following are correct regarding this approach?

Medium
362

A project manager is leading a construction project that follows a predictive life cycle. The sponsor asks for a document that formally authorizes the project and gives the project manager authority to apply organizational resources. Which document should the project manager provide?

Easy
363

During which stage of Tuckman's team development model do team members begin to resolve conflicts and establish norms?

Medium
364

A project manager is monitoring project performance. Which TWO earned value metrics are used to assess cost efficiency?

Medium
365

An organization is preparing to launch a project that will replace its aging payroll system. Executive leadership has assigned a sponsor, and the sponsor has asked the project manager to produce the document that formally authorizes the project and gives the project manager authority to apply organizational resources to project activities. Which document should the project manager produce?

Easy
366

Which TWO of the following are typical activities in the Closing phase of a project?

Hard
367

A project is implementing a new backup solution. The current infrastructure uses tape backups, and the new solution will use cloud storage. During planning, the team identifies that the internet bandwidth is insufficient for initial seed data transfer. What is the best approach to mitigate this risk?

Medium
368

A project manager is creating a risk register for a construction project. Which TWO fields are essential for calculating a risk score?

Hard
369

A project manager is midway through a data center migration when the sponsor announces that the organization will divest the business unit that owns the legacy systems being migrated. The divestiture removes the business need for half of the migration scope and shifts the completion deadline forward by two months. The sponsor asks the project manager to recommend the appropriate course of action. What should the project manager do FIRST?

Hard
370

Which of the following is a key component of a project scope statement?

Easy
371

A project manager is preparing a procurement statement of work (SOW) for an external vendor. The SOW must clearly define the deliverables, acceptance criteria, and performance standards. Which document should the project manager reference to ensure the SOW aligns with the project's overall objectives and constraints?

Medium
372

Which TWO of the following are effective techniques for managing stakeholder expectations?

Hard
373

A project manager is developing a project schedule for a construction project. The team has identified all activities and their dependencies. The project manager needs to determine the longest path through the network diagram to identify the shortest possible project duration. Which technique should the project manager use?

Medium
374

A project manager is assigned to a project that has already started without a formal project charter. What should the project manager do first?

Medium
375

During project execution, a project manager notices that team members are spending excessive time on non-essential tasks, and the project is falling behind schedule. Which tool should the project manager use first to identify the root cause of the delays?

Hard
376

Match each procurement document to its purpose.

Medium
377

A project manager is using a predictive life cycle for a regulatory compliance project with fixed milestones imposed by law. The sponsor now wants to introduce iterative development so requirements can be refined as regulations are clarified. Which project life cycle characteristic best supports combining these needs?

Medium
378

A project is in the Executing phase. The project manager needs to ensure effective communication with stakeholders. Which THREE elements should be included in the communications management plan? (Select THREE.)

Hard
379

A project manager is leading a brainstorming session to identify potential risks. The team uses a technique that encourages free thinking and avoids criticism. Which risk identification technique is being used?

Medium
380

A project manager is leading a project using a predictive life cycle. During the Executing phase, a stakeholder requests a significant change to the project scope. The project manager follows the change control process. After the change control board (CCB) approves the change, what should the project manager do NEXT?

Hard
381

A project manager is estimating activity durations for a construction project. She uses a parametric estimate based on 100 square meters per day. If the total area is 500 square meters, the estimated duration is 5 days. Which THREE statements are true about parametric estimation?

Medium
382

A project manager is leading a project with a tight budget. The team has completed all required features, but there is some remaining budget. The sponsor suggests adding a few extra features. What are TWO potential issues the project manager should consider before approving? (Choose TWO.)

Hard
383

A project to implement a new CRM system is behind schedule due to unexpected technical issues. The project manager decides to fast-track the project by overlapping phases. Which risk is most likely to occur?

Hard
384

Refer to the exhibit. What is the cost variance (CV) and schedule variance (SV)?

Medium
385

A project manager receives a change request to add a new feature to the project's software. After evaluating the impact on the triple constraint, they submit it to the change control board (CCB). The CCB approves the change. What is the project manager's next step?

Medium
386

A project manager is assigned to a new initiative in a matrix organization with a weak matrix structure. The project manager needs to obtain resources from functional departments. The functional managers have authority over their team members' assignments and priorities. What is the most likely challenge the project manager will face in this environment?

Hard
387

During project initiation, a project manager needs to identify high-level risks. Which document should the project manager reference?

Easy
388

A project manager is explaining the characteristics of a project to a new team member. Which TWO of the following are typical characteristics of a project?

Easy
389

In a risk register, the risk score is typically calculated by multiplying which two fields?

Medium
390

During which project phase is the project charter created and the project manager officially assigned?

Easy
391

A project manager needs to show the sequence of project activities and their dependencies to identify the critical path. Which tool should they use?

Medium
392

Which type of contract places the greatest cost risk on the seller?

Medium
393

A project manager is using a Kanban board to visualize workflow. Which metric should the team track to measure process efficiency?

Easy
394

A project manager needs to track task dependencies and identify the critical path. Which tool should they use?

Easy
395

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?

Hard
396

A project manager is leading a project using an agile approach and wants a visual tool that shows the amount of work remaining versus time, helping the team predict whether it will complete the backlog by the target date. Which tool should the project manager use?

Medium
397

A project team is using a Kanban board. A work item has been in the 'In Progress' column for two weeks with no updates. What is the best action for the project manager?

Medium
398

An IT project manager is using a project management software tool to track progress. The tool shows that the project's SPI is 0.8 and CPI is 1.1. Which conclusion can the project manager draw about the project's performance?

Hard
399

A project manager is evaluating change requests. According to the integrated change control process, which THREE elements should be assessed for impact before a change is approved?

Hard
400

A project manager is reviewing the project selection methods for a new initiative. Which TWO of the following are financial project selection methods? (Choose two.)

Medium
401

A project manager is reviewing the project management plan before a phase gate review. The sponsor wants evidence that the plan addresses how changes will be controlled and how the project will be kept aligned with the approved baseline. Which TWO components should the project manager confirm are included? (Choose two.)

Hard
402

Which of the following describes scope creep?

Easy
403

A project manager is reviewing the project budget and notices that the actual cost is significantly higher than planned. The project manager wants to identify which specific work packages are causing the overrun. Which report or tool should be used?

Hard
404

During sprint planning, the team uses a technique where each member privately selects a card representing a number of story points for a user story. After revealing, they discuss discrepancies. This technique is known as:

Medium
405

A project team is distributed across three time zones. The project manager needs to collaborate on project documents in real-time and maintain a single source of truth. The documents include the project plan, requirements, and design specifications. Some team members have been emailing different versions, causing confusion. The project manager wants to adopt a tool that allows simultaneous editing, version history, and access control. Which tool should the project manager implement?

Easy
406

A project is in the Closing phase. The project manager has obtained final acceptance of the product from the customer and has transferred the product to operations. Which activity should be performed next as part of closing the project?

Hard
407

A project manager is leading a software localization project spanning three countries. The schedule baseline was approved with a duration of nine months, but the vendor delivering translated content has just reported a four-week delay caused by a shortage of certified linguists. The project manager has no authority to approve additional funds and must decide how to proceed. Which of the following actions is the MOST appropriate first step?

Medium
408

A project manager is leading a distributed team across three time zones. The project has a fixed deadline and high uncertainty in requirements. The sponsor wants frequent demonstrations of working product. Which project life cycle is MOST appropriate?

Hard
409

A project manager is leading an IT infrastructure upgrade project that follows a phased life cycle. During the planning phase, the project team is divided on the estimation approach for the migration tasks. Some members insist on using expert judgment, while others prefer parametric estimating based on historical data from similar projects. The project manager needs to decide on a method to ensure accurate estimates and team consensus. What should the project manager do?

Medium
410

A project manager needs to identify stakeholders for a new project. Which document should the project manager review first to understand the project's high-level stakeholders?

Easy
411

A company is migrating from on-premise email to a cloud-based solution. The vendor changes the migration tool mid-project. Which project management document should be updated to track the impact on requirements?

Medium
412

A project manager is leading a multinational project with teams in the US, India, and Brazil. The project manager uses a project management tool that includes a dashboard for tracking milestones, tasks, and risks. The tool also has a document repository. During a virtual meeting, the project manager notices that the dashboard shows outdated data because team members are not updating task progress regularly. The project manager needs to improve real-time visibility and ensure accurate reporting. Which action should the project manager take?

Hard
413

Which TWO tools are commonly used for schedule management? (Select TWO.)

Easy
414

A project manager is estimating the duration of a task that has never been done before. The team provides three estimates: optimistic (4 days), most likely (7 days), and pessimistic (16 days). Using the PERT three-point estimate formula, what is the expected duration?

Easy
415

Which tool shows the hierarchical breakdown of work to be performed by the project team?

Easy
416

Which of the following is an example of a risk response strategy to avoid a risk?

Easy
417

During project planning, the team identifies that a key developer is only available 50% of the time. This is an example of which type of constraint?

Easy
418

Which document formally authorizes the project and identifies the project manager?

Easy
419

Which THREE of the following are key components of a project management plan?

Easy
420

Refer to the exhibit. Based on the risk register, which risk has the highest risk score?

Easy
421

Which THREE of the following are key elements of a user story? (Select THREE.)

Medium
422

During the monitoring and controlling phase, a project manager receives a status report indicating the CPI is 0.8 and SPI is 0.9. Which action should the project manager take next?

Medium
423

Which TWO items are typically included in a project closure report?

Hard
424

A project manager needs to communicate project status to stakeholders. Which TWO tools are suitable for this purpose? (Choose two.)

Hard
425

Which THREE of the following are examples of project constraints?

Medium
426

A project manager is documenting the specific actions that will be taken to manage and control risks throughout the project. Which document is this?

Easy
427

During which project phase is the project charter created and the project manager formally assigned?

Easy
428

During a project audit, the project manager discovers that several change requests were implemented without proper documentation. The project team used a verbal approval process, and changes were made directly to project documents without updating the change log. The project manager needs to establish a formal change control process and choose appropriate tools to track changes. The tools must support submission, review, approval, and implementation tracking of change requests. Which combination of tools should the project manager implement?

Medium
429

A project manager needs to communicate the project schedule to senior management, highlighting only key events such as the start and end of phases and major deliverables. Which type of chart is most appropriate?

Medium
430

A project manager is overseeing the deployment of a new server infrastructure that includes both physical and virtual servers. The project requires that the new servers be integrated into the existing monitoring system. Which protocol should the project manager ensure is enabled to allow the monitoring system to collect performance metrics from both physical and virtual servers?

Hard
431

A project manager needs to track the status of every project document, including who wrote it, when it was last revised, and who has approved it. Which tool is most appropriate for maintaining this information?

Easy
432

A project manager is reviewing the lessons learned from a previous project. Which TWO documents are commonly used to capture lessons learned? (Choose two.)

Hard
433

A project manager is selecting a project using financial methods. Which THREE of the following are valid project selection methods? (Select THREE).

Hard
434

Which document decomposes project deliverables into smaller, more manageable components?

Easy
435

A project manager is preparing the stakeholder engagement approach for a hospital construction project. The regulatory authority has high interest and high influence, and can halt the project if permits are delayed. The project manager needs to keep this stakeholder satisfied. Which classification and engagement level is MOST appropriate?

Medium
436

Which of the following is an example of gold plating?

Medium
437

A project manager is managing a project in a functional organization. Due to resource constraints, the functional manager often reassigns team members to other tasks. What is the MOST significant challenge the project manager will face?

Hard
438

A project manager is using a tool that plots risks based on their probability of occurrence and potential impact. What is this tool?

Hard
439

Which THREE of the following are typically included in a project management plan? (Select THREE.)

Hard
440

A project manager is creating documents for procurement. Which TWO documents are typically used in procurement processes? (Select two.)

Medium
441

A project to develop a mobile app is in the executing phase. The project manager uses a Kanban board to track tasks. The team is self-organizing and works in short iterations. The customer is actively involved and provides feedback frequently. Which THREE statements are true about this project?

Hard
442

A project has a budget at completion (BAC) of $200,000. After five months, the earned value (EV) is $90,000 and the actual cost (AC) is $100,000. The project manager needs to calculate the estimate at completion (EAC) assuming current cost performance will continue. What is the EAC?

Hard
443

A project manager learns that a key supplier will be three weeks late delivering a hardware component, which threatens the critical path. The PM has already asked the supplier to expedite at additional cost and has examined whether the component can be substituted. Which process is the project manager performing?

Medium
444

A project manager is leading a project to implement a new customer relationship management (CRM) system. The project requires extensive documentation, including business requirements, technical specifications, test plans, and user manuals. The team is using a shared repository but is struggling with document organization and version control. Several documents have outdated information, and team members are unsure which version is current. The project manager decides to implement a document management process. Which approach should the project manager adopt?

Medium
445

A project has a dependency that requires the foundation to be poured before the walls can be erected. This is an example of which type of dependency?

Easy
446

During which project phase is the project charter typically created and approved?

Easy
447

A project manager is assigned to a new software development project. The requirements are well understood and unlikely to change. Which project management methodology is most appropriate for this project?

Medium
448

A project manager learns that a key supplier will deliver a critical component three weeks late because of a raw material shortage at the supplier's factory. The project manager immediately notifies the sponsor, contacts two alternate vendors for quotes, and begins revising the schedule to reflect a possible slip. Which risk response strategy is the project manager applying?

Medium
449

A project manager is assigned to a project that has a high degree of uncertainty and rapidly changing requirements. The project sponsor is concerned about cost overruns and wants a method that allows for frequent delivery of value while adapting to changes. Which project management methodology should the project manager recommend?

Hard
450

According to Tuckman's model, during which stage do team members begin to resolve conflicts and establish norms?

Medium
451

Which TWO of the following are components of the project management plan?

Medium
452

A project manager is using a risk probability and impact matrix. A risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

Medium
453

During project planning, a project manager is decomposing the project scope into smaller components. Which document is being created, and what is the lowest level of decomposition called?

Medium
454

Which cost estimation technique uses historical data from similar projects to estimate the cost of the current project?

Easy
455

An agile team is reviewing their work. Which TWO metrics can be used to track progress within a sprint? (Select TWO).

Hard
456

A project team is in the storming stage of Tuckman's model. Which of the following behaviors is most likely to be observed?

Easy
457

A project manager is reviewing the project management plan. Which two components should be included? (Select TWO).

Medium
458

A project manager is in the process of formally authorizing a new project. Which document should be created during the initiation phase?

Easy
459

A project manager is assigned to a new project with unclear requirements and expects frequent changes. Which project management methodology is most suitable?

Easy
460

The project manager is reviewing the work breakdown structure (WBS) with the team to ensure that all deliverables are included. Which rule states that the WBS should capture 100% of the work defined by the project scope?

Medium
461

Which document describes the roles and responsibilities in a project using the categories Responsible, Accountable, Consulted, and Informed?

Easy
462

A project manager is assigned to upgrade the firewall for a company with multiple branch offices. The project charter has been approved, but the budget is tight. Which cost control technique should the project manager use to ensure expenses remain within budget?

Easy
463

A project manager is defining the project life cycle for a construction project where requirements are well-defined and unlikely to change. Which project management methodology is most appropriate for this scenario?

Easy
464

A project manager is analyzing quality data and wants to identify the most frequently occurring defects to prioritize corrective actions. Which quality tool should be used?

Medium
465

Which TWO documents are commonly used to define and control project scope? (Choose two.)

Easy
466

A project manager is closing out a fixed-price contract. The vendor has completed all deliverables, and the PM must formally document that the work was completed satisfactorily so that final payment can be released. Which document should the PM prepare and have signed?

Medium
467

A project has a BAC of $100,000. The earned value is $40,000, actual cost is $50,000, and planned value is $30,000. What is the estimate at completion (EAC) assuming the current cost performance is expected to continue?

Hard
468

A project manager is reviewing the issue log and notices several unresolved issues that are blocking team progress. The PM wants to ensure these issues are tracked, assigned, and resolved in a timely manner. Which action should the project manager take?

Hard
469

A project is behind schedule. The project manager notes that the critical path has been extended. Which action should the project manager take first?

Easy
470

Which TWO documents are typically created during the project planning phase?

Medium
471

A project manager is leading a team in a functional organization. Which statement BEST describes the project manager's authority?

Easy
472

A project manager is evaluating the project's performance using EVM. PV = $50,000, EV = $45,000, AC = $55,000. Which of the following is true?

Hard
473

A project manager is overseeing the deployment of a new file server that will store sensitive financial data. The project sponsor requires that data at rest be encrypted to comply with industry regulations. The project manager must choose an encryption method that provides strong security without significantly impacting performance. Which of the following should the project manager recommend?

Hard
474

A project manager calculates the cost variance (CV) as -$5,000 and the cost performance index (CPI) as 0.9. What does this indicate about the project?

Hard
475

A project manager is creating the WBS. Which rule ensures that all deliverables and work required for the project are included in the WBS and no work is omitted?

Easy
476

An IT project manager is building the cost baseline for a data center hardware refresh. The sponsor wants a single document that shows the total approved budget, the amount allocated to each work package over time, and the reserve for unplanned risks. Which artifact should the project manager produce?

Easy
477

Which THREE documents are part of the project procurement management process?

Hard
478

An IT project manager is tasked with deploying a new inventory management system. The project requires installing software on 100 workstations and training users. Which factor is most critical to include in the project schedule?

Easy
479

A project manager is closing out a project that delivered a new payroll system. The customer has formally accepted the final deliverable, and all invoices have been paid. Before releasing the team and archiving records, which activity should the project manager perform?

Easy
480

A project team is deploying new servers in a virtualized environment. The project scope includes performance monitoring. Which tool should the team configure to baseline CPU and memory usage?

Medium
481

Which of the following is a common response strategy for negative risks (threats) that involves reducing the probability or impact of the risk?

Easy
482

A project is 60% complete. The original budget (BAC) is $200,000. Actual costs to date are $130,000, and the earned value is $120,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost efficiency?

Hard
483

At a certain point in the project, the earned value (EV) is $500, the planned value (PV) is $600, and the actual cost (AC) is $400. What is the schedule performance index (SPI)?

Hard
484

A project manager is identifying stakeholders and analyzing their influence on the project. Using a power/interest grid, which group should the project manager 'manage closely'?

Medium
485

A project manager needs to document the formal approval of a change request that adds a new reporting module to an existing application. The change will increase the budget by $20,000 and extend the schedule by two weeks. Which document should the project manager use to record this decision?

Easy
486

A project manager is creating a document that formally authorizes the project and assigns the project manager. Which document is this?

Easy
487

A project manager is using earned value management. The project has a schedule variance (SV) of -$5,000. What does this indicate?

Medium
488

An agile team uses a tool where they maintain a list of features, enhancements, and bug fixes that are not yet scheduled for a sprint. This list is prioritized by the product owner. What is this list called?

Medium
489

Which of the following is a key responsibility of the project sponsor?

Easy
490

A project manager is working on a construction project that must comply with local building codes. A new regulation is introduced mid-project that requires additional safety features not in the original scope. The project manager documents the change and submits it to the change control board. What should the project manager do NEXT?

Medium
491

A project manager is creating a communication plan. Which element should be included to ensure stakeholders receive information in a timely manner?

Medium
492

A project team is experiencing scope creep because stakeholders keep adding minor features without formal approval. What is the best way to prevent this in the future?

Medium
493

A project has earned value (EV) of $50,000, actual cost (AC) of $60,000, and planned value (PV) of $55,000. What is the cost performance index (CPI)?

Hard
494

A project manager uses a control chart to monitor the number of defects found during testing. The chart shows one data point above the upper control limit (UCL). What action should the project manager take?

Medium
495

A project manager is leading a software development project. The team has completed the design phase and is about to start coding. The project sponsor asks the project manager to add a new feature that was not in the original scope. What should the project manager do first?

Medium
496

Which project life cycle phase involves formally accepting the project deliverables and releasing resources?

Easy
497

A project manager is using a hybrid methodology. The project has a fixed overall budget and a high-level schedule, but some deliverables are developed iteratively with stakeholder feedback. The team works in two-week sprints for software development, while hardware procurement follows a sequential plan. Which project life cycle is being used?

Hard
498

A project manager is creating a work breakdown structure (WBS) during the planning phase. The WBS should decompose the project deliverables into smaller, manageable components. What is the lowest level of a WBS called?

Easy
499

A company is undertaking a one-time initiative to develop a new mobile application with a defined budget, schedule, and scope. Which term best describes this initiative?

Easy
500

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $120,000 and the actual cost (AC) is $150,000. What is the estimate at completion (EAC) using the typical cost performance index (CPI) assumption?

Hard
501

An IT project manager is overseeing the migration of legacy systems to a new cloud platform. The project has a fixed budget and a strict deadline of six months. After three months, the project is on schedule but has already spent 70% of the budget due to higher-than-expected cloud service costs. The project manager must bring the project back within budget without affecting the deadline. Which of the following is the BEST course of action?

Hard
502

Which THREE items are typically found in a project management plan? (Select THREE).

Medium
503

A project to build a new office is in the planning phase. The project manager wants to use a methodology that allows for flexibility in design while still having a clear upfront plan for the overall construction. Which approach is BEST?

Medium
504

A project manager is preparing a project management plan for a construction project. The sponsor asks which subsidiary plans should be included to address scope, schedule, cost, and quality. Which TWO subsidiary plans should the project manager include? (Choose two.)

Hard
505

Which TWO of the following are key responsibilities of a project manager during the monitoring and controlling process group?

Hard
506

Refer to the exhibit. What is the total float for Task D?

Hard
507

During the execution phase, a project manager discovers that the development team has been using an unauthorized software library to accelerate work. The library has a license that could create legal risks for the company. What is the best course of action?

Hard
508

A project manager notices that a key team member is frequently pulled away to work on another priority project, causing delays. This situation is an example of which type of constraint?

Hard
509

Which THREE are components of the project management plan? (Choose three.)

Medium
510

A project manager is using a predictive life cycle for a regulatory compliance project with a fixed submission deadline. Midway through execution, a new regulation is announced that will take effect before the submission date. Which action best reflects adaptive life cycle thinking while preserving the deadline?

Hard
511

A project manager is creating a visual representation of the project schedule that shows tasks as horizontal bars along a timeline, including dependencies and milestones. Which tool is being used?

Easy
512

A project manager is reviewing a project that has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What is the best interpretation?

Hard
513

A project has been completed, and the project manager is conducting a lessons learned session and archiving project documents. Which project life cycle phase is being performed?

Easy
514

A project manager is closing a construction project and must verify that all contractual and administrative requirements have been met before releasing the final payment. Which TWO documents should the project manager review to confirm formal acceptance and closure? (Choose two.)

Hard
515

Arrange the steps for conducting a quality audit.

Medium
516

A project team uses a tool that displays columns such as 'To Do', 'In Progress', and 'Done' to visualize workflow. This is an example of which type of board?

Medium
517

During project planning, the team creates a work breakdown structure (WBS). Which of the following best describes the purpose of the WBS?

Easy
518

Which of the following best describes a project?

Easy
519

A project manager is preparing for the formal acceptance of project deliverables. The customer has been involved throughout the project and has approved interim deliverables. In which phase does formal acceptance typically occur?

Medium
520

Which TWO tools are commonly used for project scheduling?

Easy
521

During project execution, a key stakeholder demands a feature that was not included in the original scope. The project manager determines that the feature would require additional resources and extend the timeline. Which of the following is the BEST course of action?

Hard
522

A project manager is leading a team in an organization where team members are assigned to multiple projects and report to both a functional manager and the project manager. The project manager has moderate authority over the team. Which organizational structure does this describe?

Medium
523

Two project team members disagree on the technical approach for a critical deliverable. The project manager needs to resolve the conflict to avoid schedule delays. What is the best course of action?

Medium
524

During project execution, a team member proposes a change that will add a new feature to the product. The project manager documents the change request and analyzes its impact on scope, schedule, and cost. Who is typically responsible for approving or rejecting the change?

Medium
525

A project manager is building the team for a six-month software development project. The organization uses a functional structure, and the project manager has been told that team members will report to their functional managers for performance reviews and day-to-day priorities. The project manager needs to understand what authority is realistically available. Which type of organizational structure is described, and what is its typical impact on the project manager's authority?

Easy
526

Which TWO documents are typically created during the planning process group?

Medium
527

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following best describes the project's status?

Hard
528

Which of the following is NOT a typical constraint in the triple constraint of project management?

Easy
529

During project execution, the project team is experiencing conflicts and questioning the project manager's authority. According to Tuckman's model, which stage is the team in?

Hard
530

A project team is working on a construction project and is experiencing frequent change requests from the client. The project manager wants to ensure that all changes are properly evaluated and approved before implementation. Which project management process should the project manager implement?

Easy
531

A project manager has identified a stakeholder with high power and high interest. According to the power/interest grid, how should this stakeholder be managed?

Medium
532

A project sponsor asks for a document that formally authorizes the project and provides the project manager with authority to apply resources. Which document should the project manager provide?

Hard
533

Which document is used to record and track changes to project scope and their approval status?

Easy
534

During the planning phase, a project manager is creating the WBS. Which of the following best describes the process of breaking down deliverables into smaller, more manageable components?

Hard
535

A project team is performing quantitative risk analysis using a technique that runs thousands of simulations to determine the probability of completing the project on a specific date. Which technique is being used?

Hard
536

A project manager identifies a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

Medium
537

A project manager is leading a project to upgrade the organization's network infrastructure. The project sponsor asks for a document that outlines the project's purpose, high-level requirements, and key stakeholders. Which document should the project manager provide?

Easy
538

A project team is transitioning from a traditional to an agile approach. The project manager wants to adopt agile artifacts. Which THREE artifacts are commonly used in agile projects to track progress and manage work?

Medium
539

A project manager is estimating costs for a new software development project. The company has completed three similar projects in the past. Which cost estimation technique is most appropriate in this scenario?

Medium
540

A project manager is creating a risk register. One risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

Hard
541

A project team is using a tool to track user stories, epics, and bugs within sprints. The tool allows the team to view work in columns such as 'To Do', 'In Progress', and 'Done'. Which tool feature is being described?

Medium
542

A project manager is developing a communication plan. Which of the following should be determined first?

Medium
543

A project manager is chartered to deliver a new payroll system in eight months with a fixed budget of $600,000. In month three, the vendor informs the PM that a mandatory regulatory change will add 15% to the cost and two months to the schedule, but the scope is non-negotiable by law. The sponsor asks the PM to present the revised baseline for approval. Which action should the PM take FIRST?

Easy
544

A project manager is leading a global marketing campaign with team members in three countries and stakeholders who speak different languages. The project manager has created a detailed communication plan but is now receiving complaints that some stakeholders feel uninformed about major decisions. The project manager reviews the plan and notices that it specifies frequency and channels but does not address cultural differences or stakeholder influence levels. Which action should the project manager take to improve communication effectiveness?

Hard
545

A project manager is leading a team that is developing a new mobile application. During the execution phase, the product owner requests additional features that were not included in the original scope. What should the project manager do first?

Medium
546

A project manager is updating the issue log. Which TWO fields are typically included in a well-structured issue log? (Choose two.)

Medium
547

Which project document formally authorizes the project and identifies the project manager?

Easy
548

A project manager is leading a team in a matrix organization. The project has high priority, but the team members report to their functional managers. What is the PRIMARY challenge for the project manager?

Medium
549

A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.2. Which TWO conclusions can be drawn? (Select TWO.)

Medium
550

A project sponsor is responsible for providing resources and championing the project. Which of the following is also a primary responsibility of the project sponsor?

Hard
551

Which TWO tools are commonly used for project status reporting and communication with stakeholders?

Easy
552

Which THREE items are typically included in a project status report?

Hard
553

A project manager is setting up a project communication plan for a distributed team. The project manager needs to select tools that support real-time collaboration and document version control. (Choose two.)

Medium
554

A project is experiencing scope creep. Which TWO of the following are effective ways to manage scope creep? (Choose two.)

Medium
555

During project closing, which THREE activities should be performed?

Medium
556

Which project life cycle phase involves obtaining formal acceptance of the project deliverables?

Medium
557

During a project status meeting, a team member reports that a critical task is delayed due to a vendor not delivering a required component. The project manager needs to update the project schedule and communicate the impact. Which tool should the project manager use to analyze the effect of this delay on the overall project timeline?

Medium
558

A project manager is planning a construction project and identifies that the project has a fixed budget and a strict deadline. The sponsor emphasizes that quality cannot be compromised. Which THREE constraints are directly affected when a change request is approved? (Select THREE).

Medium
559

A project manager is using a network diagram to identify the critical path. Which TWO statements are true about the critical path?

Medium
560

A project manager is in the process of developing the project schedule. Which activity most directly determines the project's finish date?

Easy
561

A project manager wants to visualize task dependencies and the critical path for a construction project. Which tool should they use?

Easy
562

A project has a budget at completion (BAC) of $200,000. The actual cost (AC) is $80,000, earned value (EV) is $60,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the same cost efficiency?

Hard
563

Which project scheduling tool depicts activities as bars on a timeline, showing dependencies and milestones?

Easy
564

Which THREE activities are typically performed during the execution phase of a project?

Easy
565

A project is defined as a temporary endeavor undertaken to create a unique product, service, or result. Which of the following BEST describes a key characteristic of a project?

Easy
566

What is the difference between a risk and an issue?

Easy
567

A project manager is closing out a data-center migration. During the final review, the team discovers that two servers were decommissioned without the required security wipe, which is a compliance violation. The project manager documents the issue and assigns an owner and due date. Which process is the project manager performing?

Hard
568

A project manager is reviewing lessons learned from a previous similar project. That project suffered from frequent requirement changes that caused schedule delays and cost overruns. What should the project manager do to mitigate this risk on the current project?

Medium
569

Which TWO documents should be finalized during project closure?

Medium
570

Which document contains all identified risks, their probability and impact, and planned response strategies?

Easy
571

A project manager is creating a document that identifies all project stakeholders and their influence, interest, and impact on the project. Which document is being created?

Easy
572

A project has a total budget of $100,000. At a status date, the earned value (EV) is $50,000, the planned value (PV) is $60,000, and the actual cost (AC) is $70,000. What is the cost variance (CV)?

Easy
573

A project manager is identifying risks using the Delphi technique. Which TWO of the following are characteristics of the Delphi technique?

Easy
574

A project manager is reviewing the project schedule and notices that a critical path activity has a variance of -2 days. What does this indicate?

Medium
575

A project manager is developing a communication plan. Which two factors should be considered for each stakeholder? (Select TWO.)

Hard
576

A project team is distributed across three continents. The project manager needs a tool that allows real-time collaboration on project documents, version control, and task assignment. Which type of tool is BEST for this requirement?

Medium
577

A project sponsor is a key stakeholder. Which of the following is a primary responsibility of the project sponsor?

Medium
578

Which TWO are examples of project constraints in the project management triangle? (Choose two.)

Easy
579

A project to implement a new storage solution. The team is evaluating iSCSI vs Fibre Channel. Which factor is most important for choosing iSCSI over Fibre Channel?

Hard
580

During project execution, a key team member resigns. The project manager needs to fill the role quickly. Which document should the project manager update first?

Medium
581

Which of the following is a key component of the project scope statement?

Easy
582

A project manager is evaluating earned value metrics for a project. The CPI is 0.8 and the SPI is 0.9. Which TWO conclusions can the project manager draw?

Hard
583

In a user story, which component describes the benefit or value that the feature will provide?

Easy
584

A project manager is planning to migrate an on-premises data center to a hybrid cloud environment. The organization requires that the project team can provision and manage both on-premises and cloud resources through a single pane of glass. Which technology should the project manager prioritize?

Medium
585

A project team is executing the project plan when a key stakeholder requests a significant change to the scope. The change control board has approved the change. What should the project manager update next?

Medium
586

In a matrix organization, a project manager needs to acquire a team member from a functional department. The functional manager is reluctant to release the resource due to other work. What is the best way for the project manager to address this?

Hard
587

A project manager is closing a project that was terminated early by the sponsor due to a strategic shift. The team has completed some deliverables, and the customer has paid for work performed. Which activity is MOST important for the project manager to perform during closure?

Medium
588

A project manager is updating the project schedule and notices that the critical path has changed due to a delay in a key task. Which document should the project manager update first to reflect this change?

Medium
589

A construction project is nearing the end of the executing phase. The project manager is preparing for the closure phase. During a review, the project manager discovers that two deliverables have not been formally accepted by the client due to minor quality issues. The team has already started demobilizing resources. What should the project manager do to properly close the project?

Medium
590

A project manager is leading a project with a fixed-price contract and a hard regulatory deadline. The customer has requested a new feature that would require additional testing and a two-week delay. The project manager must decide how to respond. Which action should the project manager take FIRST?

Medium
591

A project team uses planning poker to estimate user stories. What is the purpose of this technique?

Easy
592

A project manager receives a change request from a stakeholder. What is the first step the project manager should take?

Easy
593

A project manager is preparing the resource management plan for a project that requires a scarce cybersecurity specialist for only three weeks of a nine-month schedule. The functional manager has warned that the specialist may be pulled onto a higher-priority incident at any time. Which action should the PM take to protect the schedule?

Hard
594

A project manager needs to communicate the project's progress to stakeholders with high power and low interest. According to the power/interest grid, which communication approach is most appropriate?

Medium
595

A project manager is reviewing a change request to modify the project scope. Which TWO items should be updated in the project management plan if the change is approved?

Medium
596

A project manager is planning a project in a weak matrix organization. The project manager has limited authority over team members who report to functional managers. Which TWO actions should the project manager take to improve the ability to influence project outcomes? (Choose two.)

Hard
597

A project manager is evaluating a change request that would increase the project cost by 10% but reduce schedule by 15%. The change control board approves the change. What should the project manager update?

Medium
598

A project manager is calculating the cost performance index (CPI) for a project. The earned value (EV) is $50,000 and the actual cost (AC) is $60,000. What does the CPI indicate? (Select TWO correct statements.)

Medium
599

A project manager is creating a WBS. Which two best practices should be followed? (Select TWO)

Medium
600

A project manager is closing out a completed infrastructure upgrade project. The PM must ensure the project is closed in an orderly way and that lessons from the effort are preserved for future work. Which TWO activities belong to the closing phase? (Choose two.)

Hard
601

A project has an EV of $40,000, PV of $50,000, and AC of $45,000. What is the cost performance index (CPI)?

Medium
602

A project manager is selecting a methodology for a project with well-understood requirements and low expected change. Which methodology is MOST appropriate?

Medium
603

A project manager needs to track the start and end dates of tasks as well as dependencies. Which tool should be used?

Easy
604

A project has many stakeholders with varying interests and influence. Which document should the PM use to plan how to engage them?

Hard
605

A project to build a website is expected to take 6 months with a fixed budget. During planning, the team determines that the requirements are well-understood and unlikely to change. Which methodology is most appropriate?

Medium
606

A software development project is using an agile methodology. The product owner is frequently changing requirements during sprints, causing the team to miss sprint goals. The project manager has a good relationship with the product owner. The team is frustrated and morale is dropping. The project manager needs to address this issue while maintaining stakeholder satisfaction. What should the project manager do FIRST?

Medium
607

A project manager is evaluating two potential projects. Project A has an NPV of $50,000, and Project B has an NPV of -$10,000. Which project should be selected based on NPV?

Medium
608

In a RACI matrix, which role is ultimately accountable for the successful completion of a task?

Medium
609

A project manager is tracking the completion of key deliverables against the project schedule. Which tool should they use to display only major milestones without showing detailed dependencies or tasks?

Medium
610

A change request to add a new feature has been submitted. After impact analysis, the change control board (CCB) approves the change. What should the project manager do next?

Medium
611

In a power/interest grid, stakeholders with high power and low interest should be managed with which approach?

Easy
612

A change request to add a new feature is submitted. The project manager performs an impact analysis and presents it to the Change Control Board (CCB). The CCB approves the change. What is the next step?

Medium
613

A project has a CPI of 0.8 and an SPI of 1.1. Which statement describes the project's performance?

Hard
614

Which TWO of the following are characteristics of the planning phase in the project life cycle? (Choose TWO.)

Medium
615

Which document contains information such as issue ID, description, owner, priority, status, and resolution date?

Easy
616

A project manager is selecting tools for an Agile project. Which TWO tools are commonly used for Agile project management? (Select two.)

Medium
617

During project execution, a stakeholder requests a change that will increase the project cost by 10%. The project manager documents the change and submits it to the change control board (CCB). After review, the CCB approves the change. Which document should the project manager update first?

Medium
618

A project manager is performing qualitative risk analysis and must prioritize risks for response planning. The project has limited budget and tight schedule. Which action should the project manager take to prioritize risks effectively?

Hard
619

You are the project manager for a large construction project to build a new office complex. The project is currently in the execution phase, but there have been significant delays due to inclement weather and material shortages. The sponsor has indicated that the completion date must not slip further. The project has a total budget of $10 million, and so far $6 million has been spent, with only 40% of the work completed. The project team is demoralized, and there is conflict between the on-site construction team and the procurement team regarding material orders. The senior manager has asked you to present a recovery plan at the next steering committee meeting. Given the situation, what should you do first?

Hard
620

A company is considering a project with an initial investment of $100,000 and expected annual cash inflows of $30,000 for 5 years. The discount rate is 10%. What is the approximate Net Present Value (NPV)? (Present value of annuity factor for 5 years at 10% is 3.791)

Hard
621

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000 and the actual cost (AC) is $120,000. If the cost performance is expected to continue, what is the estimate at completion (EAC)?

Hard
622

A project has three activities on the critical path. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. What is the total float for any activity on the critical path?

Medium
623

You are managing a marketing campaign project. The team uses a project management software that includes a resource management module. You notice that several team members are overallocated, and project tasks are at risk of delay. The software allows you to view resource capacity and assignments, but the data is not being updated regularly. You need to ensure resource conflicts are identified and resolved quickly. Which action should you take?

Medium
624

A project team is working in a matrix organization. The project manager needs to obtain resources from functional managers. Which challenge is the project manager MOST likely to face?

Easy
625

A project has just completed the closure phase. Which activity is performed to formally obtain confirmation from the customer that the project deliverables have been accepted?

Hard
626

During project execution, a team member reports that a key deliverable will be delayed because a required component is out of stock. The project manager updates the issue log and meets with the team to evaluate alternatives. Which project management process is being performed?

Medium
627

A project team is evaluating cloud providers for a SaaS application. The provider must guarantee 99.99% uptime and support data sovereignty requirements. Which service level agreement (SLA) clause is most critical to review?

Hard
628

During risk management, a team identifies a risk with a 20% probability of occurrence and a potential cost impact of $50,000. What is the Expected Monetary Value (EMV) of this risk?

Medium
629

A project manager reviews the following change request log: - CR-001: Adds 2 weeks to the schedule. - CR-002: Low-priority enhancement; no schedule impact. - CR-003: Reduces schedule by 1 week to offset delays from other changes. - CR-004: Urgent but high-risk; could cause additional delays. Based on the change request log, which of the following actions should the project manager take to maintain the project schedule?

Medium
630

A project manager is developing the project charter and needs to identify high-level risks. Which document should be used as an input?

Medium
631

A project manager is preparing a status report for stakeholders. The project is currently in the execution phase. Which key performance indicator should be included to show how efficiently the project is using its budget?

Hard
632

Refer to the exhibit. Based on the project status report, what is the cost variance (CV) and what does it indicate?

Hard
633

A project manager needs to document the process for submitting and approving change requests. Which document should the project manager create?

Medium
634

A project manager is building the project team for a six-month software implementation. The organization uses a weak matrix structure. The project manager needs two developers, but the functional manager controls their day-to-day assignments and performance reviews. Which action should the project manager take FIRST to secure these resources?

Medium
635

During a project status meeting, a stakeholder complains that the project is not delivering the expected business value. The project manager reviews the business case and finds that the project is on track per the approved scope. What should the project manager do?

Medium
636

A large government project is in the initiation phase. The project charter has been drafted, but there is disagreement among key stakeholders about the project's objectives. Some stakeholders want to maximize functionality, while others want to minimize cost. The project manager must lead the effort to resolve this. Which of the following is the BEST approach?

Hard
637

Which TWO of the following are examples of gold plating? (Select two.)

Medium
638

A project manager is using a tool to track project tasks, dependencies, and resource assignments. The team needs to see the critical path and adjust schedules when tasks are delayed. Which tool should the project manager use?

Medium
639

A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What does this indicate about the project's performance?

Hard
640

A project manager learns that a regulatory change will require an additional compliance review not included in the approved scope baseline. The change is mandatory to keep the project legally compliant. What should the project manager do first?

Hard
641

A project manager is creating a project charter. Which TWO components are typically included in a project charter? (Choose two.)

Medium
642

A project manager is developing the project charter for a new CRM implementation. The sponsor asks the PM to ensure the charter includes a measurable success criterion. Which of the following is the BEST example of a measurable success criterion to include in the project charter?

Medium
643

A project team is experiencing conflicts between two key members. The project manager wants to resolve the issue quickly to avoid delays. Which conflict resolution technique involves the project manager making a decision without discussion?

Easy
644

Which of the following best describes a mandatory dependency in a project schedule?

Easy
645

A project manager is assigned to a new software development project. The requirements are well understood and unlikely to change. The project team is collocated and has experience with similar projects. Which life cycle approach is MOST appropriate for this project?

Medium
646

Order the steps for creating a project schedule.

Medium
647

In the context of risk management, what is a trigger?

Medium
648

During a project kickoff meeting, the team identifies several potential risks. The project manager decides to document them in a structured format. Which project document should the project manager use to record and track these risks throughout the project?

Hard
649

A company is deploying a new web server. Which TWO security measures should the project manager include in the project plan? (Choose two.)

Hard
650

A project manager is leading a software development project. The client requests a feature change that will add two weeks to the schedule and increase costs by $10,000. The project manager evaluates the impact and presents options to the change control board. The board approves the change but the project sponsor expresses concern about the budget. What should the project manager do next?

Hard
651

A project manager is reviewing the risk register and sees a risk with high probability and high impact. The risk response strategy chosen is to purchase insurance. This is an example of which risk response strategy?

Hard
652

During a risk assessment, a project manager calculates a risk score by multiplying the probability of occurrence (0.6) by the potential impact ($50,000). The risk score is 30,000. The project manager then identifies a response strategy that reduces the probability to 0.2. After the response, the remaining risk is calculated. What is the residual risk score?

Hard
653

A project manager is estimating effort for a data migration. The team has completed similar migrations before, so they use a weighted average of optimistic, most likely, and pessimistic estimates for each work package. Which estimating technique is the project manager applying?

Medium
654

A company is implementing a new HR system. The project manager wants to ensure that all requirements are gathered up front and the scope is fixed. Which project management methodology is MOST appropriate?

Medium
655

Which TWO documents should be updated when a change request is approved?

Easy
656

A project is in the planning phase and the team is determining the sequence of activities. Which project life cycle phase follows planning?

Medium
657

A project has a Net Present Value (NPV) of -$5,000. What does this indicate?

Medium
658

A project manager is creating a lessons learned document. Which TWO are typical components of lessons learned? (Choose two.)

Easy
659

A project manager is analyzing the critical path of a 40-activity network diagram. Two paths converge on a milestone: one path has a total float of zero and a duration of 120 days, and the other path has a total float of three days and a duration of 118 days. A team member proposes reducing the duration of an activity on the path with three days of float by two days. What is the MOST likely effect of this change on the project?

Hard
660

Which of the following documents formally authorizes the project and provides the project manager with the authority to apply organizational resources?

Easy
661

In a matrix organization, a project manager is struggling to get resources assigned to project tasks because the functional managers prioritize operational work. Which type of matrix organization is MOST likely in place?

Medium
662

After a change request is approved by the Change Control Board, what must be updated to reflect the approved changes? (Choose the best answer.)

Medium
663

Which TWO of the following are characteristics of the waterfall project management methodology?

Medium
664

You are the project manager for a mid-sized company that provides an online customer portal. The portal is hosted on a single virtual machine (VM) in the company's on-premises data center with 4 vCPUs, 16 GB RAM, and a 500 GB HDD. The VM runs Windows Server 2019 and hosts both the web server (IIS) and the database (SQL Server Express). Users have been reporting slow performance, especially during peak hours (10 AM - 2 PM). The system administrator notes that CPU usage spikes to 95% during those times, and disk I/O latency averages 50 ms. The company's budget is limited, and they want a cost-effective solution that can be implemented within two weeks. The project sponsor suggests migrating to the cloud, but the IT director is concerned about security and compliance. The company has no existing cloud infrastructure or virtual private network (VPN) to the cloud. You need to propose a solution that improves performance without incurring high costs or long delays. Which of the following is the BEST course of action?

Easy
665

A project manager is working on a software development project. The team has identified a potential risk that could cause a two-week delay. The project manager decides to add extra resources to the critical path to reduce the impact. Which risk response strategy is being used?

Easy
666

A project has earned value (EV) of $120,000, planned value (PV) of $100,000, and actual cost (AC) of $110,000. What is the cost performance index (CPI)?

Hard
667

During project closing, which of the following is the primary purpose of the lessons learned document?

Medium
668

During project execution, two team members disagree on who is responsible for a specific task, leading to delays. Which project document should the project manager consult to resolve this conflict?

Hard
669

A project team uses a tool that shows only major events or deadlines, such as the start and end of phases. Which type of chart are they using?

Easy
670

A project manager is overseeing a construction project. The team uses a shared spreadsheet to track project issues. Recently, the spreadsheet has become cluttered with duplicate entries and outdated information. The project manager wants to implement a more structured approach for issue tracking. The tool must allow team members to submit issues, assign owners, set priorities, and track resolution progress. Additionally, it should generate reports for stakeholders. Which tool should the project manager choose?

Easy
671

A project manager is leading a software development project. The team has completed the coding phase and is about to begin system testing. The project sponsor requests a demonstration of the software to key stakeholders before testing begins. What should the project manager do?

Medium
672

A project manager needs to identify the root cause of a recurring defect. Which quality tool uses a fishbone diagram to categorize potential causes?

Medium
673

A project is behind schedule. The project manager decides to start the testing phase before the development phase is completely finished. This is an example of which schedule compression technique?

Hard
674

A project manager is preparing for the first phase gate review. The sponsor wants assurance that the phase has met its exit criteria before funding the next phase. Which activity best supports this decision?

Easy
675

A project manager is estimating the cost of a new software development project. The project is similar to a previous project that cost $500,000. The PM adjusts for size and complexity and estimates the new project will cost $600,000. Which estimation technique is being used?

Medium
676

A project manager is reviewing change requests. Which THREE types of changes would be subject to integrated change control?

Medium
677

Which document is used to track all changes made throughout a project, including their status and impact?

Easy
678

A project manager is creating a RACI matrix for the project. One activity involves conducting security testing. The security lead will perform the testing, the project manager is responsible for ensuring it happens, and the compliance officer needs to be informed of the results. Which assignment is correct?

Medium
679

A project manager is using a Gantt chart to track progress. Which tool would BEST complement the Gantt chart to show task dependencies and the critical path?

Hard
680

A project to implement a new backup solution. Which THREE components are essential for a comprehensive backup strategy? (Choose three.)

Medium
681

Which THREE of the following are responsibilities of a project manager during project closure?

Medium
682

A project manager is updating the risk register for a new project. Which THREE of the following fields are essential components of a risk register in CompTIA Project+?

Hard
683

A project manager is overseeing a construction project to build a new office building. The project is currently in the execution phase, with foundation work underway. During a status meeting, the project manager discovers that the detailed architectural plans, which were a deliverable of the planning phase, were never formally approved by the client. The team has been working based on preliminary drawings that were used for the initial estimate. The project schedule shows that the next major activity, framing, is scheduled to start in two weeks. The project sponsor is on an extended leave and unavailable for the next month. The project manager is concerned about significant rework if the plans are later rejected. The project has a tight budget and aggressive timeline. What should the project manager do first?

Hard
684

A project manager is assigned to a project in a matrix organization where the functional managers have significant control over team members. The PM has limited authority. This describes which type of matrix?

Hard
685

During project execution, a team member identifies a problem that has already occurred and is affecting the project schedule. The project manager should document this in which of the following?

Medium
686

A project team is distributed across multiple time zones and the project manager is using virtual meetings. What is the most effective way to ensure clear communication?

Hard
687

A project manager is developing the project management plan for a new product development project. The organization has a PMO that provides templates and standards. Which TWO components are typically included in the project management plan? (Choose two.)

Medium
688

A project manager is creating a document that formally authorizes the project and assigns the project manager. Which document is being created?

Easy
689

A project manager is evaluating whether to implement a PMO (Project Management Office) for the organization. Which scenario would best justify the creation of a PMO?

Hard
690

A project has an Earned Value (EV) of $50,000, Actual Cost (AC) of $60,000, and Planned Value (PV) of $55,000. What is the Cost Performance Index (CPI), and what does it indicate?

Hard
691

What is the 100% rule in work breakdown structure (WBS) creation?

Easy
692

A project team is using an agile methodology and the product owner frequently changes priorities mid-sprint. What is the most likely consequence?

Medium
693

During project execution, the project team completes a deliverable that exceeds the specified requirements by adding extra features without authorization. This is an example of which concept?

Medium
694

Which document formally authorizes the project and provides the project manager with the authority to apply resources?

Hard
695

Which document defines the communication requirements, including who needs what information, when, and how?

Easy
696

A project team is identifying risks. They gather subject matter experts anonymously and use a facilitator to collect their responses iteratively until consensus is reached. Which risk identification technique is being used?

Easy
697

A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. What is the cost performance index (CPI) and what does it indicate?

Hard
698

A project manager is drafting the document that formally outlines how the project team will be structured, how often status reports will be delivered, and which tools will be used for tracking tasks. This document will be reviewed and approved before execution begins. Which document is the project manager creating?

Easy
699

A project manager is leading a project to migrate an on-premises data center to a colocation facility. The project manager must ensure that the new facility provides adequate physical security for the servers. Which of the following should the project manager verify during the site visit?

Medium
700

Which agile artifact contains the prioritized list of all desired work for a product?

Easy
701

A project manager is using a technique to identify risks by gathering a group of experts who provide anonymous input through multiple rounds of questionnaires. This technique avoids groupthink and allows experts to refine their opinions. Which risk identification technique is being used?

Hard
702

A project manager is preparing the project charter for a new initiative. The sponsor asks which element must be included in the charter to authorize the project. What should the project manager include?

Easy
703

A project manager is working on a project that has a very tight deadline. The project team consists of junior and senior members. The project manager notices that the junior members are making many mistakes that require rework from senior members. This is causing delays. What should the project manager do to improve efficiency?

Easy
704

A project manager is developing the project charter. Which of the following should be included as a key element in the charter to define the project's boundaries?

Medium
705

A project manager is leading a project to upgrade an organization's wireless network. The project charter has been approved, and the project manager is now identifying the people, equipment, and materials needed to complete the work. Which project management process is the project manager performing?

Easy
706

A project manager is calculating the critical path. The network diagram shows two paths: Path A: A(3 days) → B(4 days) → C(2 days) = 9 days; Path B: D(5 days) → E(1 day) → F(3 days) = 9 days. Both have total float of zero. What is the total float for an activity on Path A?

Hard
707

A project has a critical path duration of 45 days. Activity X on the critical path has an optimistic duration of 5 days, a pessimistic duration of 13 days, and a most likely duration of 8 days. What is the expected duration of activity X using PERT?

Hard
708

A project manager is creating a risk register. The team identifies a risk that could cause a data breach if a server is misconfigured. The probability is low, but impact is high. Which risk response strategy is most appropriate?

Medium
709

In a network diagram, Activity B has a duration of 5 days. Its predecessor is Activity A (duration 3 days) with a finish-to-start relationship. Activity C (duration 4 days) has a start-to-start relationship with Activity B with a 2-day lag. What is the earliest day Activity C can start?

Hard
710

In a risk register, which field describes the event that signals a risk is about to occur?

Easy
711

A project manager is leading a distributed team that uses a kanban board to visualize workflow. The team wants to limit the number of items in progress to reduce multitasking and improve cycle time. Which tool or technique should the project manager implement?

Hard
712

Which TWO of the following are common types of organizational structures that affect project management?

Easy
713

A project requires a specific software library that is only available from a single vendor. The vendor's delivery schedule dictates when the project can begin integration testing. This dependency is best described as:

Medium
714

Which project life cycle phase involves obtaining formal acceptance of the project deliverables and releasing project resources?

Medium
715

A project manager is closing out a data migration project. The sponsor wants assurance that all contractual requirements have been met before final payment is released to the vendor. Which activity should the project manager perform to support this assurance?

Hard
716

A company is migrating to a new ERP system. The project manager needs to ensure minimal downtime during cutover. Which deployment strategy should be recommended?

Hard
717

A project manager is developing a document that will provide a common understanding of the project's objectives, deliverables, and constraints for all stakeholders. The document should also include the business case and high-level risks. Which document is the project manager creating?

Medium
718

A company is evaluating two projects. Project A has an NPV of $50,000 and a payback period of 3 years. Project B has an NPV of $40,000 and a payback period of 2 years. Which project should be selected based on NPV?

Hard
719

A project manager is closing out a customer relationship management implementation. The sponsor asks which activities are part of the closing phase rather than the execution phase. (Choose two.)

Medium
720

A project manager is closing out a project that was cancelled by the sponsor before completion. The sponsor wants to capture lessons learned and release the team. Which activity should the project manager perform FIRST?

Medium
721

A project manager creates a visual representation that shows the 20% of causes contributing to 80% of the problems in a project. Which tool is being used?

Hard
722

During the closing phase of a project, which TWO activities should be performed?

Medium
723

A project manager is planning the deployment of a new virtual desktop infrastructure (VDI) environment. The sponsor wants to understand which type of organizational structure would give the project manager the highest level of authority over team members and budget. Which organizational structure should the project manager recommend?

Medium
724

A project team has identified a risk that a key supplier may go out of business. The probability is low but the impact is high. The project manager decides to find an alternative supplier and sign a contract with them as a backup. This is an example of which risk response strategy?

Hard
725

Which TWO items are typically included in a project status report?

Hard
726

During project execution, the project manager notices that the development team has been adding extra features that were not requested by the customer. Which of the following describes this behavior?

Medium
727

A project manager is working in an organization where the project team members report to both a functional manager and the project manager. The project manager has moderate authority and shares resource management with functional managers. This is an example of which organizational structure?

Medium
728

A project manager is preparing for a post-implementation review after deploying a new CRM system. The team needs a document that captures what went well, what did not, and actionable recommendations for future projects. Which document should the project manager update?

Medium
729

A project manager is planning a new software development project. Which tool should the project manager use to break down the project deliverables into smaller, manageable work packages?

Easy
730

A project manager is closing out a project that was cancelled by the sponsor before any deliverables were completed. The sponsor asks what must still be performed before the project can be formally closed. Which activity should the project manager complete?

Easy
731

During a project status meeting, a stakeholder requests a report showing the variance of actual costs from the planned budget. Which metric should the project manager include?

Medium
732

A project manager is evaluating a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

Medium
733

A project team is entering the Storming stage of Tuckman's model. Which TWO characteristics are typical of this stage?

Medium
734

A project manager notices that a task on the critical path is delayed by 3 days. Which tool should the project manager use to determine the impact on the project completion date?

Medium
735

A project manager is assigned to a new project that involves developing a mobile application. The project sponsor wants to ensure that the project delivers value to the organization. Which project management concept should the project manager apply to align the project with strategic goals?

Medium
736

A project has a budget of $500,000 and is 40% complete. The actual cost incurred is $250,000. What is the cost variance?

Hard
737

A project manager works in an organization where team members report to both a functional manager and a project manager. The project manager has moderate authority and shares resource control with the functional manager. Which type of organizational structure does this describe?

Medium
738

A project to deploy a new CRM system is in the execution phase. The team frequently encounters integration issues because the development environment does not match the production environment. The project manager has not enforced change control, and team members have made undocumented changes to the development environment. What should the project manager do first?

Easy
739

A project team uses planning poker to estimate user stories. The product owner describes a story that involves integrating with a third-party API. The team discusses unknowns and then votes. The estimates are 5, 8, 13, and 20 story points. What should the team do next?

Hard
740

A project team is decomposing the project scope into smaller, manageable components. Which rule ensures that the WBS includes 100% of the work defined in the scope?

Medium
741

A project manager uses a diagram to identify the most frequent causes of defects in a process. The diagram displays bars in descending order and a cumulative line. Which quality tool is being used?

Medium
742

A project manager wants to measure the percentage of work completed compared to the planned schedule. Which metric should be used?

Medium
743

A project manager has just received approval for the project charter. What is the next primary activity in the initiation phase?

Easy
744

A project sponsor is reviewing a proposal for a new project. The expected cash flows are: Year 0: -$100,000; Year 1: $30,000; Year 2: $40,000; Year 3: $50,000. The discount rate is 10%. Which of the following is the Net Present Value (NPV) of the project?

Hard
745

A project team is creating a work breakdown structure (WBS) for a software development project. The project manager wants to ensure that all deliverables are identified and decomposed into manageable work packages. Which tool should the team use to represent the hierarchical decomposition of the work?

Medium
746

A project manager is leading an initiative to virtualize 40 aging physical servers onto a new hypervisor cluster. The project sponsor asks how the team will ensure that a single physical host failure does not take down the virtual machines running on it. Which hypervisor feature should the project manager confirm is configured?

Medium
747

A project manager is reviewing the project charter and notes that a specific software platform must be used for the deliverable. The project sponsor has mandated this technology due to organizational standards. In which category of constraint should this requirement be documented?

Medium
748

A project is in the execution phase, and the project manager receives a change request to add a new feature that is not in the scope statement. The change request has been approved by the change control board. What must the project manager do next?

Hard
749

Which document formally records the deliverables, acceptance criteria, exclusions, assumptions, and constraints of a project?

Easy
750

Which of the following BEST describes the role of a project sponsor?

Easy
751

A project sponsor is reviewing a project that has a Net Present Value (NPV) of -$15,000. What should the sponsor recommend?

Hard
752

A project manager is developing the project schedule. Dependencies include: Task A starts after Task B finishes; Task C must be completed before Task D can start; Task E can start when Task F starts. Which dependency types are being used?

Medium
753

A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, and the actual cost (AC) is $120,000. What is the estimate at completion (EAC) assuming the current cost performance index (CPI) will remain the same?

Hard
754

Refer to the exhibit. What should the project manager do first?

Easy
755

During project closing, which TWO activities are typically performed?

Easy
756

A project team is identifying risks. They gather a group of experts who provide anonymous responses to a questionnaire. The facilitator aggregates the responses and shares them, then the experts revise their answers. Which technique is being used?

Medium
757

A project sponsor asks for a document that outlines the high-level scope, objectives, and key stakeholders of a new project. Which document should the project manager provide?

Easy
758

A project manager is leading a project to deploy a new customer relationship management (CRM) system. The project is in the Executing phase, and the team has just completed the first sprint. During a review, the project manager notices that the team is not following the agreed-upon coding standards, leading to inconsistent code quality. Which of the following actions should the project manager take FIRST to address this issue?

Medium
759

A project manager is assigned to a project that has already been chartered. The project sponsor has provided the project charter and initial budget. The project manager is now in the planning phase. During the first planning meeting, the team identifies a major risk: a key supplier may go out of business before the project ends. The project manager needs to proceed. Which of the following is the NEXT step?

Easy
760

A project manager is selecting two documents that are essential for defining project scope. Which TWO documents should they choose?

Medium
761

An agile team uses story points for estimating effort. During sprint planning, the team's average velocity is 30 story points per sprint. The product owner wants to commit to 35 story points for the upcoming sprint. What should the team do?

Medium
762

During project closing, which activity involves obtaining formal acceptance from the customer or sponsor that deliverables meet requirements?

Medium
763

The project team is experiencing conflicts over task assignments. Which document should the project manager reference to clarify roles and responsibilities?

Medium
764

A project manager is evaluating the financial viability of several proposed projects. The steering committee wants to select projects that maximize return over time. Which TWO financial metrics should the project manager use to compare long-term profitability? (Select TWO).

Medium
765

A project manager is creating a visual timeline that displays tasks as horizontal bars, shows dependencies between tasks, and highlights the critical path. Which tool should the manager use?

Easy
766

Which project management process group involves obtaining formal acceptance of the project deliverables and archiving project documents?

Easy
767

A project manager is reviewing earned value data: PV = $150,000, EV = $120,000, AC = $130,000. Which THREE statements are correct?

Hard
768

A project manager is finalizing the resource management plan for a project that depends heavily on a scarce database administrator skill set. The sponsor asks which activities belong to the Acquire Resources process rather than to Plan Resource Management. Which TWO activities should the project manager identify? (Choose two.)

Medium
769

A project manager is planning a data center migration that will occur during a mandatory freeze on production changes. Which constraint type does this represent?

Medium
770

A project manager is leading a project through the Initiating phase. The sponsor asks what the primary purpose of the project charter is. What should the project manager explain?

Easy
771

A project has a mandatory dependency between two activities: the foundation must be poured before the walls can be erected. This dependency is based on the physical nature of the work and cannot be changed. What type of dependency is this?

Medium
772

A project team is analyzing potential risks. They gather experts who provide anonymous responses to a questionnaire, and then the facilitator shares a summary for further rounds of feedback. Which risk identification technique is being used?

Medium
773

During project execution, a stakeholder requests a change that will increase costs. Which document should the PM update first?

Medium
774

A project manager is leading a project to implement a new enterprise resource planning (ERP) system. The project is in the executing phase. The project manager needs to ensure that the project team follows the approved processes and that the project remains on track. Which TWO of the following activities are part of the Monitoring and Controlling process group? (Choose two.)

Hard
775

A project manager is closing a phase of a multi-phase program. The phase deliverables have been accepted by the customer, but several team members will continue into the next phase. Which activity should the project manager perform as part of closing this phase?

Medium
776

In which organizational structure does the project manager have the least authority?

Easy
777

In an Agile project, the team uses story points to estimate effort. During sprint planning, they select user stories from the product backlog and assign them to the sprint. What is the resulting list of items committed for the sprint called?

Easy
778

A project manager is working on a project that follows an adaptive (agile) life cycle. The team is in the middle of an iteration and the product owner wants to introduce a new requirement. What is the most appropriate action for the project manager to take?

Medium
779

A project manager identifies a risk that a key team member might leave during the project. To reduce the impact, she cross-trains other team members. Which risk response strategy is being applied?

Medium
780

During project execution, a stakeholder requests a new feature that was not included in the original scope. The project manager initiates a change request. What is the next step in the integrated change control process?

Medium
781

A project manager is preparing to close out a construction project. The final deliverable was accepted by the customer two weeks ago, but several team members have already been reassigned to a new initiative. The project manager still needs to obtain formal sign-off from the customer, archive project documents, and release remaining resources. Which activity should the project manager complete FIRST in the closing phase?

Medium
782

A project has a planned value (PV) of $50,000, earned value (EV) of $40,000, and actual cost (AC) of $45,000. What is the schedule variance (SV) and cost variance (CV)?

Medium
783

A project manager is preparing the communication plan and needs to determine the appropriate format and frequency for status updates to a steering committee that meets monthly. The committee wants concise, decision-oriented information. Which approach best fits this need?

Hard
784

In earned value management, the project has an EV of $50,000, PV of $60,000, and AC of $55,000. What is the cost variance (CV)?

Medium
785

During project initiation, the project sponsor provides the project manager with a document that authorizes the project and assigns the project manager. This document also outlines high-level scope, budget, and timeline. Which document is this?

Hard
786

During a project to deploy a new enterprise resource planning (ERP) system, the project manager identifies that the vendor's implementation methodology does not align with the organization's change management process. The project manager needs to address this misalignment. What should the project manager do FIRST?

Hard
787

A project manager is midway through a data migration project when the vendor informs them that a critical API will be deprecated in six weeks, well before the planned cutover. The project manager convenes the team and identifies three candidate responses: rewrite the integration, negotiate a vendor extension, or move the cutover earlier. What has the project manager MOST directly performed?

Hard
788

A project manager is managing a construction project. The scope is well-defined, but the customer is open to minor changes during execution. Which methodology is most suitable?

Easy
789

During a project, a key stakeholder requests an additional feature that was not in the original scope. The project manager logs a change request and evaluates that the change will increase the project cost by 5% and delay the schedule by 2 weeks. After the change control board (CCB) approves the request, what is the project manager's NEXT step?

Hard
790

A project manager is closing out a customer portal project when a key vendor reports that a delivered component fails security acceptance criteria. The component is already installed in the production environment, and the customer has begun using it. The project manager must decide how to handle the situation before final sign-off. Which TWO actions are MOST appropriate? (Choose two.)

Hard
791

A project manager is assigning resources to activities. Activity X requires a specialized skill that is only available from a contractor. The project manager decides to hire the contractor. Which TWO documents are most likely to be used to define the work and terms for this contractor? (Select TWO).

Hard
792

A project manager needs to identify which tasks are critical to the project's completion date. After creating the project schedule, which tool should be used to visualize the critical path?

Medium
793

In which organizational structure does the project manager have the least authority over project resources?

Easy
794

During project execution, a key stakeholder requests a new feature that was not in the original scope. The project manager is concerned about the impact on the schedule and budget. This is an example of:

Medium
795

Which TWO of the following activities are typically performed during the initiation phase of a project?

Easy
796

A project manager is initiating a new project and needs to formally authorize the project and assign the project manager. Which document provides this authorization?

Easy
797

Which document breaks down the project deliverables into smaller, more manageable components?

Easy
798

A project manager is developing a communication plan. Which two elements should be included in the plan? (Select TWO)

Medium
799

A project manager is decomposing the project scope into smaller components. Which output is produced?

Medium
800

A project is falling behind schedule. The project manager considers crashing or fast-tracking. Which THREE statements about these techniques are correct? (Select three.)

Hard
801

A project manager is assigned to a new project that has a tight deadline. The sponsor wants to fast-track the project by overlapping some phases. Which project management concept should the PM be most concerned about regarding this approach?

Easy
802

During a project, the project manager calculates the following: Earned Value (EV) = $50,000, Planned Value (PV) = $60,000, Actual Cost (AC) = $55,000. Which statement accurately describes the project's performance?

Hard
803

A project manager is reviewing the project schedule and notices that the critical path has a duration of 120 days. One activity on the critical path has a duration of 15 days and a total float of 0. If the duration of that activity is reduced by 5 days, what is the new critical path duration?

Medium
804

A project manager is evaluating two projects. Project A has an initial investment of $50,000 and expected annual returns of $15,000 for 5 years. Project B has an initial investment of $80,000 and expected annual returns of $22,000 for 5 years. Based on payback period, which project should be selected, and what is the payback period for that project?

Hard
805

A project manager is preparing the team charter for a distributed project team that spans three time zones. The sponsor wants the charter to reduce friction before work begins. Which TWO items belong in the team charter? (Choose two.)

Hard
806

A project is experiencing cost overruns. The project manager wants to calculate key earned value metrics. Which THREE metrics are needed to compute the cost performance index (CPI) and schedule performance index (SPI)? (Select three.)

Hard
807

A project manager is in the process of developing the project charter. Which of the following would be included in the project charter?

Easy
808

A project manager is conducting a risk assessment and identifies a risk with a high probability and high impact. The team decides to purchase insurance to cover potential losses. This is an example of which risk response strategy?

Hard
809

Which TWO documents are typically created during the project initiation phase? (Select TWO.)

Medium
810

A project manager is defining the roles and responsibilities for a project. Which TWO of the following are typical responsibilities of the project sponsor? (Select TWO).

Easy
811

A project has been delayed due to unexpected regulatory changes. The project manager has analyzed the impact and determines that the project will miss the original deadline by two months. The sponsor is concerned about the delay. What is the first step the PM should take?

Hard
812

A project manager is preparing a report for stakeholders that lists project risks, their impact, and response strategies. Which document should be used?

Medium
813

A project is closing. The project manager collects feedback from the team on what went well and what could be improved. Which document is being created?

Hard
814

During project execution, a team member reports that a key deliverable will be delayed by two weeks due to an unforeseen technical issue. The project manager evaluates the change and determines the impact on the critical path. According to best practices, what should the project manager do first?

Medium
815

A project manager is working on a project with a fixed-price contract. The customer requests a significant change that will increase the project scope and cost. The project manager documents the change and submits it to the change control board (CCB). Which of the following is the MOST likely outcome if the CCB approves the change?

Medium
816

A project manager has been assigned to lead a project that will deploy a new enterprise resource planning system across five regional offices. Executive leadership has emphasized that the go-live date cannot move because of a regulatory deadline, and the budget has been capped. During planning, the project manager realizes the team cannot deliver the full original feature set within the fixed time and budget. Which TWO actions should the project manager take to address this situation? (Choose two.)

Hard
817

Which of the following best describes a program?

Easy
818

A project manager is leading a project to virtualize a company's physical servers. The project team is evaluating hypervisors and needs to ensure that the chosen solution supports live migration of virtual machines and high availability. Which two features should the project manager verify are supported by the hypervisor? (Choose two.)

Medium
819

A project team is using a document management system with version control. A team member accidentally overwrites the latest version of the project charter with an older draft. What is the BEST way to recover the correct version?

Hard
820

During project execution, a team member proposes a change that will affect the scope baseline. What is the first step the project manager should take?

Hard
821

A project team is using Jira for agile development. They have a list of features to be developed over multiple sprints. What is the term for this list, which represents all the work planned for the project?

Medium
822

A project has a budget at completion (BAC) of $200,000, earned value (EV) of $120,000, and actual cost (AC) of $130,000. What is the estimate at completion (EAC) if the cost performance is expected to continue?

Hard
823

In an Agile project, the team uses a tool to manage user stories and tasks. Which tool is specifically designed for Agile project management, supporting Scrum and Kanban boards?

Easy
824

In an agile project, the team is using user stories to capture requirements. Which of the following is the correct format for a user story?

Medium
825

In a fixed-price contract, which party bears the risk of cost overruns?

Easy
826

During execution of a construction project, a subcontractor uncovers an unrecorded underground utility line, forcing a redesign of a foundation section. The project manager records this in the issue log and submits a change request. Which characteristic of this event determines how it should be classified and handled through the change control process?

Hard
827

During the executing phase, a project manager observes that team members are starting to collaborate and share ideas openly. According to Tuckman's stages of team development, which stage is the team likely in?

Medium
828

A project manager is calculating the Expected Monetary Value (EMV) for a risk event. The probability of the risk occurring is 20%, and the impact if it occurs is $50,000. What is the EMV?

Hard
829

An agile team uses story points to estimate user stories. During planning poker, one developer consistently gives much higher estimates than the rest of the team. What is the best action for the team?

Medium
830

A project manager is estimating the cost of a new software development project. They use historical data from a similar project to derive the cost per function point and multiply it by the expected number of function points. Which estimation technique is being used?

Medium
831

During project execution, a critical team member is assigned to another project and is no longer available full-time. The project manager updates the issue log and tries to negotiate with the functional manager for an alternative. However, the issue cannot be resolved at this level. What is the next step according to issue management best practices?

Medium
832

A project manager wants to identify the most significant causes of delays in a software development project. Which quality tool should she use to prioritize the causes based on the Pareto principle?

Medium
833

A project manager is developing the project charter. Which of the following should be included as a key element of the project charter?

Easy
834

A project is in the Monitoring and Controlling phase. A change request has been submitted to add a new feature. The change control board (CCB) has approved the change. Which THREE actions should the project manager take next?

Hard
835

Which THREE are common types of project organizational structures? (Choose three.)

Hard
836

During a sprint review, the team shows that they completed 30 story points this sprint, which is consistent with their average velocity. The product owner asks how much work the team can likely complete in the next two sprints. Using velocity, what is the best estimate?

Medium
837

A project manager is overseeing the deployment of a new VoIP system across a corporate campus. The project sponsor asks the project manager to provide a document that outlines the technical specifications, including supported protocols, codecs, and bandwidth requirements, to ensure compatibility with the existing network. Which document should the project manager provide?

Medium
838

During a project, the team adds extra features to a deliverable because they believe it will increase customer satisfaction, even though the features were not specified in the requirements. This is an example of:

Medium
839

A large software development project is using a waterfall life cycle. The project has just completed the design phase, and the project manager is scheduled to conduct a phase gate review before proceeding to coding. The project sponsor, under pressure from upper management to deliver faster, asks the project manager to skip the gate review to save one week and move directly to coding. The sponsor argues that the design is sound and the review is a formality. What should the project manager do?

Hard
840

During project planning, the project manager wants to ensure that all work is defined and that no work is omitted. Which tool or technique should be used?

Medium
841

A project team is estimating costs for a new software development project. They use data from a similar previous project and adjust for size differences. Which estimating technique is being used?

Medium
842

A project manager is leading a software upgrade project. The project is using an agile methodology with two-week sprints. After three sprints, the team has not completed all planned user stories, and the product owner is frustrated. The project manager reviews the velocity and finds it is 30% lower than estimated. The team cites unforeseen technical debt. What should the project manager do?

Medium
843

During project execution, a team member reports that a critical deliverable is behind schedule due to an unexpected dependency. The project manager needs to update the project schedule and communicate the impact. Which tool should the project manager use first to assess the impact on the critical path?

Hard
844

A project manager is closing out a fixed-price construction project. All deliverables have been accepted, final payment has been received, and the product has been transitioned to the operations team. The project manager is now compiling the final report and archiving records. Which of the following BEST describes the purpose of this activity?

Medium
845

A project manager is preparing a project charter. Which of the following should be included in the charter?

Medium
846

Put the steps for creating a work breakdown structure (WBS) in the correct order.

Medium
847

You are the project manager for a large infrastructure project that involves upgrading the network switches across five regional offices. The project has a budget of $500,000 and a deadline of six months. During the third month, you receive a report that the vendor has encountered a manufacturing defect in the switches, causing a two-month delay. Additionally, the cost to replace the defective switches will be $100,000 over budget. The project sponsor is concerned about the impact on the business and wants to know the best way to move forward. There is a possibility that the vendor can expedite shipping for an additional $50,000, but it will only save one month. Alternatively, you can switch to a different vendor, but that would require renegotiating contracts and retesting, adding three months to the schedule. Another option is to descope one of the regional offices to reduce costs and time. However, that office is critical for an upcoming product launch. What is the BEST course of action for the project manager?

Hard
848

Which cost estimation technique uses historical data from similar projects to estimate the current project?

Easy
849

During a software development project, the team estimates story points using planning poker. A story is estimated at 8 points, while a similar story was previously estimated at 5 points. What is the primary reason for using relative sizing with story points?

Medium
850

A project is in execution when a critical vendor fails to deliver a key component. The project manager determines this will push the project past the deadline. After submitting a change request, what should the project manager do next?

Hard
851

A project manager is evaluating two project proposals. Proposal A has an NPV of $50,000 and a payback period of 2 years. Proposal B has an NPV of $30,000 and a payback period of 1.5 years. Which proposal is more financially beneficial based on NPV?

Medium
852

During scope verification, the project manager requests formal acceptance of a deliverable from the customer. The customer refuses to sign, stating the deliverable does not meet acceptance criteria. What should the project manager do next?

Medium
853

In a manufacturing project, the team uses a Pareto chart to analyze defects. The chart shows that 80% of defects come from 20% of the causes. Which principle does this illustrate?

Medium
854

A project manager wants to document knowledge gained during the project to help future projects. Which document should be used?

Easy
855

A project is deploying a new virtualized server environment. The project manager receives a report that resource pooling is inefficient. Which technology can best improve resource utilization across the virtual hosts?

Hard
856

A project is in execution, and the project manager discovers that a key resource is overallocated. Which of the following actions should the project manager take to resolve this?

Hard
857

A project manager is creating a document that defines the project's objectives, key stakeholders, high-level requirements, and initial budget. Which document is this?

Easy
858

A project manager is assigned to a new software development project with clearly defined requirements and minimal expected changes. Which project management methodology is most appropriate for this scenario?

Easy
859

A project schedule is displayed as a bar chart showing tasks against a calendar. Which tool is being used?

Easy
860

A project manager has just received formal approval of the project charter from the sponsor. The organization uses a predictive (waterfall) approach and requires a documented baseline before any build work begins. Which activity should the project manager perform NEXT in the project life cycle?

Easy
861

A project is in the execution phase. The project manager discovers that the actual cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 0.9. What does this indicate about the project?

Hard
862

Which TWO of the following are characteristics of a project? (Choose two.)

Easy
863

Which TWO of the following are key components of IT infrastructure that a project manager should consider when planning a new software deployment? (Choose two.)

Medium
864

In a construction project, the foundation must be completed before the framing can begin. This is an example of which type of dependency?

Medium
865

During project execution, a key stakeholder requests a change that would require additional funding. The project manager should:

Medium
866

What is the primary purpose of a Work Breakdown Structure (WBS) in project planning?

Easy
867

A project manager is reviewing the communication plan. Which THREE elements must be included to ensure effective project communications? (Choose three.)

Hard
868

A project manager is estimating the cost of a new software development project. Since the project is similar to a previous one, the manager uses the cost of the previous project as a basis, adjusting for known differences. Which cost estimation technique is being used?

Medium
869

A small consulting firm is considering taking on a new project to develop a custom software application for a client. The firm has limited resources, and the owner, who is also the project manager, must decide whether to accept the project. The client has offered a fixed price of $50,000 with a six-month deadline. The firm estimates that the project will require 800 hours of work from a senior developer and a junior developer. The senior developer is currently assigned to another project that will last another four months, while the junior developer is available full-time. The owner has a decent cash reserve but is concerned about overextending the team. What should the owner do FIRST?

Easy
870

A project manager is reviewing the project's risk register and wants to prioritize risks for further analysis. The project manager decides to use a tool that plots risks based on their probability of occurrence and potential impact. Which tool is the project manager using?

Medium
871

During project planning, the team creates a hierarchical decomposition of the total scope of work to be carried out by the project team. Each descending level represents an increasingly detailed definition of the project work. What is this called?

Medium
872

A project team is facing a critical issue that the project manager cannot resolve. According to best practices, what should the project manager do?

Medium
873

A project manager is leading the deployment of a new VoIP system across three office locations. The project sponsor wants to understand what type of network topology would provide redundancy if a single link between two switches fails. Which topology should the project manager recommend?

Easy
874

A project manager is creating the project management plan. Which TWO subsidiary plans should be included? (Select TWO.)

Medium
875

A project manager notices that the actual cost (AC) is $50,000, the earned value (EV) is $45,000, and the planned value (PV) is $55,000. Which statement is true regarding schedule and cost performance?

Medium
876

In an agile project using Jira, the product owner wants to prioritize the work for the next iteration. Which document or artefact should they refer to?

Easy
877

Midway through a six-month project, the project manager notices that the team has completed 40 percent of the planned work but has consumed 60 percent of the budget. The sponsor asks for a forecast of the total cost at completion based on current performance. Which earned value metric should the project manager use to answer this question?

Hard
878

A project team is in the process of obtaining seller responses, evaluating proposals, and awarding a contract. Which procurement document is used to formally request a proposal from potential sellers?

Medium
879

A project manager is leading a project to implement a new Voice over IP (VoIP) system across multiple offices. The project manager needs to ensure the network infrastructure can support the VoIP traffic. Which TWO factors should the project manager verify? (Choose two.)

Medium
880

You are a project manager for a marketing campaign project. The project has just been initiated, and you are working with the sponsor to identify key stakeholders. The project involves multiple departments: marketing, sales, IT, and legal. One of the stakeholders from sales has expressed strong opposition to the project, claiming it will redirect resources away from ongoing sales initiatives. The project sponsor is concerned this stakeholder might try to block the project. What is the first step you should take to manage this situation?

Easy
881

A project manager is developing a network diagram and needs to represent an activity that can start only after its predecessor has finished. Which dependency type does this describe?

Medium
882

A project manager notices that a task is taking longer than planned and the project is falling behind schedule. The project manager wants to identify the root cause of the delay. Which quality tool would be most appropriate?

Medium
883

Which THREE of the following are project management knowledge areas as defined in the PMBOK Guide?

Hard
884

A project manager is leading a software upgrade project and wants a single document that lists all project stakeholders, their roles, and their communication requirements. Which document should the project manager create?

Easy
885

A project manager is closing a project. Which THREE activities are part of the project closure process? (Select THREE).

Medium
886

During the initiating phase of a project, a project charter is created. Which of the following is typically included in a project charter?

Easy
887

A project manager is developing the project schedule and needs to determine the earliest date the project can finish. The team has identified all activities and their dependencies. Which technique should the project manager use?

Medium
888

A project manager is evaluating risk responses. For a risk with high probability and high impact, which risk response strategy is most appropriate to eliminate the threat?

Medium
889

A project manager is updating the project charter and needs to document the measurable criteria that will be used to determine whether the project is successful, such as reducing processing time by 20% within six months. Which element of the project charter is the project manager defining?

Easy
890

A project to migrate on-premises email to Office 365 is behind schedule. The project sponsor asks the project manager to add more resources to accelerate the timeline. The project manager should first:

Hard
891

Which document formally authorizes a project and assigns the project manager?

Easy
892

A project is behind schedule due to underestimation of task durations. The project manager needs to compress the schedule without increasing costs. Which technique should the project manager consider?

Hard
893

A project manager is planning a marketing campaign for a new product launch. The campaign has a tight budget and strict deadline. During execution, the marketing team proposes adding a social media component that was not in the original scope. The project manager is concerned about scope creep. Which TWO actions should the project manager take to manage this situation?

Medium
894

A project manager is leading a project to develop a new mobile application. The team is distributed across three time zones. The project manager needs to ensure that all team members have access to the latest project documents and can collaborate in real time. Which of the following tools is BEST suited for this purpose?

Easy
895

A project manager is developing a project charter. Which of the following is typically included in the project charter?

Medium
896

During a server migration project, the team discovers that the new servers have a different CPU architecture than the old ones. The project manager must decide the best course of action. What should the project manager do first?

Medium
897

A project team is developing a new software product. The product owner frequently changes priorities based on customer feedback. The team needs to adapt quickly and deliver value incrementally. Which project management methodology is most suitable?

Medium
898

A project involves integrating an on-premises IT infrastructure with a public cloud provider. The project team must ensure secure connectivity. Which of the following should be implemented?

Hard
899

Which of the following best defines a project?

Easy
900

A project manager is working on a project to upgrade the company's email system from an on-premises Exchange server to Microsoft 365. The project has completed the planning phase and is now in execution. During a weekly status meeting, the lead engineer reports that the initial migration batch of 100 users experienced significant delays due to unexpected compatibility issues with custom email add-ins used by the finance department. Additionally, the migration tool failed to synchronize some mailbox items, causing data loss for three users. The project timeline is tight, and the sponsor is concerned about meeting the go-live date in four weeks. There are still 900 users to migrate. The project manager needs to take action. Which of the following is the BEST course of action?

Hard
901

A collection of projects and programs managed together to achieve strategic objectives is known as a:

Easy
902

Which THREE of the following are outputs of the project initiation process? (Choose three.)

Medium
903

A project manager is preparing a presentation for the steering committee. The PM wants to show the cumulative planned value, earned value, and actual cost over time to illustrate cost and schedule performance trends. Which tool or technique should the project manager use?

Medium
904

A project manager is updating the issue log for a new issue: a critical supplier has gone out of business, causing a shortage of materials. Which TWO fields are essential to include in the issue log entry?

Medium
905

A project sponsor has requested a document that provides a high-level overview of the project, including business need, key assumptions, constraints, and initial risks. Which document should the project manager provide?

Medium
906

A project team is estimating the duration of a task. The optimistic estimate is 4 days, the pessimistic is 12 days, and the most likely is 6 days. Using the three-point estimating technique (PERT), what is the expected duration?

Easy
907

Put the steps for closing a project in the correct order.

Medium
908

A project team is in the execution phase and the project manager notices that the actual cost is consistently higher than planned. Which process should be used to address this?

Easy
909

A project manager is reviewing the key components of a project management plan. Which THREE of the following are typically included in a project management plan?

Hard
910

During a sprint planning meeting, the development team estimates user stories using story points. They each have a set of cards with values like 1, 2, 3, 5, 8, 13. After discussing a story, all team members simultaneously reveal their chosen card. What technique are they using?

Medium
911

A project manager is creating the WBS. Which THREE of the following are characteristics of a well-constructed WBS?

Medium
912

A project team is experiencing conflicts and power struggles among members. According to Tuckman's stages of group development, which stage is the team likely in?

Medium
913

In which organizational structure does a project manager have the highest level of authority?

Easy
914

A project manager joins an initiative that will deliver a mobile banking feature. Regulatory requirements are stable and well documented, but the marketing team keeps revising the desired user experience every few weeks. The organization wants early feedback from real customers while limiting rework on the regulated components. Which approach BEST fits this project?

Medium
915

A project manager is performing schedule compression because the project is behind schedule. The team decides to start a follow-on activity before its predecessor is fully completed. This approach increases the risk of rework. Which schedule compression technique is being used?

Medium
916

A project manager is evaluating two potential projects. Project A has an NPV of $50,000, while Project B has an NPV of -$10,000. Which project should the organization select based solely on NPV?

Hard
917

A project manager is updating the risk register after a risk event occurred. The risk response plan included a contingency reserve, but the actual impact was higher than expected. What should the project manager do next?

Hard
918

Which TWO tools are commonly used for risk identification in a project?

Easy
919

A project manager has identified a risk with a probability of 0.4 and an impact of $50,000. What is the risk score?

Medium
920

You are a project manager for a construction project. During the monitoring and controlling phase, you review the project performance and find that the earned value (EV) is $50,000, the actual cost (AC) is $60,000, and the planned value (PV) is $55,000. The project is behind schedule and over budget. The project team is demotivated due to the delays. The customer has expressed concerns about project progress. The project contract includes a penalty clause for missed milestones. Which of the following actions should you take first?

Hard
921

A project manager is preparing a presentation for the steering committee and wants to show the project's planned start and finish dates, key milestones, and major deliverables in a single high-level visual. Which tool should the project manager use?

Medium
922

A project manager is reviewing project selection methods. Which method calculates the present value of future cash flows minus the initial investment?

Medium
923

A project manager is reviewing the project's earned value data. The cost performance index (CPI) is 0.85, and the schedule performance index (SPI) is 1.05. What does this indicate about the project?

Hard
924

What is the primary difference between a risk and an issue in project management?

Easy
925

Which THREE are examples of direct costs in a project? (Select THREE.)

Hard
926

A project has a BAC of $200,000. After three months, the earned value (EV) is $80,000 and the actual cost (AC) is $90,000. What is the cost variance (CV) and what does it indicate?

Medium
927

Which document is used to track and manage changes to the project baseline?

Easy
928

Refer to the exhibit. A project manager is monitoring server performance for a web application deployment. Based on the exhibit, what is the status of the web server?

Easy
929

Which TWO of the following are methods of schedule compression? (Select TWO).

Easy
930

A project manager is preparing a benefits realization plan for a project that will replace a legacy order-processing system. The sponsor asks how the team will confirm that the intended business value is actually achieved after the system goes live. Which action should the project manager take to address the sponsor's concern?

Medium
931

Match each project management methodology or framework to its key characteristic.

Medium
932

A project is transitioning from the planning phase to the executing phase. The project manager must ensure the team is prepared to begin work. Which THREE activities should be performed during this transition? (Choose three.)

Hard
933

A project manager is preparing a procurement document that asks vendors to provide a price for a specific product. Which type of document is this?

Easy
934

A project manager is reviewing the schedule performance and finds that the earned value (EV) is $50,000 and the planned value (PV) is $60,000. What does this indicate?

Medium
935

A project manager is using a control chart to monitor quality. The data points fall within the control limits but show a run of seven points above the mean. What does this indicate?

Hard
936

During project execution, a stakeholder requests an additional feature. The project manager documents the request and evaluates its impact on the triple constraint. Which process is being performed?

Medium
937

A project manager is assigned to a program that includes multiple projects aimed at digital transformation. Which TWO statements correctly describe the relationship between projects, programs, and portfolios? (Select TWO).

Hard
938

A project manager is planning a software development project and needs to determine the sequence of activities. The team will first gather requirements, then design the architecture, then develop the code, then test, and finally deploy. Which project life cycle model is being used?

Easy
939

A company is implementing a new backup solution for its mixed environment of legacy and modern servers. The backup server is connected to the same network segment as production traffic. During initial testing, some backups fail intermittently, especially during peak hours. The backup logs show timeouts. The project manager is asked to identify the most likely cause and recommend a solution. Which of the following is the best course of action?

Easy
940

Which TWO documents are typically created during project initiation?

Easy
941

You are the project manager for a software upgrade project at a mid-sized company. The project has a budget of $500,000 and a timeline of 12 months. The team consists of 10 members, including developers, testers, and a business analyst. The project is in month 8, and the team has completed 60% of the work but has spent $400,000. The sponsor is concerned about the budget overrun and asks for a recovery plan. The original estimate at completion (EAC) was $500,000. Using earned value management, you calculate the cost performance index (CPI) is 0.75 and the schedule performance index (SPI) is 0.90. The team is demoralized due to scope creep and unclear requirements. The business analyst recently left, and the replacement is not yet fully onboarded. Which of the following is the BEST course of action to bring the project back on track?

Hard
942

A project manager is leading a construction project. The project sponsor has requested that the project be completed one month earlier than originally planned. Which THREE actions should the project manager take to assess the feasibility of this request? (Choose three.)

Hard
943

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following statements is TRUE?

Hard
944

A project manager receives a status report showing that the project is behind schedule. The report uses a red-yellow-green status indicator. What does the red indicator typically signify?

Hard
945

Which document contains the subsidiary plans for scope, schedule, cost, quality, resources, communication, risk, and procurement?

Easy
946

During the planning phase, a project manager conducts a stakeholder analysis. Which of the following is the primary purpose of this activity?

Medium
947

A project manager is selecting tools for agile project management. Which TWO tools are specifically designed for agile methodologies?

Medium
948

Which document defines the roles and responsibilities of stakeholders in a project and is often presented as a matrix?

Medium
949

A project manager is using a quality tool that displays data points over time with upper and lower control limits. The tool helps distinguish between common cause and special cause variation. Which tool is this?

Medium
950

During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?

Easy
951

A project manager is identifying stakeholders and documenting their interests and influence. In which project life cycle phase is this activity performed?

Easy
952

A vendor is hired to provide a service with a fixed price of $100,000, regardless of actual costs incurred. Which contract type is this?

Medium
953

A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?

Hard
954

A project manager is in the Closing phase of a project to implement a new customer relationship management (CRM) system. The project scope has been completed, and the product has been accepted by the customer. Which activity should the project manager perform next?

Hard

Frequently asked questions

What does the scenario questions domain cover on the PK0-005 exam?
scenario questions questions test whether you can apply the concept in context, not just recognise a definition.
How many questions are in this domain?
This page lists all 954 scenario questions questions in the PK0-005 question bank. The actual exam draws from this domain proportionally to its weighting in the official exam blueprint.
What is the best way to practise this domain?
Start with a short focused session (10 questions) to identify gaps, then work through explanations. Repeat with a longer session once the weak areas feel solid.
Can I practise only scenario questions questions?
Yes — the session launcher on this page filters questions to this domain only. Choose any session length for inline explanations and scoring.