PK0-005 · domain
scenario questions
Practise CompTIA Project+ PK0-005 scenario questions practice questions — original exam-style scenarios with answer choices, explanations, and analysis of common mistakes.
Focused practice
Practice scenario questions questions
Scored sessions drawing only from this domain — pick a length below.
Start 20-question practice test →What this domain covers
What to know about scenario questions
scenario questions questions test whether you can apply the concept in context, not just recognise a definition.
How the topic appears in realistic exam-style scenarios.
Which detail in the question changes the correct answer.
How to eliminate plausible but wrong options.
How to connect the question back to the wider exam objective.
Watch out for
Common scenario questions exam traps
- ▸Answering from memory before reading the full scenario.
- ▸Missing a constraint such as cost, availability, security, scope or command context.
- ▸Choosing a broad answer when the question asks for the most specific fix.
- ▸Ignoring why the wrong options are tempting.
Question index
All scenario questions questions (980)
Click any question to see the full explanation, or start a practice session above.
Which THREE of the following are responsibilities of a project manager? (Select THREE).
Hard2In a project, the critical path has a duration of 100 days. Activity X on the critical path has a duration of 10 days and can be crashed to 7 days at an additional cost of $3,000. What is the crash cost per day for Activity X?
Hard3During project execution, the project manager notices that the team is struggling with communication, and key stakeholders are not receiving timely updates. Which THREE documents should the project manager review to improve the situation? (Select THREE).
Hard4A project manager is tracking remaining work over the course of a sprint to see if the team is on pace to complete all committed stories. Which agile artifact should the project manager use?
Easy5Which THREE of the following are generally considered to be part of the project management process groups?
Hard6During a phase gate review, the review board determines that the project does not yet meet the exit criteria for the current phase. What is the most likely outcome?
Hard7A project manager is using a schedule compression technique that adds resources to critical path activities to shorten the project duration. Which technique is being used?
Hard8A project manager is using a predictive life cycle for a software development project. What is a key characteristic of this approach?
Hard9Which stakeholder role is typically responsible for providing resources and support for the project?
Easy10A project to upgrade network infrastructure is behind schedule due to unforeseen compatibility issues. The project manager has already used all management reserve. Which action best aligns with the control schedule process?
Hard11Refer to the exhibit. Which WBS element is the highest level of decomposition shown?
Hard12During project execution, a key stakeholder requests additional features that were not originally approved. The project manager is concerned about scope creep. Which type of project constraint is most directly impacted by scope creep?
Hard13A project manager is estimating the cost of a software development project. Using data from a similar past project, she adjusts for size and complexity. Which estimation technique is she using?
Medium14The project manager receives a defect report for CI-103. The team identifies that a new requirement necessitates updating CI-103. According to the configuration management process, what should the project manager do FIRST?
Medium15A project team is working on a software development project and needs to track changes to requirements, design documents, and source code. They want to ensure that all team members can access the latest versions and that changes are logged with the author and timestamp. Which type of tool should the project manager implement to meet these needs?
Medium16During project execution, a team member identifies a potential risk that was not included in the risk register. The project manager logs it and begins the risk assessment process. Where should this risk be recorded?
Hard17A project has an issue where a key deliverable fails quality inspection. The project manager escalates to the project sponsor, but the issue remains unresolved. Which THREE actions should the project manager take according to issue management best practices?
Hard18Which TWO documents should be included in the procurement management plan? (Select TWO).
Medium19Which TWO documents are typically created during the project initiating phase?
Easy20Which project management tool displays project tasks against a timeline and shows dependencies?
Easy21A project is being executed in a matrix organization. The project manager discovers that a functional manager is reassigning a key team member to another project without notice. What should the project manager do first?
Hard22Which of the following is an output of the Close Project or Phase process?
Easy23Arrange the steps for performing procurement management.
Medium24A project team is developing a WBS. Which THREE of the following are characteristics of a well-constructed WBS?
Medium25Which THREE of the following are components of the project management plan as defined in the PMBOK Guide?
Medium26A project team is experiencing frequent scope changes. The project manager wants to ensure that all changes are properly reviewed and approved. Which document should the project manager reference?
Medium27You are a project manager for a software development company that uses an Agile methodology with two-week sprints. The team uses Jira for task tracking and Confluence for documentation. During the latest sprint review, stakeholders expressed confusion about the current project status because the burndown chart shows a steady increase in remaining work. Upon investigation, you discover that the development team has been adding new tasks to the current sprint without updating the sprint backlog or adjusting the scope. The product owner is unaware of these additions. The team complains that they are overworked and missing deadlines. Which of the following is the BEST course of action to address the situation?
Medium28A software development project is currently in the execution phase. The project manager has a team of 10 developers and 2 testers. The project is scheduled to be completed in 6 months, with a budget of $500,000. At the end of month 3, the project manager reviews the status and finds that only 40% of the work is complete, whereas 50% was planned. The actual cost incurred is $280,000. The project manager calculates the CPI as 0.71 and the SPI as 0.80. The project sponsor is concerned and asks for a recovery plan. The project manager must decide the best course of action. Which action should the project manager take?
Hard29A project has a CPI of 0.9 and an SPI of 1.1. Which two statements are true? (Select TWO.)
Medium30In a RACI matrix, which role is responsible for performing the work?
Medium31A project team member is consistently late in completing assigned tasks, affecting the critical path. The project manager should FIRST:
Medium32A project manager is reviewing quality control results. Which THREE tools are commonly used to identify the root causes of defects or to prioritize improvement efforts? (Choose three.)
Medium33A company is deploying a new VoIP system. Which network infrastructure component is most critical for ensuring voice quality?
Easy34A project manager is leading a team to develop a new mobile application. The project has a fixed budget and a strict deadline. During the execution phase, the stakeholder requests additional features that were not originally planned. Which project constraint is most directly affected by this request?
Easy35A project team is using Jira for an agile project. The product owner wants to see the total amount of work completed each sprint and the remaining work. Which two charts should the project manager use? (Choose two, but this is a multiple-choice single select for the best pair. Actually, this is a multiple-choice question asking for a single best tool.)
Medium36A control chart shows a process with data points fluctuating within the upper and lower control limits, but 8 consecutive points appear on one side of the mean. What does this indicate?
Hard37Which THREE of the following are best practices for managing IT infrastructure projects? (Choose three.)
Hard38Which of the following is the primary purpose of a feasibility study during the initiating phase?
Medium39A project manager is creating a communication plan. Which tool is BEST for tracking the status of project deliverables and their approval?
Easy40A project manager is leading a data center migration project for a financial services company. The project involves moving 50 servers from an on-premises facility to a co-location data center. The project has a strict deadline of December 31 due to lease expiration. The team has completed 60% of the work with 70% of the budget spent. The project manager notices that the co-location provider has been consistently late in provisioning network circuits, causing delays. Additionally, the team discovered that two servers have incompatible hardware with the new environment, requiring reconfiguration. The project sponsor is pressuring the team to finish on time. What should the project manager do FIRST?
Hard41In which type of organizational structure does the project manager have the least authority?
Medium42A project manager is leading a software development project that has a fixed budget and strict deadline. During the execution phase, the development team identifies a critical security vulnerability that requires immediate remediation, which will add two weeks to the schedule and increase costs by 10%. What is the BEST course of action for the project manager?
Medium43Which project scheduling tool displays tasks as horizontal bars on a timeline, shows dependencies between tasks, and can highlight the critical path?
Easy44A project manager is overseeing a manufacturing process improvement project. During the monitoring and controlling phase, the project manager notices that the project is two weeks behind schedule due to unexpected machine downtime. The team suggests reducing the amount of testing on the new equipment to recover the schedule. The project sponsor is concerned about meeting the deadline and supports the team's suggestion. What should the project manager do?
Hard45A project manager is working in a matrix organization. The project team members report to both the project manager and their functional managers. The project manager has moderate authority and shares resources. This type of matrix is known as:
Medium46A project team is developing a new mobile application. During execution, a stakeholder requests additional features that were not in the original scope. The project manager is concerned about scope creep. Which TWO actions should the project manager take to manage this request? (Select TWO).
Easy47A project manager is selecting a project from several proposals. The project with the highest Net Present Value (NPV) also has the longest payback period. Which TWO factors should the project manager consider when recommending this project? (Select TWO).
Medium48A project manager is creating a work breakdown structure (WBS) for a software development project. Which technique is most effective for decomposing the project scope into manageable components?
Medium49During a quality audit, the project team discovers that 80% of customer complaints are caused by 20% of the defect types. Which quality tool should the project manager use to present this data and prioritize corrective actions?
Hard50A project team is experiencing conflicts due to unclear roles and responsibilities. Which document should the project manager refer to in order to clarify team members' roles?
Easy51A project manager is analyzing the critical path of a network diagram. Which TWO statements about the critical path are true?
Medium52A project manager is estimating costs for a new project using a top-down approach based on historical data from a similar project. Which estimation technique is being used?
Medium53A project manager is evaluating two project proposals. Project A has an initial investment of $100,000 and is expected to generate cash flows of $30,000 per year for 5 years. Project B has an initial investment of $50,000 and cash flows of $20,000 per year for 3 years. Using payback period, which project should be selected?
Hard54A project team is working on a software development project. The project manager needs to track which team members are assigned to each task. Which document provides this information?
Easy55A project team is sharing documents via email but experiencing version confusion. Which tool should the PM implement to improve version control?
Medium56A project team discovers a problem that is currently happening and affecting project deliverables. The project manager needs to document this situation. Which document should be used to record this?
Easy57Which document contains the deliverables, acceptance criteria, exclusions, assumptions, and constraints for a project?
Easy58A project team is using an agile methodology to develop a new feature. The product owner frequently reprioritizes the backlog based on changing customer needs. Which characteristic of agile does this BEST illustrate?
Medium59A project manager is using the power/interest grid to classify stakeholders. Which group should be managed most closely because they have high power and high interest?
Medium60While monitoring and controlling, the project manager reviews earned value metrics and finds CPI = 0.8 and SPI = 1.1. What does this indicate?
Medium61A project manager is developing a communication plan. The project has team members in three countries with different time zones. Which communication method is most effective for daily status updates?
Hard62In a RACI matrix, the person who is ultimately accountable for the completion of a task is denoted by which letter?
Easy63During a project, a stakeholder requests additional features that were not in the original scope. The project manager adds these features without formal change control. This is an example of:
Hard64A company wants to select a project based on the time it takes to recover the initial investment. Which project selection method should be used?
Easy65A multinational company is undertaking a new software implementation project across three regions: North America, Europe, and Asia. The project manager has created a detailed project plan with resources from each region. However, the North American team lead insists on using a different project management methodology than the other regions, claiming it's more efficient. The European team lead is concerned about integration issues. The Asian team lead is neutral. The project manager needs to decide how to proceed. Which approach is BEST?
Hard66A stakeholder requests a copy of the project's requirements documentation. Which document would the project manager provide to meet this request?
Easy67A project manager is updating the risk register after identifying a new risk. Which TWO fields are typically included in a risk register? (Select TWO).
Medium68During project planning, the project manager wants to identify all documents that will be created and maintained throughout the project. Which project document should the project manager create?
Medium69Which diagram is used in quality management to prioritize the most significant causes of a problem, based on the 80/20 rule?
Medium70A project manager is preparing a request for proposal (RFP) for a vendor to provide specialized equipment. Which THREE items should be included in the RFP?
Medium71A project team is conducting a lessons learned session. In which project life cycle phase does this typically occur?
Easy72A project manager is closing a project that delivered a new customer relationship management (CRM) system. The customer has accepted the deliverables, and the team has completed the final project report. Which activity should the project manager perform NEXT?
Easy73Which TWO documents are used to track changes that occur during a project? (Select TWO)
Easy74Which TWO documents are typically used to formally document and communicate a project's acceptance criteria and final deliverables?
Medium75A project manager wants to visualize the sequence of project activities and their dependencies to identify the critical path. Which tool should be used?
Easy76A change request is submitted to add a new feature to a project. What is the first step the project manager should take?
Medium77A company is implementing a new enterprise resource planning (ERP) system. The project is in the execution phase. The project manager receives a report that during user acceptance testing (UAT), 15 critical defects were found. The defects are related to incorrect calculation logic in the financial module. The testing team estimates that fixing these defects will require two additional weeks of work by the development team. The project sponsor is concerned about the schedule delay and asks the project manager to proceed with the go-live as planned and fix the defects after go-live. The project manager must decide the best course of action. What should the project manager do?
Hard78A senior manager is comparing two projects for selection. The manager wants to use a method that considers the time value of money. Which TWO project selection methods incorporate the time value of money?
Medium79You are a project manager for a software development project. The team uses a cloud-based project management tool that includes features like task assignment, Gantt charts, and document storage. During a status meeting, a team member reports that they cannot find the latest version of the project schedule. Several team members have been updating the schedule file directly on the shared drive without version control. As a result, the file has multiple conflicting copies. You need to resolve this issue and prevent it from recurring. Which course of action should you take?
Easy80You are the project manager for an IT project to upgrade the company's network infrastructure. The project has a schedule baseline approved, and the team is using Agile methodology due to changing requirements. During the second sprint, a key stakeholder requests a new feature that was not originally planned. The team is concerned this will impact the sprint goal. The project is being tracked with a burn-down chart, and the velocity so far is 30 points per sprint. The product owner is hesitant to include the new feature because it will increase the scope and delay the release. As the project manager, what should you do?
Medium81A project manager receives a status report showing that the project's SPI is 0.9. What does this indicate?
Easy82A project manager is starting a new project and needs to define the project life cycle. Which document should the project manager consult to determine the phases and deliverables?
Easy83A project manager is leading a software development project with stable requirements and a fixed budget. The team prefers a sequential approach with clear phases. Which methodology is most appropriate?
Medium84A large organization is deploying a new ERP system. The infrastructure team provisions a cluster of virtual machines for the application and a separate database server. During load testing with typical user loads, the database server shows high I/O wait times. The storage administrator confirms that the storage array has sufficient capacity and the disks are healthy. The hypervisor shows no CPU or memory pressure. Which of the following is the most likely cause of the high I/O wait?
Hard85Which TWO of the following are components of a project charter?
Medium86During the execution phase of a software development project, the team discovers a critical bug that was not identified during planning. The project manager needs to decide how to handle the bug without significantly impacting the project scope and timeline. Which action should the project manager take first?
Medium87Order the steps for performing risk management planning.
Medium88An organization has multiple projects that are not directly related but are all aimed at achieving the company's strategic goal of expanding into new markets. Which term best describes this collection?
Medium89A project team is distributed across three time zones. The project manager needs a tool for real-time collaboration, file sharing, and instant messaging. Which type of tool is MOST appropriate?
Easy90Which TWO of the following are key activities performed during the Initiating phase of a project?
Easy91A project manager is using a schedule compression technique that adds resources to critical path activities to shorten the project duration. Which technique is being used, and what is its primary trade-off?
Hard92Which THREE of the following are commonly recognized project constraints according to the Project Management Body of Knowledge (PMBOK)?
Hard93A project is in the execution phase, and a key team member reports that a required resource is not available due to a conflict with another project. Which project management concept should the PM use to resolve this?
Easy94Which THREE tools are commonly used for measuring project performance against the baseline?
Hard95A project manager is reviewing the project management plan and notices that an important deliverable's acceptance criteria are missing. The project is currently in the execution phase. What is the best course of action?
Hard96Match each acronym to its definition in project management.
Medium97An agile team uses a burnup chart to track progress. Which THREE pieces of information are typically shown on a burnup chart?
Medium98A project manager is tracking project performance and notices that the SPI is 0.8 and the CPI is 1.2. What does this indicate about the project?
Hard99A project manager is analyzing stakeholders and categorizes a key executive who has high power and high interest. According to the power/interest grid, how should the project manager engage this stakeholder?
Medium100In a network diagram, the critical path is the longest path through the project. What does it determine?
Medium101During project planning, the project manager creates a network diagram. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. Activities A and B can start immediately. Activity C can start only after Activity A is complete. Activity B has no dependency on others. What is the duration of the critical path?
Medium102A project manager needs to break down the project scope into smaller, manageable components. Which tool should they use?
Medium103A project has a BAC of $500,000 and a CPI of 0.8. What is the estimate at completion (EAC) assuming the current cost performance will continue?
Hard104A project manager identifies a key stakeholder who has high interest in the project but low power to influence decisions. In the power/interest grid, where should this stakeholder be placed?
Easy105During project execution, a team discovers that the actual cost of work performed is $45,000, the planned value is $50,000, and the earned value is $40,000. Which statement is correct?
Medium106A project manager is analyzing quality issues and wants to use tools that help identify and prioritize problems. Which TWO tools are appropriate for this purpose? (Select TWO.)
Hard107A project manager uses Monte Carlo simulation to analyze schedule risks. This technique is used to:
Hard108Which contract type places the most cost risk on the seller?
Medium109A project manager is creating a Work Breakdown Structure (WBS). Which technique is used to break down deliverables into smaller, manageable components?
Medium110A project manager is assigned to a new project and needs to document high-level risks, assumptions, and constraints. Which document should the project manager create first?
Easy111A project manager is defining what work is required to complete the project. Which document should be created first to formally define the scope?
Easy112A project is near completion, but the key stakeholder cannot perform user acceptance testing (UAT) due to prior commitments. What should the project manager do?
Medium113A project manager is reviewing dependencies in the project schedule. Which THREE types of dependencies are recognized in project management? (Choose three.)
Hard114A project has a dependency where the software must be coded before it can be tested. This is an example of which type of dependency?
Medium115Who is typically responsible for providing the project budget and resources, and for resolving issues that are beyond the project manager's authority?
Medium116A project manager is assigned to a new project. The sponsor provides a high-level scope and asks for a cost estimate. Which estimation technique should the project manager use at this early stage?
Easy117A project manager is using a control chart to monitor the number of defects per day. The chart shows 10 data points within the control limits, but all 10 points are above the mean. What does this indicate?
Hard118A project manager is estimating the cost of a software development project. She uses the actual cost of a similar past project and adjusts it for known differences in size and complexity. Which cost estimation technique is she using?
Medium119A project manager at a mid-sized software company is leading a project to develop a new mobile application. The project is in the execution phase, and the team is using an Agile methodology with two-week sprints. The project manager has been using a shared spreadsheet to track tasks, but team members frequently report that they are unsure of what tasks to work on next, and there is confusion about which tasks are blocked. Additionally, the project manager is spending several hours each day updating the spreadsheet and answering questions about task status. The company has a subscription to Jira, but the team has not been using it. The project manager wants to improve visibility and reduce administrative overhead. What should the project manager do first?
Medium120A project manager is reviewing the issue log and notices an issue with high priority that has not been resolved. The project manager has tried to resolve it but cannot. What should the project manager do next?
Medium121During the execution phase of a software development project, the team discovers that the database schema needs to be altered to accommodate a new regulatory requirement. The project manager is reviewing the change request. What is the MOST important factor to consider before approving the change?
Medium122A project manager is developing a communication plan for a software implementation project. The team includes developers, business analysts, and external vendors. Which document should the project manager reference to ensure communication aligns with stakeholder expectations?
Medium123Which document defines how project information is distributed to stakeholders and who receives what information?
Easy124A project manager uses a power/interest grid to categorize stakeholders. Stakeholders with high power and low interest should be managed using which approach?
Medium125A project manager is reviewing the risk register and sees that a high-probability, high-impact risk has a response strategy of 'mitigate' with a planned action to purchase insurance. This is an example of which risk response strategy?
Hard126Which TWO elements are typically included in a risk register? (Choose two.)
Easy127A project manager is assigned to a project that has poorly defined requirements. Which project management methodology would be most suitable to handle this uncertainty?
Easy128During project monitoring and controlling, the project manager calculates the cost performance index (CPI) as 0.8. What does this indicate?
Medium129A project manager is conducting a lessons learned session at the end of a project. Which TWO activities are typically performed during project closure? (Select two.)
Medium130A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. Which TWO statements are true regarding the project's performance? (Choose two.)
Hard131A project has a budget of $100,000 and a duration of 12 months. After 6 months, the project is 50% complete and has spent $60,000. What is the cost variance?
Medium132During a quality audit, the team identifies that defects are concentrated in a few areas. The project manager decides to use a Pareto chart. Which TWO statements are true about Pareto charts?
Hard133In which project life cycle phase are the key performance indicators (KPIs) typically established to measure project success?
Easy134An organization is evaluating two potential projects. Project A has an NPV of $50,000 and a payback period of 2 years. Project B has an NPV of $40,000 and a payback period of 1.5 years. The organization's policy is to select projects with the highest NPV. Which project should be selected?
Medium135A project manager is deploying a new web application to a cloud environment. The application requires high availability and automatic scaling based on traffic. Which IT infrastructure component should the project manager use to meet these requirements?
Easy136A project team is using Agile methodology. The product owner frequently changes priorities during the sprint, causing confusion. What is the most appropriate action for the project manager (scrum master)?
Hard137A project manager notices that project costs are consistently exceeding the budget. Which process should the project manager use to address this issue?
Easy138Which TWO of the following are components of the project management plan?
Medium139Given EV = $80,000 and AC = $90,000, what is the project's cost performance index (CPI) and what does it indicate?
Medium140In an agile project, the team is defining the 'Definition of Done' (DoD). Which TWO statements are typically included in a good DoD?
Medium141Which document is used to formally accept the project deliverables and signify project closure?
Easy142The sponsor asks the project manager to accelerate the project schedule without changing scope. Which technique should the project manager recommend?
Medium143Put the steps for managing a change request in the correct order.
Medium144A project team is using Jira for agile project management. They want to visualize the flow of work across columns such as 'To Do', 'In Progress', and 'Done'. Which board type should they use?
Medium145A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, actual cost (AC) is $120,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost performance index (CPI)?
Hard146During a project, a critical team member is reassigned to a higher-priority project, leaving the project without sufficient resources. This is an example of a(n):
Hard147A project manager is evaluating the benefits of using a project charter. Which TWO of the following are primary purposes of a project charter?
Medium148During a project audit, it is discovered that several deliverables did not meet quality standards. The project manager wants to identify the root causes. Which tool is most appropriate?
Easy149Which project document formally authorizes the project and provides the project manager with the authority to apply organizational resources?
Easy150A project manager is working on a project with high uncertainty and rapidly changing requirements. Which project life cycle model is MOST appropriate?
Hard151Which TWO of the following are examples of key performance indicators (KPIs) used to measure project success?
Medium152After a change request is approved, the project manager updates the project baseline. Which document must also be updated to reflect the impact of the change on project risks?
Medium153In which Tuckman stage do team members begin to resolve their differences, establish norms, and develop closer relationships?
Easy154During project execution, the project manager notices that the team is adding extra features that were not requested by the customer. This is an example of which common project constraint issue?
Medium155Which THREE items are considered agile artefacts?
Medium156Which document formally authorizes the project and assigns the project manager?
Medium157Which TWO are typically outputs of the scope planning process? (Choose two.)
Medium158At the end of a project phase, the team holds a meeting to discuss what went well and what could be improved. Which document is produced from this meeting?
Medium159Which TWO of the following are inputs to the Develop Project Management Plan process?
Medium160Which TWO are common components of a project management plan? (Choose two.)
Medium161A project manager is assigned to a new software development project. During the initiation phase, the project sponsor is hesitant to approve the project charter because the business case does not clearly quantify the expected benefits. The project manager has gathered initial requirements and conducted a feasibility study. What should the project manager do next to move the project forward?
Easy162A project manager wants to visually represent the flow of tasks and decision points in a business process. Which tool should be used?
Medium163During which phase of the project life cycle is the project charter created and stakeholders initially identified?
Easy164During execution, the project manager receives a customer change request to add a significant feature. Analysis shows the change will increase the budget by 15% and extend the schedule by two months. What should the project manager do first?
Hard165A project manager is reviewing the project schedule. Activity A has an early start (ES) of day 1 and an early finish (EF) of day 5. Activity B has an ES of day 6 and an EF of day 10. Activity C has a duration of 2 days and depends on both A and B. What is the total float of Activity B if the project must be completed by day 12?
Hard166A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.8. What does this indicate about the project?
Hard167Which THREE components are typically included in a project management plan?
Hard168Which document formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities?
Easy169A project has a budget at completion (BAC) of $500,000. After 3 months, the earned value (EV) is $200,000, the actual cost (AC) is $250,000, and the planned value (PV) is $180,000. What is the cost performance index (CPI) and what does it indicate?
Hard170A project manager is developing the project charter and needs to identify the key stakeholders who will influence the project's success. Which tool or document should the project manager use to capture this information?
Medium171What is the critical path duration?
Easy172A project manager is closing a project. Which TWO activities are typically performed during the project closure phase?
Medium173A project manager is developing a project schedule and needs to estimate activity durations. Which TWO techniques are commonly used for estimating activity durations? (Choose two.)
Hard174A project manager is leading a cross-functional team that is working together for the first time. The team members are polite but hesitant to share ideas. According to Tuckman's stages of group development, which stage is the team currently in?
Easy175A project manager identifies a risk that could cause a $50,000 loss with a 20% probability. What is the expected monetary value (EMV) of this risk?
Hard176A project manager is selecting a data center for a new application that requires high availability and disaster recovery. Which type of data center arrangement is most appropriate?
Easy177A project manager is developing the communication management plan. Which element should be included to ensure stakeholders receive timely information?
Medium178A project manager is reviewing a change request to add a new feature to a software product. The change will increase the project timeline by two weeks and require additional budget. Which of the following should the project manager do first?
Medium179In a network diagram using PDM, activity B can start only after activity A has finished. Which dependency type does this represent?
Medium180Arrange the phases of the project life cycle in the correct order.
Medium181A project manager is assigning stakeholders to quadrants on a power/interest grid. Which stakeholders require the most active management?
Medium182During project closure, which three activities should be performed? (Select THREE)
Hard183Refer to the exhibit. What is the duration of the critical path?
Easy184Which TWO of the following are key activities typically performed during the planning phase of a project? (Choose two.)
Hard185In the stakeholder power/interest grid, stakeholders with high power and low interest should be managed using which strategy?
Easy186A server administrator is troubleshooting a failed backup job. The backup software configuration specifies a backup volume by its UUID, but the logs indicate that the specified volume cannot be found. What is the most likely cause of the error?
Medium187Which document formally authorizes the project and assigns the project manager?
Easy188An agile team has a velocity of 30 story points per sprint. The product backlog contains 120 story points of work. How many sprints are needed to complete the backlog assuming no changes?
Medium189During project execution, a key stakeholder requests a change that increases scope. According to the project management plan, which document should the project manager update first?
Medium190Which phase has the most total float?
Medium191Refer to the exhibit. What is the total duration of the project?
Medium192During project planning, the project manager is creating a risk register. Which THREE pieces of information are typically included in a risk register? (Select three.)
Medium193A project manager is estimating the cost of a new software development project. She uses the actual cost of a similar past project and adjusts for differences in size and complexity. Which estimation technique is she using?
Medium194A project manager is performing schedule compression. The team decides to start a successor activity before its predecessor is fully complete. Which technique are they using, and what is a primary downside?
Hard195A project manager is developing a network diagram for a software rollout. Activity D (3 days) can start only after Activity C (2 days) finishes, and Activity E (4 days) can start when Activity C starts. Activities D and E must both finish before Activity F (1 day) begins. What type of dependency exists between Activity C and Activity E?
Medium196During project execution, the project manager notices that actual costs are consistently higher than planned. Which process should the project manager use to analyze this variance?
Easy197During a server migration project, the team discovers that the new hardware requires a specific firmware version not currently installed. The project schedule is tight. What is the best course of action?
Hard198A project manager is leading a project to upgrade the storage area network (SAN) for a hospital's electronic health records (EHR) system. The current SAN is reaching capacity and has performance issues during peak hours. The new SAN must support high availability with synchronous replication between two data centers located 10 km apart. The project budget is tight, and the timeline is aggressive. During a risk assessment, the project manager identifies that the fiber optic cable between the data centers is owned by a third-party provider and has a history of outages. The project sponsor is concerned about meeting the go-live date and asks the project manager to recommend a course of action to mitigate the risk of cable outages affecting the SAN replication. Which of the following is the BEST course of action?
Easy199During project planning, the project manager needs to estimate the cost of each work package. Which tool or technique is best suited for this?
Hard200Which of the following is NOT a phase in the typical project life cycle?
Easy201A project has completed the planning phase and is about to begin execution. However, a key stakeholder raises a concern that a critical requirement is missing. What is the best course of action?
Hard202A project manager is leading a construction project. The team identifies a risk that a key supplier may go bankrupt. The project manager decides to purchase insurance to cover potential losses. Which risk response strategy is being used?
Hard203A project team is using Jira for an Agile project. Which TWO artefacts are typically managed within Jira for sprint planning and tracking? (Choose two.)
Medium204A project has a constraint that a specific software must be used because it is the standard in the organization. The project manager must work within this limitation. What type of constraint is this?
Medium205A team uses a tool that clarifies roles by showing who is responsible, accountable, consulted, and informed for each task. Which tool is this?
Medium206A project manager is closing a project and needs to ensure all project objectives have been met. Which document should be used to verify completion of deliverables?
Hard207An organization is deploying a new storage area network (SAN). Which of the following is a key consideration for ensuring high performance?
Easy208A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $90,000, and the actual cost (AC) is $100,000. What is the estimate at completion (EAC) if the project is expected to continue at the same cost performance?
Hard209A project has a technical constraint that requires using a specific software platform mandated by the customer. This is an example of which type of constraint?
Hard210A project manager is leading a cross-functional team in a matrix organization. The project is experiencing conflicts between team members due to competing priorities from their functional departments. Which THREE techniques should the project manager use to resolve resource conflicts? (Select THREE).
Medium211A project manager is using a quantitative analysis technique that runs thousands of iterations of the project schedule to determine the probability of completing the project by a certain date. This technique uses probability distributions for activity durations. Which technique is being described?
Hard212A project sponsor proposes increasing the project budget to add a new feature requested by a key stakeholder. What should the project manager do first?
Easy213During a project, the project manager receives a change request that would modify the project's scope. According to the integrated change control process, which THREE actions are part of evaluating this change request? (Choose three.)
Medium214During a sprint review, the product owner notices that the team completed 30 story points in the previous sprint and 25 in the current sprint. The project manager wants to track the average story points completed per sprint to predict future performance. Which metric should be used?
Medium215A project manager is leading a software development project. The team is using an agile approach with iterative cycles. Which project life cycle model best describes this approach?
Hard216A project team is working on a software development project. The project manager wants to ensure that all changes to the codebase are reviewed and approved before they are integrated. Which type of tool should be used?
Easy217You are managing a network upgrade project for a large corporation. The project involves replacing outdated switches and routers across three data centers. During the execution phase, you discover that one of the key vendors has shipped the wrong model of switches for Data Center B. The correct switches have a lead time of four weeks, which will delay the project by three weeks. The project sponsor is pressuring you to meet the original deadline. The project budget has some contingency reserves. What should you do?
Medium218A project manager has identified a risk with a probability of 0.3 and an impact of 4 on a scale of 1-5. What is the risk score?
Medium219A data center upgrade project requires redundancy for critical systems. Which three components should be redundant? (Choose three.)
Medium220Which THREE are common types of project management documentation? (Choose three.)
Medium221In which project management process group is the project charter formally approved, giving the project manager authority to allocate resources?
Medium222During which project phase is the project charter created?
Easy223A project manager is struggling to get timely decisions from the steering committee. To improve governance, what should the project manager update?
Hard224A project manager is closing a project that delivered a new customer relationship management system. Which THREE activities are part of the closing process? (Select THREE).
Hard225Refer to the exhibit. A project team performed a deployment that failed and was rolled back. What should the project manager do next?
Hard226In a precedence diagramming method (PDM) network, a successor activity cannot start until its predecessor activity has started. Which type of dependency does this represent?
Medium227A project manager needs to determine the critical path of a project. Which statement about the critical path is true?
Easy228A project manager is selecting a project selection method. Which TWO methods evaluate the profitability of a project? (Choose TWO.)
Medium229A project manager notices that actual costs are significantly higher than planned for the first two months of a six-month project. The project is critical to the organization, and the sponsor is concerned about the budget. What is the BEST course of action for the project manager?
Hard230Which project scheduling tool shows activities as bars on a timeline, including dependencies and milestones?
Easy231A project manager is assigned to a new project that involves developing a mobile application. The project sponsor is from the marketing department, and the key stakeholders include the IT director and the customer. Which organizational structure is most likely being used if the project manager has limited authority and must rely on the functional managers to provide resources?
Easy232A project manager needs to document the roles and responsibilities of team members for a new project. Which document should the project manager create?
Easy233A steering committee is reviewing project performance. Which of the following is a key responsibility of the steering committee?
Hard234A project manager is creating a document that identifies all project stakeholders and their interests, influence, and expectations regarding the project. This document is the:
Medium235A project manager is updating the risk register and plans to respond to a high-priority risk. Which THREE are examples of proactive risk response strategies?
Medium236A project is in the planning phase. The project manager is working with the team to break down the project deliverables into smaller, more manageable components. Which process is being performed?
Easy237A project is in the monitoring and controlling phase. The project manager is reviewing the earned value metrics: EV = $50,000, PV = $60,000, AC = $55,000. Which of the following statements is correct?
Hard238A project has a constraint that a key piece of equipment must be sourced from a specific vendor due to organizational policy. This is an example of which type of constraint?
Hard239Which TWO of the following are characteristics of a project? (Select TWO).
Medium240A project has earned value (EV) of $50,000, planned value (PV) of $60,000, and actual cost (AC) of $55,000. What is the cost performance index (CPI)?
Hard241During project execution, the team uses a shared online workspace to collaborate on documents. This is an example of which type of tool?
Easy242A project manager is reviewing the risk register and sees that a high-impact risk has a probability of 0.3 and an impact of $50,000. The team implements a response that reduces the probability to 0.1 and the impact remains $50,000. The response cost is $5,000. What is the net expected monetary value (EMV) of implementing the response?
Hard243During the planning phase, a team member estimates a task duration as 5-7 days based on a similar past project. Which estimating technique is being used?
Medium244Match each communication method to its description.
Medium245A project manager uses a tool that shows the sequence of project activities and their dependencies. Which tool is this?
Easy246A project manager is evaluating a project proposal. Which TWO of the following criteria are most important for deciding whether to approve the project?
Easy247In a network diagram, Activity A has a duration of 5 days, Activity B has 3 days, and Activity C has 4 days. Activity A and B can start simultaneously, but Activity C cannot start until both A and B are complete. What is the critical path duration?
Hard248A project manager is overseeing a data center migration. The new infrastructure must support high availability and scalability. Which TWO components are essential for achieving these goals?
Easy249During project execution, a key stakeholder requests a new feature that was not included in the scope baseline. What should the project manager do first?
Easy250Which document formally authorizes the project and assigns the project manager?
Easy251A project manager is assigned to a new project that has a tight deadline. The team members are from different departments and have competing priorities. Which project management process group is the project manager likely to spend the MOST time in during the initial phase of the project?
Easy252Refer to the exhibit. What is the total duration of the project on the critical path?
Hard253During project execution, a customer requests a new feature that was not in the original scope. The project manager receives a change request. What is the NEXT step the project manager should take?
Medium254A project manager has identified a risk that could cause a $50,000 loss with a 20% probability. What is the Expected Monetary Value (EMV) of this risk?
Easy255During a sprint review, the product owner notices that the team has completed 30 story points, but the burndown chart shows an upward trend. What is the most likely cause?
Medium256A project manager is using the Delphi technique for risk identification. Which of the following best describes this technique?
Medium257A project is in the monitoring and controlling phase. The project manager notices that the cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 1.2. What does this indicate about the project?
Hard258A project team is using an Agile approach. During the sprint review, the product owner decides to reprioritize the backlog, moving a high-effort story to the next sprint. What is the primary benefit of this flexibility?
Hard259A project has a budget at completion (BAC) of $200,000. After 3 months, the earned value (EV) is $80,000, and the actual cost (AC) is $100,000. What is the estimate at completion (EAC) assuming the cost performance index (CPI) will remain the same for the remainder of the project?
Hard260A project manager is conducting a risk assessment workshop. Which THREE items should be included in the risk register for each identified risk?
Hard261A project manager needs to ensure that the IT infrastructure project complies with industry standards for data security. Which document should the project team reference?
Medium262A project manager is leading a project in an organization that uses a hybrid methodology. The team follows a predictive approach for requirements gathering and design, but uses iterative sprints for development. Which life cycle best describes this project?
Hard263Match each project management tool or technique to its purpose.
Medium264A project team is adding extra features to a deliverable that were not requested by the customer, in an effort to improve the product. This practice is known as:
Easy265A project to upgrade network switches. Which TWO factors should the project manager consider when selecting switches? (Choose two.)
Easy266A software development team uses short, time-boxed iterations, daily stand-up meetings, and a prioritized backlog. Requirements are expected to evolve throughout the project. Which project management methodology is being used?
Medium267A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?
Medium268During project selection, an organization evaluates multiple projects using financial methods. Which THREE of the following are commonly used financial project selection methods? (Select THREE).
Hard269During project execution, a vendor is hired to provide specialized services. The contract is structured so that the vendor is paid for all allowable costs plus a fixed fee. Which type of contract is this?
Hard270Refer to the exhibit. Based on the exhibit, what is the status of change C001?
Medium271Which TWO of the following are primary responsibilities of the project manager? (Select two.)
Medium272Which TWO of the following are typically included as phases in a project life cycle according to the Project Management Institute (PMI)?
Easy273A project manager is creating a document that formally authorizes the project and assigns the project manager. This document includes the business case, high-level scope, and budget constraints. What is this document called?
Easy274During a network upgrade project, a technician accidentally disconnects a critical switch, causing an outage. The project manager needs to update the issue log and communicate with stakeholders. Which communication method is most appropriate for notifying senior management of the outage?
Medium275A project has three activities on the critical path: A (5 days), B (10 days), C (5 days). Activity D (8 days) has a total float of 3 days. If activity B is delayed by 2 days, what is the new project duration?
Hard276A project manager is tracking issues and their resolution status. Which document should the manager use to record and monitor these issues?
Medium277You are the project manager for a cloud migration project at a mid-sized company. The project team consists of internal IT staff and a third-party vendor responsible for data transfer. During a weekly status meeting, you discover that the vendor has been using an unauthorized tool to accelerate data transfer, which violates the security policy outlined in the project charter. The vendor claims the tool is necessary to meet the aggressive timeline. The project sponsor is concerned about security but also about schedule delays. You need to take the most appropriate action to address this issue while maintaining project control. Which action should you take?
Medium278Which TWO tools are commonly used for project scheduling and displaying task dependencies? (Select TWO)
Medium279A project manager is managing an IT infrastructure upgrade project. The project plan includes a detailed schedule, resource assignments, and a risk register. The project manager uses a spreadsheet to track risks, but the spreadsheet has become large and difficult to maintain. Team members are not consistently updating risk information, and some risks have been ignored. The project manager wants to adopt a more effective risk management tool that encourages regular updates and provides risk scoring. Which tool should the project manager implement?
Hard280A senior project manager is overseeing a large infrastructure upgrade project for a government agency. The project involves multiple vendors and strict compliance requirements. The project team has been using a shared network drive to store project documents, but team members often struggle to find the latest versions of documents, and there have been instances where outdated documents were used, leading to rework. The project manager needs to implement a solution that ensures document version control, access control, and audit trails. The agency has a limited budget and cannot afford expensive enterprise content management systems. What is the best course of action?
Hard281A project manager is analyzing the impact of a proposed change on the project's schedule, cost, and quality. After the analysis, the change request is reviewed by a group of stakeholders who decide whether to approve it. This group is known as the:
Medium282A project manager is using schedule compression techniques to meet a deadline. Which THREE statements about fast-tracking and crashing are correct?
Hard283A project manager is analyzing the network diagram and identifies that Activity X has a late start (LS) of day 10 and an early start (ES) of day 8. Which TWO statements are true about Activity X? (Select two.)
Hard284A project sponsor asks for a report showing the planned vs. actual cost performance. Which project document contains the necessary data to create this report?
Medium285During project execution, a stakeholder requests additional features that were not in the original scope. The project manager identifies this as scope creep. What is the best action for the project manager to take?
Medium286While upgrading storage, the project team discovers that the SAN switch is saturated. What immediate step should the project manager take?
Easy287Based on the change request log exhibit, what should the project manager do next regarding the change requests?
Easy288A project manager is reviewing a control chart and notices several data points outside the upper control limit (UCL). Which type of variation do these points indicate?
Hard289A project manager reviews the following risk register: R1 (Vendor delay) has a probability of 0.8 and an impact of 0.6; R2 (Resource shortage) has a probability of 0.6 and an impact of 0.5; R3 (Technical failure) has a probability of 0.6 and an impact of 0.6; R4 (Scope creep) has a probability of 0.7 and an impact of 0.5. Which risk should the project manager prioritize for active monitoring and response?
Hard290Which THREE documents are typically part of the project management plan?
Medium291During a status meeting, a team member reports that a task is taking longer than estimated. The project manager updates the task's remaining duration in the project schedule. This action is part of which process?
Medium292Which THREE documents are typically created during the initiating process group?
Easy293A project team is distributed across three time zones. The project manager notices that communication breakdowns are causing delays. Which communication method should the project manager implement to improve collaboration and ensure information is stored for future reference?
Medium294A project manager wants to analyze the project schedule to identify the longest path of dependent tasks. Which technique should be used?
Hard295A project team is identifying risks using a technique that involves a group of experts answering questionnaires anonymously to avoid bias. Which risk identification technique is being used?
Medium296A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $120,000, and the actual cost (AC) is $150,000. What is the estimate to complete (ETC) assuming the project will continue to perform at the same cost efficiency?
Hard297In a network diagram, if Activity B cannot start until Activity A is complete, what type of dependency is this?
Medium298A project has three activities: Activity A (5 days), Activity B (7 days), Activity C (4 days). Activity B depends on A. Activity C depends on B. What is the total float for Activity B?
Hard299A project manager is preparing for the project closure phase. Which three activities should the project manager perform? (Select THREE).
Hard300A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What does this indicate?
Hard301A project manager is evaluating whether to proceed with a project that has a net present value (NPV) of -$10,000, an internal rate of return (IRR) of 4%, and a payback period of 3 years. The company's required rate of return is 6%. What should the project manager recommend?
Hard302Which TWO of the following are examples of project constraints? (Select TWO).
Medium303A project to migrate on-premises email to a cloud-based service is nearing completion. After the final cutover, some users report that emails sent to certain domains are not being delivered. The project team checks the mail servers and finds no errors. The project manager reviews the DNS records and discovers that the MX records were not updated to point to the new service. What should the team do first?
Medium304A project sponsor asks the project manager to accelerate the schedule. Which TWO schedule compression techniques could the project manager consider?
Hard305Which risk response strategy involves taking action to reduce the probability or impact of a risk?
Easy306A project manager is managing an agile project. The team uses iterative development and daily stand-up meetings. Which of the following is a key principle of agile project management?
Easy307Which TWO of the following are risk identification techniques commonly used in project management? (Choose two.)
Easy308During the planning phase, the project manager wants to define the project scope in detail. Which document should be created?
Easy309Who is responsible for providing the project with resources and removing obstacles that are beyond the project manager's control?
Easy310During project closing, which activity is performed to formally obtain acceptance of the project deliverables from the sponsor or customer?
Medium311A project manager needs to assign tasks to team members. Which document provides the detailed breakdown of work packages?
Easy312Which TWO of the following are outputs of the project initiation phase?
Medium313A project is behind schedule. The project manager decides to start the next phase before the previous phase is fully complete, overlapping activities. This technique is known as:
Hard314During project planning, the project manager decomposes the project scope into smaller, more manageable components. What is the resulting document called?
Medium315A project manager is leading a software development project in a matrix organization. The project manager shares resources with functional managers. In this type of organizational structure, which of the following BEST describes the project manager's authority?
Medium316A project manager is closing a project. Which TWO activities should be performed during project closure? (Select two.)
Medium317Which THREE of the following are characteristics of a project as defined by PMI?
Hard318A project manager is working on a construction project and needs to calculate the total float for a non-critical path activity. The activity has an early start of day 5, late start of day 10, early finish of day 15, and late finish of day 20. What is the total float?
Hard319A project manager notices that the project is behind schedule. The planned value (PV) is $50,000, earned value (EV) is $40,000, and actual cost (AC) is $45,000. What is the schedule performance index (SPI) and what does it indicate?
Hard320A project manager is evaluating potential IT infrastructure projects. Which two project selection methods consider financial return? (Choose two.)
Easy321Arrange the steps for initiating a project in the correct order.
Medium322A project manager is overseeing the implementation of a new customer relationship management (CRM) system. The vendor requires access to the company's internal network to install and configure the software. Which of the following is the BEST practice to ensure security while allowing vendor access?
Hard323Which document formally authorizes a project and provides the project manager with the authority to apply organizational resources?
Easy324Order the steps for effective stakeholder communication.
Medium325During the planning phase, which three documents are typically created? (Select THREE.)
Medium326A project team is using planning poker to estimate user stories. What is the purpose of this technique?
Medium327A project manager is reviewing the procurement process. Which document is used to invite vendors to submit a proposal for a project?
Hard328A project manager is developing the risk management plan. Which of the following is the primary purpose of this plan?
Hard329During the planning phase, a team identifies a risk that could cause a 10% increase in project cost if it occurs, with a 20% probability. What is the expected monetary value (EMV) of this risk?
Hard330A project team is decomposing the project scope into work packages. Which of the following best describes the purpose of a Work Breakdown Structure (WBS)?
Hard331A project is 40% complete. The earned value (EV) is $80,000, planned value (PV) is $100,000, and actual cost (AC) is $90,000. What is the cost performance index (CPI) and schedule performance index (SPI)?
Hard332A project manager is assigned to a project in a strong matrix organizational structure. The project manager has significant authority over the project team, and team members report to both the project manager and their functional managers. Which of the following best describes the project manager's level of authority in this structure?
Medium333During project execution, a key stakeholder requests a change that will affect the project scope. The project manager assesses the impact and finds it will increase costs by 15% and delay the schedule by two weeks. What is the FIRST action the project manager should take?
Medium334A project manager is assigned to a new project. The project charter has been approved. Which of the following is the NEXT step?
Easy335A company is initiating a project to develop a new mobile application. The project manager needs to secure approval and funding. Which project role is primarily responsible for providing the necessary resources and championing the project?
Easy336Refer to the exhibit. A developer deployed a new version of an application to production. After restarting the service, the application fails to connect to the database. What is the most likely cause?
Medium337A project manager is calculating the estimate to complete (ETC) for a task using earned value management. The task has a budget at completion (BAC) of $10,000, earned value (EV) of $4,000, and actual cost (AC) of $5,000. Assuming the work will continue at the planned rate, what is the ETC?
Medium338In which project life cycle phase are project risks identified and a risk management plan created?
Medium339Which document formally defines the deliverables, acceptance criteria, exclusions, assumptions, and constraints of a project?
Easy340A project sponsor wants to formally close a project. Which of the following documents should the project manager prepare to obtain sign-off that the project is complete?
Easy341During a sprint review, the team notes that the remaining work is not decreasing as expected. Which agile artefact would best help visualize the trend of remaining work over the sprint duration?
Medium342A project manager is using an issue log to track problems. During a weekly status meeting, a team member reports a new issue that has already caused a one-day delay. The project manager adds it to the issue log. What is the NEXT step?
Hard343A project manager is closing a project. Which TWO activities are typically performed during the closing phase?
Medium344A project manager needs to communicate project progress to stakeholders who have low power and high interest. Which of the following is the most appropriate communication method?
Medium345Match each document type to its description in project management.
Medium346A project manager is reviewing the project constraints. The triple constraint traditionally includes scope, time, and cost. However, quality is also often considered a constraint. Which TWO of the following are part of the triple constraint? (Select TWO).
Medium347A project manager at a marketing firm is using Microsoft Project to manage a campaign launch. The project has 15 tasks with several dependencies, including finish-to-start and start-to-start. Team members update their task progress daily. After a week, the project manager notices that some tasks are not reflecting updated finish dates even though dependencies are marked as complete. For example, Task 4 (Design finalization) has a finish-to-start dependency on Task 3 (Concept approval), which was completed three days ago, but Task 4's start date remains unchanged, causing the entire schedule to appear delayed. The project manager has verified that all task links are correctly set in the software. What should the project manager do first?
Easy348A project team is creating a WBS. They ensure that every deliverable and work package is included and that the sum of the work at the lower levels equals the total work at the higher levels. Which principle are they applying?
Easy349A project manager is leading a project that uses a hybrid methodology. The project has a fixed deadline but the requirements are expected to evolve. Which approach best describes how the PM should handle the project?
Hard350Which document contains the subsidiary plans for scope, schedule, cost, quality, resources, communication, risk, and procurement?
Easy351A project manager is leading a hybrid project that combines waterfall planning with iterative execution. Which of the following is a key challenge in managing such a project?
Hard352A project manager is planning a new data center build. The organization requires high availability and low latency for critical applications. Which infrastructure component should be prioritized to meet these requirements?
Easy353A project manager is evaluating the cost performance of a project. Which TWO earned value metrics should be used to determine if the project is over budget?
Hard354Which TWO of the following are key characteristics of a project? (Select TWO).
Medium355A project manager needs to determine the project's success criteria before the project is initiated. Which document should contain these criteria?
Medium356A project manager documents a change request and updates the change log. Which step of integrated change control is being performed?
Medium357An IT project is nearing completion. The project manager is preparing for project closure. During the final testing, the client identifies a few minor defects that were not in the original scope. The project manager has a signed scope baseline. The client insists these defects must be fixed before acceptance. The project budget is nearly exhausted, and the schedule has no buffer. What should the project manager do FIRST?
Medium358A project manager is performing quantitative risk analysis. Which THREE of the following techniques are commonly used? (Select three.)
Hard359A project manager is leading a software development project. The team is consistently delivering work late, causing schedule delays. The project manager suspects the initial duration estimates were too optimistic. What is the best action to improve future estimation accuracy?
Medium360A project team member consistently misses deadlines and produces low-quality work. The project manager wants to address the issue without demotivating the team member. What is the appropriate first step?
Medium361A project manager uses a quantitative risk analysis tool that runs thousands of simulations to determine the probability of completing the project by a certain date. Which technique is being used?
Hard362Based on the exhibit, which risk should the project manager address first?
Hard363A marketing project manager is responsible for launching a new product. The project manager has created a project charter, a stakeholder register, and a high-level schedule. The sponsor has approved the charter. The project manager needs to develop a detailed project plan. According to best practices, what should the project manager do next?
Easy364A project is in the executing phase. The project manager notices that the actual cost is consistently higher than planned, and the schedule is behind. After analyzing the situation, the project manager decides to fast-track some tasks. What is the primary impact of fast-tracking?
Medium365Match each risk response strategy to its description.
Medium366Refer to the exhibit. Based on the risk register, which risk should receive the highest priority for response?
Medium367A project team is identifying risks using a SWOT analysis. Which THREE of the following are categories examined in a SWOT analysis? (Select THREE).
Medium368A project is experiencing scope creep because stakeholders are requesting additional features without formal change control. What is the best course of action for the project manager to prevent this?
Medium369Refer to the exhibit. The project manager is reviewing the project schedule. What is the total duration of the critical path?
Easy370During project execution, a stakeholder requests a new feature that was not originally included in the scope. The project manager records the request and evaluates its impact on the triple constraint. What should the project manager do next?
Easy371A project manager identifies a risk that a critical vendor may not deliver on time. The project manager decides to document the risk and monitor it closely, but does not take any proactive action. This is an example of which risk response?
Hard372A project manager is analyzing the project schedule and notes that two activities, design and development, are currently scheduled sequentially. To accelerate the schedule, the project manager considers overlapping the activities. Which TWO of the following are correct regarding this approach?
Medium373A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?
Hard374During which stage of Tuckman's team development model do team members begin to resolve conflicts and establish norms?
Medium375A project manager is monitoring project performance. Which TWO earned value metrics are used to assess cost efficiency?
Medium376Which TWO of the following are typical activities in the Closing phase of a project?
Hard377Which TWO of the following are common causes of project delays in IT infrastructure projects? (Choose two.)
Easy378A project is implementing a new backup solution. The current infrastructure uses tape backups, and the new solution will use cloud storage. During planning, the team identifies that the internet bandwidth is insufficient for initial seed data transfer. What is the best approach to mitigate this risk?
Medium379A project manager is creating a risk register for a construction project. Which TWO fields are essential for calculating a risk score?
Hard380Which of the following is a key component of a project scope statement?
Easy381Which TWO of the following are effective techniques for managing stakeholder expectations?
Hard382A project manager is assigned to a project that has already started without a formal project charter. What should the project manager do first?
Medium383During project execution, a project manager notices that team members are spending excessive time on non-essential tasks, and the project is falling behind schedule. Which tool should the project manager use first to identify the root cause of the delays?
Hard384Match each procurement document to its purpose.
Medium385A project is in the Executing phase. The project manager needs to ensure effective communication with stakeholders. Which THREE elements should be included in the communications management plan? (Select THREE.)
Hard386A project manager is leading a brainstorming session to identify potential risks. The team uses a technique that encourages free thinking and avoids criticism. Which risk identification technique is being used?
Medium387During risk assessment, a project team identifies a risk that has a high probability of occurrence and high impact on project cost. Which risk response strategy is most appropriate?
Hard388In a network diagram, Activity A has early start (ES) of 0 and early finish (EF) of 5. Activity B depends on A and has ES=5, EF=10. Activity C also depends on A and has ES=5, EF=12. Activity D depends on B and C and has ES=12, EF=15. What is the total float for Activity C?
Hard389A project manager is estimating activity durations for a construction project. She uses a parametric estimate based on 100 square meters per day. If the total area is 500 square meters, the estimated duration is 5 days. Which THREE statements are true about parametric estimation?
Medium390A project manager is leading a project with a tight budget. The team has completed all required features, but there is some remaining budget. The sponsor suggests adding a few extra features. What are TWO potential issues the project manager should consider before approving? (Choose TWO.)
Hard391A project to implement a new CRM system is behind schedule due to unexpected technical issues. The project manager decides to fast-track the project by overlapping phases. Which risk is most likely to occur?
Hard392Refer to the exhibit. What is the cost variance (CV) and schedule variance (SV)?
Medium393A project manager is using a predictive (waterfall) life cycle for a construction project. Which THREE documents are typically created during the planning phase?
Hard394A project to consolidate multiple physical servers into a private cloud. What is the primary benefit of using server virtualization?
Easy395A project manager receives a change request to add a new feature to the project's software. After evaluating the impact on the triple constraint, they submit it to the change control board (CCB). The CCB approves the change. What is the project manager's next step?
Medium396A project involves installing new firewalls across multiple sites. The project manager notices the schedule is slipping due to site-specific electrical requirements that were not initially identified. What is the best course of action?
Medium397A project manager is assigned to a new initiative in a matrix organization with a weak matrix structure. The project manager needs to obtain resources from functional departments. The functional managers have authority over their team members' assignments and priorities. What is the most likely challenge the project manager will face in this environment?
Hard398During project initiation, a project manager needs to identify high-level risks. Which document should the project manager reference?
Easy399A project manager is explaining the characteristics of a project to a new team member. Which TWO of the following are typical characteristics of a project?
Easy400In a risk register, the risk score is typically calculated by multiplying which two fields?
Medium401During which project phase is the project charter created and the project manager officially assigned?
Easy402A project manager needs to show the sequence of project activities and their dependencies to identify the critical path. Which tool should they use?
Medium403Which type of contract places the greatest cost risk on the seller?
Medium404A project manager is using a Kanban board to visualize workflow. Which metric should the team track to measure process efficiency?
Easy405A project manager needs to track task dependencies and identify the critical path. Which tool should they use?
Easy406A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?
Hard407A project team is using a Kanban board. A work item has been in the 'In Progress' column for two weeks with no updates. What is the best action for the project manager?
Medium408Which THREE of the following are valid project closure activities?
Hard409An IT project manager is using a project management software tool to track progress. The tool shows that the project's SPI is 0.8 and CPI is 1.1. Which conclusion can the project manager draw about the project's performance?
Hard410A project manager is evaluating change requests. According to the integrated change control process, which THREE elements should be assessed for impact before a change is approved?
Hard411A project manager is reviewing the project selection methods for a new initiative. Which TWO of the following are financial project selection methods? (Choose two.)
Medium412Which of the following describes scope creep?
Easy413A project manager is reviewing the project budget and notices that the actual cost is significantly higher than planned. The project manager wants to identify which specific work packages are causing the overrun. Which report or tool should be used?
Hard414During sprint planning, the team uses a technique where each member privately selects a card representing a number of story points for a user story. After revealing, they discuss discrepancies. This technique is known as:
Medium415A project team is distributed across three time zones. The project manager needs to collaborate on project documents in real-time and maintain a single source of truth. The documents include the project plan, requirements, and design specifications. Some team members have been emailing different versions, causing confusion. The project manager wants to adopt a tool that allows simultaneous editing, version history, and access control. Which tool should the project manager implement?
Easy416After a change request is approved, the project manager updates the project management plan. This is an example of updating which type of document?
Hard417Refer to the exhibit. Based on the exhibit, which response strategy is the project manager planning to use for this risk?
Easy418A project manager is leading an IT infrastructure upgrade project that follows a phased life cycle. During the planning phase, the project team is divided on the estimation approach for the migration tasks. Some members insist on using expert judgment, while others prefer parametric estimating based on historical data from similar projects. The project manager needs to decide on a method to ensure accurate estimates and team consensus. What should the project manager do?
Medium419A project manager needs to identify stakeholders for a new project. Which document should the project manager review first to understand the project's high-level stakeholders?
Easy420A company is migrating from on-premise email to a cloud-based solution. The vendor changes the migration tool mid-project. Which project management document should be updated to track the impact on requirements?
Medium421Which TWO of the following are key considerations when designing an IT infrastructure for a new data center?
Medium422Which TWO of the following are commonly used project scheduling tools? (Select exactly 2.)
Medium423A project manager is leading a multinational project with teams in the US, India, and Brazil. The project manager uses a project management tool that includes a dashboard for tracking milestones, tasks, and risks. The tool also has a document repository. During a virtual meeting, the project manager notices that the dashboard shows outdated data because team members are not updating task progress regularly. The project manager needs to improve real-time visibility and ensure accurate reporting. Which action should the project manager take?
Hard424Which TWO tools are commonly used for schedule management? (Select TWO.)
Easy425A project manager is estimating the duration of a task that has never been done before. The team provides three estimates: optimistic (4 days), most likely (7 days), and pessimistic (16 days). Using the PERT three-point estimate formula, what is the expected duration?
Easy426Which tool shows the hierarchical breakdown of work to be performed by the project team?
Easy427Which of the following is an example of a risk response strategy to avoid a risk?
Easy428During project planning, the team identifies that a key developer is only available 50% of the time. This is an example of which type of constraint?
Easy429Which THREE of the following are key outputs of the Executing phase?
Medium430Which document formally authorizes the project and identifies the project manager?
Easy431Which THREE of the following are key components of a project management plan?
Easy432A project manager is using a prioritized list of project risks. Each risk has an assigned owner and a planned response. The project manager notices that one risk has a high probability and impact, but no response has been planned. What should the project manager do FIRST?
Hard433A project manager is planning the deployment of a new web application. The IT team has identified the following requirements: the application must be accessible 24/7, handle traffic spikes, and maintain session persistence. Which TWO infrastructure components should the project manager include in the design to meet these requirements?
Medium434Refer to the exhibit. Based on the risk register, which risk has the highest risk score?
Easy435Which THREE of the following are key elements of a user story? (Select THREE.)
Medium436During the monitoring and controlling phase, a project manager receives a status report indicating the CPI is 0.8 and SPI is 0.9. Which action should the project manager take next?
Medium437Which TWO items are typically included in a project closure report?
Hard438Which of the following BEST defines a project?
Easy439A project manager needs to communicate project status to stakeholders. Which TWO tools are suitable for this purpose? (Choose two.)
Hard440Which THREE of the following are examples of project constraints?
Medium441A company is implementing a hybrid cloud solution to meet fluctuating demand. The project budget is fixed, and the timeline is aggressive. Which project management approach is most appropriate to manage scope changes while controlling costs?
Hard442A project manager is documenting the specific actions that will be taken to manage and control risks throughout the project. Which document is this?
Easy443During which project phase is the project charter created and the project manager formally assigned?
Easy444Refer to the exhibit. Which change should be implemented FIRST?
Easy445During a project audit, the project manager discovers that several change requests were implemented without proper documentation. The project team used a verbal approval process, and changes were made directly to project documents without updating the change log. The project manager needs to establish a formal change control process and choose appropriate tools to track changes. The tools must support submission, review, approval, and implementation tracking of change requests. Which combination of tools should the project manager implement?
Medium446A project manager needs to communicate the project schedule to senior management, highlighting only key events such as the start and end of phases and major deliverables. Which type of chart is most appropriate?
Medium447A project manager is reviewing the lessons learned from a previous project. Which TWO documents are commonly used to capture lessons learned? (Choose two.)
Hard448A project manager is selecting a project using financial methods. Which THREE of the following are valid project selection methods? (Select THREE).
Hard449A project manager is reviewing quality control results and sees a pattern of increasing defects over time. Which THREE quality tools would be most appropriate to analyze this situation?
Hard450Which document decomposes project deliverables into smaller, more manageable components?
Easy451Which of the following is an example of gold plating?
Medium452A project manager is managing a project in a functional organization. Due to resource constraints, the functional manager often reassigns team members to other tasks. What is the MOST significant challenge the project manager will face?
Hard453A project manager is using a tool that plots risks based on their probability of occurrence and potential impact. What is this tool?
Hard454You are the project manager for a medium-sized software company that is developing a customer relationship management (CRM) application using a hybrid Agile-Waterfall approach. The project is in the execution phase, and the team has completed three two-week sprints. The project sponsor has expressed concern that the product owner is not prioritizing the backlog effectively, resulting in the development team working on low-value features. Additionally, the testing team, which follows a Waterfall approach, is complaining that they are not receiving stable builds for integration testing. The project is at risk of missing the release deadline. As the project manager, what should you do first?
Hard455Refer to the exhibit. According to the stakeholder register entry, how should the project manager engage the sponsor?
Easy456Which THREE of the following are typically included in a project management plan? (Select THREE.)
Hard457A project manager is creating documents for procurement. Which TWO documents are typically used in procurement processes? (Select two.)
Medium458A project to develop a mobile app is in the executing phase. The project manager uses a Kanban board to track tasks. The team is self-organizing and works in short iterations. The customer is actively involved and provides feedback frequently. Which THREE statements are true about this project?
Hard459A project has a budget at completion (BAC) of $200,000. After five months, the earned value (EV) is $90,000 and the actual cost (AC) is $100,000. The project manager needs to calculate the estimate at completion (EAC) assuming current cost performance will continue. What is the EAC?
Hard460A project manager is leading a project to implement a new customer relationship management (CRM) system. The project requires extensive documentation, including business requirements, technical specifications, test plans, and user manuals. The team is using a shared repository but is struggling with document organization and version control. Several documents have outdated information, and team members are unsure which version is current. The project manager decides to implement a document management process. Which approach should the project manager adopt?
Medium461A project has a dependency that requires the foundation to be poured before the walls can be erected. This is an example of which type of dependency?
Easy462A project manager is overseeing a software development project using Agile methodology. The team uses a physical Kanban board to track tasks, but the project manager is struggling to generate reports for stakeholders who are remote. The team needs to maintain the visual board for daily stand-ups while also having digital access for remote members. The project manager wants to choose a tool that supports both physical and digital boards with synchronization. Which tool should the project manager select?
Hard463During which project phase is the project charter typically created and approved?
Easy464A project manager is assigned to a new software development project. The requirements are well understood and unlikely to change. Which project management methodology is most appropriate for this project?
Medium465A project manager is assigned to a project that has a high degree of uncertainty and rapidly changing requirements. The project sponsor is concerned about cost overruns and wants a method that allows for frequent delivery of value while adapting to changes. Which project management methodology should the project manager recommend?
Hard466According to Tuckman's model, during which stage do team members begin to resolve conflicts and establish norms?
Medium467Which TWO of the following are components of the project management plan?
Medium468A project manager is using a risk probability and impact matrix. A risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?
Medium469During project planning, a project manager is decomposing the project scope into smaller components. Which document is being created, and what is the lowest level of decomposition called?
Medium470During the planning phase, a project team is selecting risk response strategies for identified risks. Which THREE are valid risk response strategies?
Hard471Which cost estimation technique uses historical data from similar projects to estimate the cost of the current project?
Easy472An agile team is reviewing their work. Which TWO metrics can be used to track progress within a sprint? (Select TWO).
Hard473A project team is in the storming stage of Tuckman's model. Which of the following behaviors is most likely to be observed?
Easy474A project manager is reviewing the project management plan. Which two components should be included? (Select TWO).
Medium475A project manager is in the process of formally authorizing a new project. Which document should be created during the initiation phase?
Easy476A project manager is assigned to a new project with unclear requirements and expects frequent changes. Which project management methodology is most suitable?
Easy477The project manager is reviewing the work breakdown structure (WBS) with the team to ensure that all deliverables are included. Which rule states that the WBS should capture 100% of the work defined by the project scope?
Medium478Which document describes the roles and responsibilities in a project using the categories Responsible, Accountable, Consulted, and Informed?
Easy479A project manager is assigned to upgrade the firewall for a company with multiple branch offices. The project charter has been approved, but the budget is tight. Which cost control technique should the project manager use to ensure expenses remain within budget?
Easy480A project manager is defining the project life cycle for a construction project where requirements are well-defined and unlikely to change. Which project management methodology is most appropriate for this scenario?
Easy481A project manager is creating a document that lists the project deliverables, acceptance criteria, exclusions, assumptions, and constraints. Which document is being created?
Easy482A project manager is analyzing quality data and wants to identify the most frequently occurring defects to prioritize corrective actions. Which quality tool should be used?
Medium483Which TWO documents are commonly used to define and control project scope? (Choose two.)
Easy484A project has a BAC of $100,000. The earned value is $40,000, actual cost is $50,000, and planned value is $30,000. What is the estimate at completion (EAC) assuming the current cost performance is expected to continue?
Hard485A project is behind schedule. The project manager notes that the critical path has been extended. Which action should the project manager take first?
Easy486Which TWO documents are typically created during the project planning phase?
Medium487A project manager is leading a team in a functional organization. Which statement BEST describes the project manager's authority?
Easy488A project manager is evaluating the project's performance using EVM. PV = $50,000, EV = $45,000, AC = $55,000. Which of the following is true?
Hard489A project manager calculates the cost variance (CV) as -$5,000 and the cost performance index (CPI) as 0.9. What does this indicate about the project?
Hard490A project manager is creating the WBS. Which rule ensures that all deliverables and work required for the project are included in the WBS and no work is omitted?
Easy491During project initiation, which three documents are typically created or updated? (Select THREE).
Medium492Which THREE documents are part of the project procurement management process?
Hard493A project team is deploying new servers in a virtualized environment. The project scope includes performance monitoring. Which tool should the team configure to baseline CPU and memory usage?
Medium494Which of the following is a common response strategy for negative risks (threats) that involves reducing the probability or impact of the risk?
Easy495A project is 60% complete. The original budget (BAC) is $200,000. Actual costs to date are $130,000, and the earned value is $120,000. What is the estimate at completion (EAC) if the project will continue to perform at the current cost efficiency?
Hard496At a certain point in the project, the earned value (EV) is $500, the planned value (PV) is $600, and the actual cost (AC) is $400. What is the schedule performance index (SPI)?
Hard497A project manager is identifying stakeholders and analyzing their influence on the project. Using a power/interest grid, which group should the project manager 'manage closely'?
Medium498A project manager is creating a document that formally authorizes the project and assigns the project manager. Which document is this?
Easy499A project manager is using earned value management. The project has a schedule variance (SV) of -$5,000. What does this indicate?
Medium500An agile team uses a tool where they maintain a list of features, enhancements, and bug fixes that are not yet scheduled for a sprint. This list is prioritized by the product owner. What is this list called?
Medium501Which of the following is a key responsibility of the project sponsor?
Easy502A project manager is creating a communication plan. Which element should be included to ensure stakeholders receive information in a timely manner?
Medium503A project is in the executing phase when a key stakeholder requests a new feature that was not part of the original scope. The project manager needs to handle this request appropriately. Which TWO actions should the project manager take? (Select TWO).
Easy504A project team is experiencing scope creep because stakeholders keep adding minor features without formal approval. What is the best way to prevent this in the future?
Medium505A project manager is reviewing lessons learned from a previous project and notices that scope creep occurred because stakeholders requested changes after the project moved into the execution phase. Which action should the project manager take in the current project to prevent this issue?
Medium506A project has earned value (EV) of $50,000, actual cost (AC) of $60,000, and planned value (PV) of $55,000. What is the cost performance index (CPI)?
Hard507A project manager uses a control chart to monitor the number of defects found during testing. The chart shows one data point above the upper control limit (UCL). What action should the project manager take?
Medium508A project manager is leading a software development project. The team has completed the design phase and is about to start coding. The project sponsor asks the project manager to add a new feature that was not in the original scope. What should the project manager do first?
Medium509Which project life cycle phase involves formally accepting the project deliverables and releasing resources?
Easy510A project manager is using a hybrid methodology. The project has a fixed overall budget and a high-level schedule, but some deliverables are developed iteratively with stakeholder feedback. The team works in two-week sprints for software development, while hardware procurement follows a sequential plan. Which project life cycle is being used?
Hard511A project manager is leading an agile project using Scrum. The product owner frequently changes priorities based on customer feedback. Which TWO roles are directly responsible for managing these changes? (Select TWO).
Hard512A project manager is creating a work breakdown structure (WBS) during the planning phase. The WBS should decompose the project deliverables into smaller, manageable components. What is the lowest level of a WBS called?
Easy513A company is undertaking a one-time initiative to develop a new mobile application with a defined budget, schedule, and scope. Which term best describes this initiative?
Easy514A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $120,000 and the actual cost (AC) is $150,000. What is the estimate at completion (EAC) using the typical cost performance index (CPI) assumption?
Hard515An IT project manager is overseeing the migration of legacy systems to a new cloud platform. The project has a fixed budget and a strict deadline of six months. After three months, the project is on schedule but has already spent 70% of the budget due to higher-than-expected cloud service costs. The project manager must bring the project back within budget without affecting the deadline. Which of the following is the BEST course of action?
Hard516Which THREE items are typically found in a project management plan? (Select THREE).
Medium517A project to build a new office is in the planning phase. The project manager wants to use a methodology that allows for flexibility in design while still having a clear upfront plan for the overall construction. Which approach is BEST?
Medium518The project manager is reviewing the network configuration for a new branch office. The configuration shows two interfaces. Which of the following is a project management concern regarding this configuration?
Easy519Which TWO of the following are key responsibilities of a project manager during the monitoring and controlling process group?
Hard520During the execution phase, a project manager discovers that the development team has been using an unauthorized software library to accelerate work. The library has a license that could create legal risks for the company. What is the best course of action?
Hard521A project is in the initiation phase, and the sponsor asks the project manager to evaluate which project to select among three proposals. Proposal A has an NPV of $150,000, Proposal B has a payback period of 18 months, and Proposal C has an internal rate of return (IRR) of 12%. The organization's cost of capital is 10%. Which project should be selected based on the most financially sound criterion?
Hard522A project manager notices that a key team member is frequently pulled away to work on another priority project, causing delays. This situation is an example of which type of constraint?
Hard523Which THREE are components of the project management plan? (Choose three.)
Medium524A project manager is creating a visual representation of the project schedule that shows tasks as horizontal bars along a timeline, including dependencies and milestones. Which tool is being used?
Easy525A project manager is reviewing a project that has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What is the best interpretation?
Hard526A project has been completed, and the project manager is conducting a lessons learned session and archiving project documents. Which project life cycle phase is being performed?
Easy527Refer to the exhibit. What is the total duration of the critical path?
Medium528A project is in the planning phase. The project manager is determining the sequence of activities and their dependencies. The team uses a technique that represents activities as nodes and shows the logical flow of the project. Which technique is being used?
Medium529Arrange the steps for conducting a quality audit.
Medium530A project team uses a tool that displays columns such as 'To Do', 'In Progress', and 'Done' to visualize workflow. This is an example of which type of board?
Medium531During project planning, the team creates a work breakdown structure (WBS). Which of the following best describes the purpose of the WBS?
Easy532Which of the following best describes a project?
Easy533Which contract type places the most cost risk on the seller?
Easy534A project manager is preparing for the formal acceptance of project deliverables. The customer has been involved throughout the project and has approved interim deliverables. In which phase does formal acceptance typically occur?
Medium535Which TWO tools are commonly used for project scheduling?
Easy536During project execution, a key stakeholder demands a feature that was not included in the original scope. The project manager determines that the feature would require additional resources and extend the timeline. Which of the following is the BEST course of action?
Hard537A project manager is leading a team in an organization where team members are assigned to multiple projects and report to both a functional manager and the project manager. The project manager has moderate authority over the team. Which organizational structure does this describe?
Medium538Two project team members disagree on the technical approach for a critical deliverable. The project manager needs to resolve the conflict to avoid schedule delays. What is the best course of action?
Medium539During project execution, a team member proposes a change that will add a new feature to the product. The project manager documents the change request and analyzes its impact on scope, schedule, and cost. Who is typically responsible for approving or rejecting the change?
Medium540Which TWO documents are typically created during the planning process group?
Medium541A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following best describes the project's status?
Hard542Which of the following is NOT a typical constraint in the triple constraint of project management?
Easy543During project execution, the project team is experiencing conflicts and questioning the project manager's authority. According to Tuckman's model, which stage is the team in?
Hard544A project team is working on a construction project and is experiencing frequent change requests from the client. The project manager wants to ensure that all changes are properly evaluated and approved before implementation. Which project management process should the project manager implement?
Easy545A project manager has identified a stakeholder with high power and high interest. According to the power/interest grid, how should this stakeholder be managed?
Medium546A project sponsor asks for a document that formally authorizes the project and provides the project manager with authority to apply resources. Which document should the project manager provide?
Hard547Which document is used to record and track changes to project scope and their approval status?
Easy548Based on the exhibit, who is directly responsible for the work of Developer 1?
Easy549During the planning phase, a project manager is creating the WBS. Which of the following best describes the process of breaking down deliverables into smaller, more manageable components?
Hard550A project team is performing quantitative risk analysis using a technique that runs thousands of simulations to determine the probability of completing the project on a specific date. Which technique is being used?
Hard551A project manager identifies a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?
Medium552A project has the following activities and dependencies: A (5 days), B (3 days, after A), C (4 days, after A), D (2 days, after B), E (6 days, after C), F (1 day, after D and E). What is the total float of activity C?
Hard553A project team is transitioning from a traditional to an agile approach. The project manager wants to adopt agile artifacts. Which THREE artifacts are commonly used in agile projects to track progress and manage work?
Medium554A project manager is estimating costs for a new software development project. The company has completed three similar projects in the past. Which cost estimation technique is most appropriate in this scenario?
Medium555A project manager is creating a risk register. One risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?
Hard556A project team is using a tool to track user stories, epics, and bugs within sprints. The tool allows the team to view work in columns such as 'To Do', 'In Progress', and 'Done'. Which tool feature is being described?
Medium557A project manager is developing a communication plan. Which of the following should be determined first?
Medium558During the executing phase, a vendor delivers a product that does not meet the specifications outlined in the SOW. Which document should the project manager reference first to address this issue?
Hard559A project manager is leading a team that is developing a new mobile application. During the execution phase, the product owner requests additional features that were not included in the original scope. What should the project manager do first?
Medium560A project manager is updating the issue log. Which TWO fields are typically included in a well-structured issue log? (Choose two.)
Medium561Which project document formally authorizes the project and identifies the project manager?
Easy562A project manager is leading a team in a matrix organization. The project has high priority, but the team members report to their functional managers. What is the PRIMARY challenge for the project manager?
Medium563A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.2. Which TWO conclusions can be drawn? (Select TWO.)
Medium564A construction project is underway, and the project manager is using a Gantt chart to track progress. The project is divided into five phases: Foundation, Framing, Plumbing, Electrical, and Finishing. The project manager notices that the Framing phase is behind schedule because of a delayed material shipment. The Gantt chart shows that Framing has a predecessor of Foundation and a successor of Plumbing. The project manager updates the Gantt chart to reflect the delay. Which action should the project manager take next?
Medium565A project sponsor is responsible for providing resources and championing the project. Which of the following is also a primary responsibility of the project sponsor?
Hard566Which TWO tools are commonly used for project status reporting and communication with stakeholders?
Easy567Which THREE items are typically included in a project status report?
Hard568A project manager needs to create a RACI matrix for a project. Which THREE roles should be included in the matrix?
Easy569A project is experiencing scope creep. Which TWO of the following are effective ways to manage scope creep? (Choose two.)
Medium570During project closing, which THREE activities should be performed?
Medium571Which project life cycle phase involves obtaining formal acceptance of the project deliverables?
Medium572During a project status meeting, a team member reports that a critical task is delayed due to a vendor not delivering a required component. The project manager needs to update the project schedule and communicate the impact. Which tool should the project manager use to analyze the effect of this delay on the overall project timeline?
Medium573A project manager is planning a construction project and identifies that the project has a fixed budget and a strict deadline. The sponsor emphasizes that quality cannot be compromised. Which THREE constraints are directly affected when a change request is approved? (Select THREE).
Medium574A project manager is using a network diagram to identify the critical path. Which TWO statements are true about the critical path?
Medium575A project manager is in the process of developing the project schedule. Which activity most directly determines the project's finish date?
Easy576A project manager wants to visualize task dependencies and the critical path for a construction project. Which tool should they use?
Easy577A project has a budget at completion (BAC) of $200,000. The actual cost (AC) is $80,000, earned value (EV) is $60,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the same cost efficiency?
Hard578Which project scheduling tool depicts activities as bars on a timeline, showing dependencies and milestones?
Easy579Which THREE activities are typically performed during the execution phase of a project?
Easy580A project is defined as a temporary endeavor undertaken to create a unique product, service, or result. Which of the following BEST describes a key characteristic of a project?
Easy581During project planning, the project team identifies several assumptions and constraints. Which document is the most appropriate place to record these items?
Easy582What is the difference between a risk and an issue?
Easy583A project manager is reviewing lessons learned from a previous similar project. That project suffered from frequent requirement changes that caused schedule delays and cost overruns. What should the project manager do to mitigate this risk on the current project?
Medium584Which TWO documents should be finalized during project closure?
Medium585Which document contains all identified risks, their probability and impact, and planned response strategies?
Easy586A project manager is creating a document that identifies all project stakeholders and their influence, interest, and impact on the project. Which document is being created?
Easy587Based on the exhibit, which task is experiencing a schedule variance (SV) that is negative? The project's total planned value (PV) for these tasks is the sum of planned efforts, and earned value (EV) is calculated as % complete * planned effort.
Hard588A project has a total budget of $100,000. At a status date, the earned value (EV) is $50,000, the planned value (PV) is $60,000, and the actual cost (AC) is $70,000. What is the cost variance (CV)?
Easy589Which document is created during the closure phase to formally indicate the project is complete and accepted by the customer?
Easy590A project manager is identifying risks using the Delphi technique. Which TWO of the following are characteristics of the Delphi technique?
Easy591Refer to the exhibit. What is the critical path duration?
Medium592A project manager is reviewing the project schedule and notices that a critical path activity has a variance of -2 days. What does this indicate?
Medium593A project manager is developing a communication plan. Which two factors should be considered for each stakeholder? (Select TWO.)
Hard594A project team is distributed across three continents. The project manager needs a tool that allows real-time collaboration on project documents, version control, and task assignment. Which type of tool is BEST for this requirement?
Medium595A project sponsor is a key stakeholder. Which of the following is a primary responsibility of the project sponsor?
Medium596Which TWO are examples of project constraints in the project management triangle? (Choose two.)
Easy597A project to implement a new storage solution. The team is evaluating iSCSI vs Fibre Channel. Which factor is most important for choosing iSCSI over Fibre Channel?
Hard598A project manager discovers that a critical path activity is behind schedule. The project has no float on the critical path. Which action should the project manager take to bring the project back on track without increasing scope?
Hard599During project execution, a key team member resigns. The project manager needs to fill the role quickly. Which document should the project manager update first?
Medium600Which of the following is a key component of the project scope statement?
Easy601A project manager is evaluating earned value metrics for a project. The CPI is 0.8 and the SPI is 0.9. Which TWO conclusions can the project manager draw?
Hard602In a user story, which component describes the benefit or value that the feature will provide?
Easy603A project manager is reviewing the communication plan and notices that stakeholder A is listed as 'Responsible' for a task in the RACI matrix. According to RACI, what does 'Responsible' mean?
Medium604A project team is executing the project plan when a key stakeholder requests a significant change to the scope. The change control board has approved the change. What should the project manager update next?
Medium605In a matrix organization, a project manager needs to acquire a team member from a functional department. The functional manager is reluctant to release the resource due to other work. What is the best way for the project manager to address this?
Hard606A project manager is updating the project schedule and notices that the critical path has changed due to a delay in a key task. Which document should the project manager update first to reflect this change?
Medium607A project manager is reviewing the schedule and notices that the critical path has been affected by a delay in a non-critical task. Which of the following is the most likely reason?
Hard608A construction project is nearing the end of the executing phase. The project manager is preparing for the closure phase. During a review, the project manager discovers that two deliverables have not been formally accepted by the client due to minor quality issues. The team has already started demobilizing resources. What should the project manager do to properly close the project?
Medium609A project manager is reviewing the project's critical path. Two tasks on the critical path have float of zero, and a third task has a float of three days. The sponsor asks to compress the schedule by two days. Which action should the PM take?
Hard610A project team uses planning poker to estimate user stories. What is the purpose of this technique?
Easy611A project manager receives a change request from a stakeholder. What is the first step the project manager should take?
Easy612A company is managing multiple projects simultaneously. One project focuses on upgrading the IT infrastructure, another on developing a new customer portal, and a third on training staff on new software. These projects are grouped together because they all contribute to the same strategic goal of digital transformation. According to CompTIA Project+, how is this grouping best described?
Medium613Match each project management knowledge area to its description.
Medium614A project manager needs to communicate the project's progress to stakeholders with high power and low interest. According to the power/interest grid, which communication approach is most appropriate?
Medium615A project manager is reviewing a change request to modify the project scope. Which TWO items should be updated in the project management plan if the change is approved?
Medium616A project manager is evaluating a change request that would increase the project cost by 10% but reduce schedule by 15%. The change control board approves the change. What should the project manager update?
Medium617A project manager is calculating the cost performance index (CPI) for a project. The earned value (EV) is $50,000 and the actual cost (AC) is $60,000. What does the CPI indicate? (Select TWO correct statements.)
Medium618A project manager is creating a WBS. Which two best practices should be followed? (Select TWO)
Medium619A project has an EV of $40,000, PV of $50,000, and AC of $45,000. What is the cost performance index (CPI)?
Medium620A project manager is selecting a methodology for a project with well-understood requirements and low expected change. Which methodology is MOST appropriate?
Medium621A project manager needs to track the start and end dates of tasks as well as dependencies. Which tool should be used?
Easy622A project has many stakeholders with varying interests and influence. Which document should the PM use to plan how to engage them?
Hard623A project to build a website is expected to take 6 months with a fixed budget. During planning, the team determines that the requirements are well-understood and unlikely to change. Which methodology is most appropriate?
Medium624A software development project is using an agile methodology. The product owner is frequently changing requirements during sprints, causing the team to miss sprint goals. The project manager has a good relationship with the product owner. The team is frustrated and morale is dropping. The project manager needs to address this issue while maintaining stakeholder satisfaction. What should the project manager do FIRST?
Medium625A project manager is evaluating two potential projects. Project A has an NPV of $50,000, and Project B has an NPV of -$10,000. Which project should be selected based on NPV?
Medium626In a RACI matrix, which role is ultimately accountable for the successful completion of a task?
Medium627A project manager is tracking the completion of key deliverables against the project schedule. Which tool should they use to display only major milestones without showing detailed dependencies or tasks?
Medium628A change request to add a new feature has been submitted. After impact analysis, the change control board (CCB) approves the change. What should the project manager do next?
Medium629In a power/interest grid, stakeholders with high power and low interest should be managed with which approach?
Easy630A change request to add a new feature is submitted. The project manager performs an impact analysis and presents it to the Change Control Board (CCB). The CCB approves the change. What is the next step?
Medium631A project has a CPI of 0.8 and an SPI of 1.1. Which statement describes the project's performance?
Hard632Which TWO of the following are characteristics of the planning phase in the project life cycle? (Choose TWO.)
Medium633Which document contains information such as issue ID, description, owner, priority, status, and resolution date?
Easy634A project manager is selecting tools for an Agile project. Which TWO tools are commonly used for Agile project management? (Select two.)
Medium635During project execution, a stakeholder requests a change that will increase the project cost by 10%. The project manager documents the change and submits it to the change control board (CCB). After review, the CCB approves the change. Which document should the project manager update first?
Medium636During project planning, the team identifies high uncertainty that could affect the schedule. Which document should the project manager create or update?
Medium637A company is considering a project with an initial investment of $100,000 and expected annual cash inflows of $30,000 for 5 years. The discount rate is 10%. What is the approximate Net Present Value (NPV)? (Present value of annuity factor for 5 years at 10% is 3.791)
Hard638A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000 and the actual cost (AC) is $120,000. If the cost performance is expected to continue, what is the estimate at completion (EAC)?
Hard639A project has three activities on the critical path. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. What is the total float for any activity on the critical path?
Medium640A project manager is creating a project schedule. Which THREE items are typically included in a schedule baseline?
Easy641You are managing a marketing campaign project. The team uses a project management software that includes a resource management module. You notice that several team members are overallocated, and project tasks are at risk of delay. The software allows you to view resource capacity and assignments, but the data is not being updated regularly. You need to ensure resource conflicts are identified and resolved quickly. Which action should you take?
Medium642A project has just completed the closure phase. Which activity is performed to formally obtain confirmation from the customer that the project deliverables have been accepted?
Hard643During project execution, a team member reports that a key deliverable will be delayed because a required component is out of stock. The project manager updates the issue log and meets with the team to evaluate alternatives. Which project management process is being performed?
Medium644Which TWO of the following are examples of resource leveling techniques?
Hard645A project team is evaluating cloud providers for a SaaS application. The provider must guarantee 99.99% uptime and support data sovereignty requirements. Which service level agreement (SLA) clause is most critical to review?
Hard646During risk management, a team identifies a risk with a 20% probability of occurrence and a potential cost impact of $50,000. What is the Expected Monetary Value (EMV) of this risk?
Medium647A project manager reviews the following change request log: - CR-001: Adds 2 weeks to the schedule. - CR-002: Low-priority enhancement; no schedule impact. - CR-003: Reduces schedule by 1 week to offset delays from other changes. - CR-004: Urgent but high-risk; could cause additional delays. Based on the change request log, which of the following actions should the project manager take to maintain the project schedule?
Medium648A project manager is developing the project charter and needs to identify high-level risks. Which document should be used as an input?
Medium649A project manager is preparing a status report for stakeholders. The project is currently in the execution phase. Which key performance indicator should be included to show how efficiently the project is using its budget?
Hard650Refer to the exhibit. Based on the project status report, what is the cost variance (CV) and what does it indicate?
Hard651A project manager is reviewing the risk response plan for a critical project deliverable. Based on the exhibit, which issue exists with the current risk response setup?
Easy652A project manager is updating the risk register. Which TWO fields are typically included in a risk register?
Medium653A project manager needs to document the process for submitting and approving change requests. Which document should the project manager create?
Medium654During a project status meeting, a stakeholder complains that the project is not delivering the expected business value. The project manager reviews the business case and finds that the project is on track per the approved scope. What should the project manager do?
Medium655A large government project is in the initiation phase. The project charter has been drafted, but there is disagreement among key stakeholders about the project's objectives. Some stakeholders want to maximize functionality, while others want to minimize cost. The project manager must lead the effort to resolve this. Which of the following is the BEST approach?
Hard656Which TWO of the following are examples of gold plating? (Select two.)
Medium657A project manager is using a tool to track project tasks, dependencies, and resource assignments. The team needs to see the critical path and adjust schedules when tasks are delayed. Which tool should the project manager use?
Medium658A project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. What does this indicate about the project's performance?
Hard659A project manager is creating a project charter. Which TWO components are typically included in a project charter? (Choose two.)
Medium660A project team is experiencing conflicts between two key members. The project manager wants to resolve the issue quickly to avoid delays. Which conflict resolution technique involves the project manager making a decision without discussion?
Easy661Which of the following best describes a mandatory dependency in a project schedule?
Easy662A project manager is assigned to a new software development project. The requirements are well understood and unlikely to change. The project team is collocated and has experience with similar projects. Which life cycle approach is MOST appropriate for this project?
Medium663Order the steps for creating a project schedule.
Medium664In the context of risk management, what is a trigger?
Medium665During a project kickoff meeting, the team identifies several potential risks. The project manager decides to document them in a structured format. Which project document should the project manager use to record and track these risks throughout the project?
Hard666A company is deploying a new web server. Which TWO security measures should the project manager include in the project plan? (Choose two.)
Hard667A project manager is leading a software development project. The client requests a feature change that will add two weeks to the schedule and increase costs by $10,000. The project manager evaluates the impact and presents options to the change control board. The board approves the change but the project sponsor expresses concern about the budget. What should the project manager do next?
Hard668A project manager is reviewing the risk register and sees a risk with high probability and high impact. The risk response strategy chosen is to purchase insurance. This is an example of which risk response strategy?
Hard669During a risk assessment, a project manager calculates a risk score by multiplying the probability of occurrence (0.6) by the potential impact ($50,000). The risk score is 30,000. The project manager then identifies a response strategy that reduces the probability to 0.2. After the response, the remaining risk is calculated. What is the residual risk score?
Hard670A company is implementing a new HR system. The project manager wants to ensure that all requirements are gathered up front and the scope is fixed. Which project management methodology is MOST appropriate?
Medium671A project manager is analyzing quality control data and wants to identify whether process variation is due to special causes or common causes. Which TWO tools would be most helpful?
Hard672Which TWO documents should be updated when a change request is approved?
Easy673A project is in the planning phase and the team is determining the sequence of activities. Which project life cycle phase follows planning?
Medium674A project has a Net Present Value (NPV) of -$5,000. What does this indicate?
Medium675A project manager is creating a lessons learned document. Which TWO are typical components of lessons learned? (Choose two.)
Easy676Which of the following documents formally authorizes the project and provides the project manager with the authority to apply organizational resources?
Easy677Refer to the exhibit. What is the total float for Task D?
Hard678In a matrix organization, a project manager is struggling to get resources assigned to project tasks because the functional managers prioritize operational work. Which type of matrix organization is MOST likely in place?
Medium679After a change request is approved by the Change Control Board, what must be updated to reflect the approved changes? (Choose the best answer.)
Medium680Which TWO of the following are characteristics of the waterfall project management methodology?
Medium681During a project, a key team member is assigned to another critical project and will no longer be available. This results in a delay in the project schedule. The project manager notes this as an issue in the issue log. What is the difference between this issue and a risk?
Medium682You are the project manager for a mid-sized company that provides an online customer portal. The portal is hosted on a single virtual machine (VM) in the company's on-premises data center with 4 vCPUs, 16 GB RAM, and a 500 GB HDD. The VM runs Windows Server 2019 and hosts both the web server (IIS) and the database (SQL Server Express). Users have been reporting slow performance, especially during peak hours (10 AM - 2 PM). The system administrator notes that CPU usage spikes to 95% during those times, and disk I/O latency averages 50 ms. The company's budget is limited, and they want a cost-effective solution that can be implemented within two weeks. The project sponsor suggests migrating to the cloud, but the IT director is concerned about security and compliance. The company has no existing cloud infrastructure or virtual private network (VPN) to the cloud. You need to propose a solution that improves performance without incurring high costs or long delays. Which of the following is the BEST course of action?
Easy683A project manager is working on a software development project. The team has identified a potential risk that could cause a two-week delay. The project manager decides to add extra resources to the critical path to reduce the impact. Which risk response strategy is being used?
Easy684A project has earned value (EV) of $120,000, planned value (PV) of $100,000, and actual cost (AC) of $110,000. What is the cost performance index (CPI)?
Hard685During project closing, which of the following is the primary purpose of the lessons learned document?
Medium686During project execution, two team members disagree on who is responsible for a specific task, leading to delays. Which project document should the project manager consult to resolve this conflict?
Hard687A project team uses a tool that shows only major events or deadlines, such as the start and end of phases. Which type of chart are they using?
Easy688A project manager is overseeing a construction project. The team uses a shared spreadsheet to track project issues. Recently, the spreadsheet has become cluttered with duplicate entries and outdated information. The project manager wants to implement a more structured approach for issue tracking. The tool must allow team members to submit issues, assign owners, set priorities, and track resolution progress. Additionally, it should generate reports for stakeholders. Which tool should the project manager choose?
Easy689A project team is deploying a new application, and the error log shows repeated connection refused errors. The database server is on a separate subnet. What is the most likely cause of this issue?
Easy690A project manager is leading a software development project. The team has completed the coding phase and is about to begin system testing. The project sponsor requests a demonstration of the software to key stakeholders before testing begins. What should the project manager do?
Medium691A project manager needs to identify the root cause of a recurring defect. Which quality tool uses a fishbone diagram to categorize potential causes?
Medium692A project is behind schedule. The project manager decides to start the testing phase before the development phase is completely finished. This is an example of which schedule compression technique?
Hard693A project manager is estimating the cost of a new software development project. The project is similar to a previous project that cost $500,000. The PM adjusts for size and complexity and estimates the new project will cost $600,000. Which estimation technique is being used?
Medium694A project manager is reviewing change requests. Which THREE types of changes would be subject to integrated change control?
Medium695Which document is used to track all changes made throughout a project, including their status and impact?
Easy696A project manager is creating a RACI matrix for the project. One activity involves conducting security testing. The security lead will perform the testing, the project manager is responsible for ensuring it happens, and the compliance officer needs to be informed of the results. Which assignment is correct?
Medium697A project manager is using a Gantt chart to track progress. Which tool would BEST complement the Gantt chart to show task dependencies and the critical path?
Hard698A project to implement a new backup solution. Which THREE components are essential for a comprehensive backup strategy? (Choose three.)
Medium699Which THREE of the following are responsibilities of a project manager during project closure?
Medium700A project manager is updating the risk register for a new project. Which THREE of the following fields are essential components of a risk register in CompTIA Project+?
Hard701A project manager is overseeing a construction project to build a new office building. The project is currently in the execution phase, with foundation work underway. During a status meeting, the project manager discovers that the detailed architectural plans, which were a deliverable of the planning phase, were never formally approved by the client. The team has been working based on preliminary drawings that were used for the initial estimate. The project schedule shows that the next major activity, framing, is scheduled to start in two weeks. The project sponsor is on an extended leave and unavailable for the next month. The project manager is concerned about significant rework if the plans are later rejected. The project has a tight budget and aggressive timeline. What should the project manager do first?
Hard702Refer to the exhibit. Based on the risk register, which risk should the project manager prioritize for immediate response?
Hard703Which of the following is a key input to the change control process when a change request is submitted?
Medium704A project manager is assigned to a project in a matrix organization where the functional managers have significant control over team members. The PM has limited authority. This describes which type of matrix?
Hard705During project execution, a team member identifies a problem that has already occurred and is affecting the project schedule. The project manager should document this in which of the following?
Medium706A project team is distributed across multiple time zones and the project manager is using virtual meetings. What is the most effective way to ensure clear communication?
Hard707During a database migration project, the team encounters an error when trying to connect to the new database server from the application server. The network team confirms that the ports are open and the firewall rules are correct. The database team reports that the database service is running and listening on the expected port. Which of the following is the MOST likely cause of the connectivity issue?
Medium708A project manager is creating a document that formally authorizes the project and assigns the project manager. Which document is being created?
Easy709A project manager is evaluating whether to implement a PMO (Project Management Office) for the organization. Which scenario would best justify the creation of a PMO?
Hard710A project has an Earned Value (EV) of $50,000, Actual Cost (AC) of $60,000, and Planned Value (PV) of $55,000. What is the Cost Performance Index (CPI), and what does it indicate?
Hard711Which statement is true?
Hard712Refer to the exhibit. Which WBS element is a work package?
Medium713What is the 100% rule in work breakdown structure (WBS) creation?
Easy714A project manager is breaking down the project deliverables into smaller components. Which technique ensures that all work required for the project is included and no work outside the scope is added?
Medium715A project team is using an agile methodology and the product owner frequently changes priorities mid-sprint. What is the most likely consequence?
Medium716During project execution, the project team completes a deliverable that exceeds the specified requirements by adding extra features without authorization. This is an example of which concept?
Medium717Which document formally authorizes the project and provides the project manager with the authority to apply resources?
Hard718Which document defines the communication requirements, including who needs what information, when, and how?
Easy719A project team is identifying risks. They gather subject matter experts anonymously and use a facilitator to collect their responses iteratively until consensus is reached. Which risk identification technique is being used?
Easy720A project has an Earned Value (EV) of $50,000, Planned Value (PV) of $60,000, and Actual Cost (AC) of $55,000. What is the cost performance index (CPI) and what does it indicate?
Hard721Which agile artifact contains the prioritized list of all desired work for a product?
Easy722A project manager is using a technique to identify risks by gathering a group of experts who provide anonymous input through multiple rounds of questionnaires. This technique avoids groupthink and allows experts to refine their opinions. Which risk identification technique is being used?
Hard723Refer to the exhibit. The project manager is reviewing the schedule. What is the status of the project?
Medium724A project manager is working on a project that has a very tight deadline. The project team consists of junior and senior members. The project manager notices that the junior members are making many mistakes that require rework from senior members. This is causing delays. What should the project manager do to improve efficiency?
Easy725A project manager is developing the project charter. Which of the following should be included as a key element in the charter to define the project's boundaries?
Medium726A project manager is calculating the critical path. The network diagram shows two paths: Path A: A(3 days) → B(4 days) → C(2 days) = 9 days; Path B: D(5 days) → E(1 day) → F(3 days) = 9 days. Both have total float of zero. What is the total float for an activity on Path A?
Hard727A project has a critical path duration of 45 days. Activity X on the critical path has an optimistic duration of 5 days, a pessimistic duration of 13 days, and a most likely duration of 8 days. What is the expected duration of activity X using PERT?
Hard728A project manager is creating a risk register. The team identifies a risk that could cause a data breach if a server is misconfigured. The probability is low, but impact is high. Which risk response strategy is most appropriate?
Medium729In a network diagram, Activity B has a duration of 5 days. Its predecessor is Activity A (duration 3 days) with a finish-to-start relationship. Activity C (duration 4 days) has a start-to-start relationship with Activity B with a 2-day lag. What is the earliest day Activity C can start?
Hard730Which THREE items are typically found in a project charter? (Select THREE)
Hard731In a risk register, which field describes the event that signals a risk is about to occur?
Easy732Which TWO of the following are common types of organizational structures that affect project management?
Easy733A project requires a specific software library that is only available from a single vendor. The vendor's delivery schedule dictates when the project can begin integration testing. This dependency is best described as:
Medium734Which project life cycle phase involves obtaining formal acceptance of the project deliverables and releasing project resources?
Medium735Match each project management process group to its primary purpose.
Medium736A company is migrating to a new ERP system. The project manager needs to ensure minimal downtime during cutover. Which deployment strategy should be recommended?
Hard737A company is evaluating two projects. Project A has an NPV of $50,000 and a payback period of 3 years. Project B has an NPV of $40,000 and a payback period of 2 years. Which project should be selected based on NPV?
Hard738Which TWO of the following are key characteristics of a project? (Select TWO.)
Medium739Refer to the exhibit. Which risk response strategy is most appropriate for this risk?
Easy740A project has a budget at completion (BAC) of $200,000. After two months, the earned value (EV) is $80,000 and the actual cost (AC) is $90,000. The CPI is 0.89. Which THREE statements are correct regarding cost performance and forecasting?
Hard741A project manager creates a visual representation that shows the 20% of causes contributing to 80% of the problems in a project. Which tool is being used?
Hard742During project execution, the team lead reports that a key developer is leaving the company. The project sponsor is concerned about the impact on the project schedule. What should the project manager do FIRST?
Medium743During the closing phase of a project, which TWO activities should be performed?
Medium744A project team has identified a risk that a key supplier may go out of business. The probability is low but the impact is high. The project manager decides to find an alternative supplier and sign a contract with them as a backup. This is an example of which risk response strategy?
Hard745Which TWO items are typically included in a project status report?
Hard746A team is implementing a disaster recovery plan that includes replication to a secondary data center. Which metric should the project manager prioritize defining in the DR plan?
Medium747During project execution, the project manager notices that the development team has been adding extra features that were not requested by the customer. Which of the following describes this behavior?
Medium748A project manager is working in an organization where the project team members report to both a functional manager and the project manager. The project manager has moderate authority and shares resource management with functional managers. This is an example of which organizational structure?
Medium749A project manager is planning a new software development project. Which tool should the project manager use to break down the project deliverables into smaller, manageable work packages?
Easy750During a project status meeting, a stakeholder requests a report showing the variance of actual costs from the planned budget. Which metric should the project manager include?
Medium751A project manager is evaluating a risk with a probability of 30% and an impact of $50,000. What is the expected monetary value (EMV) of this risk?
Medium752A project team is entering the Storming stage of Tuckman's model. Which TWO characteristics are typical of this stage?
Medium753A project manager notices that a task on the critical path is delayed by 3 days. Which tool should the project manager use to determine the impact on the project completion date?
Medium754Which THREE documents are typically finalized during the project closure phase?
Hard755A project manager is assigned to a new project that involves developing a mobile application. The project sponsor wants to ensure that the project delivers value to the organization. Which project management concept should the project manager apply to align the project with strategic goals?
Medium756A project has a budget of $500,000 and is 40% complete. The actual cost incurred is $250,000. What is the cost variance?
Hard757A project manager works in an organization where team members report to both a functional manager and a project manager. The project manager has moderate authority and shares resource control with the functional manager. Which type of organizational structure does this describe?
Medium758A project to deploy a new CRM system is in the execution phase. The team frequently encounters integration issues because the development environment does not match the production environment. The project manager has not enforced change control, and team members have made undocumented changes to the development environment. What should the project manager do first?
Easy759A project team uses planning poker to estimate user stories. The product owner describes a story that involves integrating with a third-party API. The team discusses unknowns and then votes. The estimates are 5, 8, 13, and 20 story points. What should the team do next?
Hard760During project executing, the team is developing a communication plan. Which THREE factors should the project manager consider when determining the communication needs of stakeholders?
Medium761A project team is decomposing the project scope into smaller, manageable components. Which rule ensures that the WBS includes 100% of the work defined in the scope?
Medium762A project manager uses a diagram to identify the most frequent causes of defects in a process. The diagram displays bars in descending order and a cumulative line. Which quality tool is being used?
Medium763A project manager wants to measure the percentage of work completed compared to the planned schedule. Which metric should be used?
Medium764A project manager has just received approval for the project charter. What is the next primary activity in the initiation phase?
Easy765A project sponsor is reviewing a proposal for a new project. The expected cash flows are: Year 0: -$100,000; Year 1: $30,000; Year 2: $40,000; Year 3: $50,000. The discount rate is 10%. Which of the following is the Net Present Value (NPV) of the project?
Hard766A project team is creating a work breakdown structure (WBS) for a software development project. The project manager wants to ensure that all deliverables are identified and decomposed into manageable work packages. Which tool should the team use to represent the hierarchical decomposition of the work?
Medium767A project manager is reviewing the project charter and notes that a specific software platform must be used for the deliverable. The project sponsor has mandated this technology due to organizational standards. In which category of constraint should this requirement be documented?
Medium768A project is in the execution phase, and the project manager receives a change request to add a new feature that is not in the scope statement. The change request has been approved by the change control board. What must the project manager do next?
Hard769Which document formally records the deliverables, acceptance criteria, exclusions, assumptions, and constraints of a project?
Easy770Which of the following BEST describes the role of a project sponsor?
Easy771A project sponsor is reviewing a project that has a Net Present Value (NPV) of -$15,000. What should the sponsor recommend?
Hard772A project manager is developing the project schedule. Dependencies include: Task A starts after Task B finishes; Task C must be completed before Task D can start; Task E can start when Task F starts. Which dependency types are being used?
Medium773A project manager is developing the project management plan. The sponsor requests detailed cost estimates for each work package, but the activities have not yet been defined. What should the project manager do?
Medium774A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000, and the actual cost (AC) is $120,000. What is the estimate at completion (EAC) assuming the current cost performance index (CPI) will remain the same?
Hard775Refer to the exhibit. What should the project manager do first?
Easy776During project closing, which TWO activities are typically performed?
Easy777A project team is identifying risks. They gather a group of experts who provide anonymous responses to a questionnaire. The facilitator aggregates the responses and shares them, then the experts revise their answers. Which technique is being used?
Medium778A project sponsor asks for a document that outlines the high-level scope, objectives, and key stakeholders of a new project. Which document should the project manager provide?
Easy779A project manager is assigned to a project that has already been chartered. The project sponsor has provided the project charter and initial budget. The project manager is now in the planning phase. During the first planning meeting, the team identifies a major risk: a key supplier may go out of business before the project ends. The project manager needs to proceed. Which of the following is the NEXT step?
Easy780Which TWO techniques are used in the Perform Quantitative Risk Analysis process? (Choose two.)
Hard781A project manager is selecting two documents that are essential for defining project scope. Which TWO documents should they choose?
Medium782An agile team uses story points for estimating effort. During sprint planning, the team's average velocity is 30 story points per sprint. The product owner wants to commit to 35 story points for the upcoming sprint. What should the team do?
Medium783During project closing, which activity involves obtaining formal acceptance from the customer or sponsor that deliverables meet requirements?
Medium784The project team is experiencing conflicts over task assignments. Which document should the project manager reference to clarify roles and responsibilities?
Medium785A project manager is evaluating the financial viability of several proposed projects. The steering committee wants to select projects that maximize return over time. Which TWO financial metrics should the project manager use to compare long-term profitability? (Select TWO).
Medium786A project manager is creating a visual timeline that displays tasks as horizontal bars, shows dependencies between tasks, and highlights the critical path. Which tool should the manager use?
Easy787Which project management process group involves obtaining formal acceptance of the project deliverables and archiving project documents?
Easy788A project manager is reviewing earned value data: PV = $150,000, EV = $120,000, AC = $130,000. Which THREE statements are correct?
Hard789Which TWO documents are typically included in the project management plan?
Medium790A project has a mandatory dependency between two activities: the foundation must be poured before the walls can be erected. This dependency is based on the physical nature of the work and cannot be changed. What type of dependency is this?
Medium791A project team is analyzing potential risks. They gather experts who provide anonymous responses to a questionnaire, and then the facilitator shares a summary for further rounds of feedback. Which risk identification technique is being used?
Medium792A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?
Medium793A project manager is analyzing project performance using earned value management. Which THREE metrics are used to calculate the estimate at completion (EAC)?
Hard794During project execution, a stakeholder requests a change that will increase costs. Which document should the PM update first?
Medium795Refer to the exhibit. Which change request(s) require formal approval from the change control board?
Easy796In which organizational structure does the project manager have the least authority?
Easy797In an Agile project, the team uses story points to estimate effort. During sprint planning, they select user stories from the product backlog and assign them to the sprint. What is the resulting list of items committed for the sprint called?
Easy798A project manager identifies a risk that a key team member might leave during the project. To reduce the impact, she cross-trains other team members. Which risk response strategy is being applied?
Medium799During project execution, a stakeholder requests a new feature that was not included in the original scope. The project manager initiates a change request. What is the next step in the integrated change control process?
Medium800Which THREE are valid types of project termination? (Choose three.)
Hard801A project has a planned value (PV) of $50,000, earned value (EV) of $40,000, and actual cost (AC) of $45,000. What is the schedule variance (SV) and cost variance (CV)?
Medium802In earned value management, the project has an EV of $50,000, PV of $60,000, and AC of $55,000. What is the cost variance (CV)?
Medium803During project initiation, the project sponsor provides the project manager with a document that authorizes the project and assigns the project manager. This document also outlines high-level scope, budget, and timeline. Which document is this?
Hard804Which THREE of the following are key components of a project management plan?
Medium805A project manager is managing a construction project. The scope is well-defined, but the customer is open to minor changes during execution. Which methodology is most suitable?
Easy806During a project, a key stakeholder requests an additional feature that was not in the original scope. The project manager logs a change request and evaluates that the change will increase the project cost by 5% and delay the schedule by 2 weeks. After the change control board (CCB) approves the request, what is the project manager's NEXT step?
Hard807A project manager is assigning resources to activities. Activity X requires a specialized skill that is only available from a contractor. The project manager decides to hire the contractor. Which TWO documents are most likely to be used to define the work and terms for this contractor? (Select TWO).
Hard808A project is being planned in a matrix organization. The project manager needs to identify key roles and their responsibilities. Which THREE of the following are typical project roles? (Choose three.)
Hard809A project manager needs to identify which tasks are critical to the project's completion date. After creating the project schedule, which tool should be used to visualize the critical path?
Medium810In which organizational structure does the project manager have the least authority over project resources?
Easy811Which THREE of the following are risk identification techniques?
Medium812During project execution, a key stakeholder requests a new feature that was not in the original scope. The project manager is concerned about the impact on the schedule and budget. This is an example of:
Medium813Which TWO of the following activities are typically performed during the initiation phase of a project?
Easy814Which document breaks down the project deliverables into smaller, more manageable components?
Easy815A project manager is developing a communication plan. Which two elements should be included in the plan? (Select TWO)
Medium816A project team is in the Performing stage of Tuckman's model. Which TWO behaviors are characteristic of this stage?
Easy817During project execution, a stakeholder requests a new feature that was not in the original scope. The project manager adds it to the change log and obtains approval. Which document should be updated NEXT?
Medium818A project manager is decomposing the project scope into smaller components. Which output is produced?
Medium819A project is falling behind schedule. The project manager considers crashing or fast-tracking. Which THREE statements about these techniques are correct? (Select three.)
Hard820A project manager is assigned to a new project that has a tight deadline. The sponsor wants to fast-track the project by overlapping some phases. Which project management concept should the PM be most concerned about regarding this approach?
Easy821During a project, the project manager calculates the following: Earned Value (EV) = $50,000, Planned Value (PV) = $60,000, Actual Cost (AC) = $55,000. Which statement accurately describes the project's performance?
Hard822A project is in the execution phase, developing a mobile payment application. The project manager receives a report that a critical security vulnerability was discovered in the third-party authentication library used by the application. The library is widely used and has an available patch that requires upgrading to a newer version. However, upgrading the library will break compatibility with the existing user authentication database schema, requiring a database migration that was not planned. The project has a fixed budget and a tight deadline. The change control board (CCB) meets weekly, and the next meeting is in three days. The lead developer recommends applying the patch immediately without waiting for CCB approval, arguing that the security risk is high and the patch is straightforward. What is the BEST course of action for the project manager?
Hard823A project manager is reviewing the project schedule and notices that the critical path has a duration of 120 days. One activity on the critical path has a duration of 15 days and a total float of 0. If the duration of that activity is reduced by 5 days, what is the new critical path duration?
Medium824Which TWO of the following are examples of project constraints? (Select TWO).
Medium825A project manager is evaluating two projects. Project A has an initial investment of $50,000 and expected annual returns of $15,000 for 5 years. Project B has an initial investment of $80,000 and expected annual returns of $22,000 for 5 years. Based on payback period, which project should be selected, and what is the payback period for that project?
Hard826A project is experiencing cost overruns. The project manager wants to calculate key earned value metrics. Which THREE metrics are needed to compute the cost performance index (CPI) and schedule performance index (SPI)? (Select three.)
Hard827A project manager is in the process of developing the project charter. Which of the following would be included in the project charter?
Easy828A project manager is conducting a risk assessment and identifies a risk with a high probability and high impact. The team decides to purchase insurance to cover potential losses. This is an example of which risk response strategy?
Hard829A project manager is building a project schedule and needs to identify the critical path. Which TWO techniques are commonly used in project scheduling tools to help determine the critical path?
Hard830Which TWO of the following are commonly considered as project constraints according to the Project Management Body of Knowledge?
Medium831Which TWO documents are typically created during the project initiation phase? (Select TWO.)
Medium832A project manager is defining the roles and responsibilities for a project. Which TWO of the following are typical responsibilities of the project sponsor? (Select TWO).
Easy833Match each quality management concept to its definition.
Medium834A project has been delayed due to unexpected regulatory changes. The project manager has analyzed the impact and determines that the project will miss the original deadline by two months. The sponsor is concerned about the delay. What is the first step the PM should take?
Hard835A project manager is preparing a report for stakeholders that lists project risks, their impact, and response strategies. Which document should be used?
Medium836A project is closing. The project manager collects feedback from the team on what went well and what could be improved. Which document is being created?
Hard837Which TWO activities are typically performed during the initiation phase of a project?
Medium838During project execution, a team member reports that a key deliverable will be delayed by two weeks due to an unforeseen technical issue. The project manager evaluates the change and determines the impact on the critical path. According to best practices, what should the project manager do first?
Medium839Which of the following best describes a program?
Easy840A project team is using a document management system with version control. A team member accidentally overwrites the latest version of the project charter with an older draft. What is the BEST way to recover the correct version?
Hard841During project execution, a team member proposes a change that will affect the scope baseline. What is the first step the project manager should take?
Hard842Refer to the exhibit. What is the duration of the critical path?
Hard843A project team is using Jira for agile development. They have a list of features to be developed over multiple sprints. What is the term for this list, which represents all the work planned for the project?
Medium844A project has a budget at completion (BAC) of $200,000, earned value (EV) of $120,000, and actual cost (AC) of $130,000. What is the estimate at completion (EAC) if the cost performance is expected to continue?
Hard845In an Agile project, the team uses a tool to manage user stories and tasks. Which tool is specifically designed for Agile project management, supporting Scrum and Kanban boards?
Easy846In an agile project, the team is using user stories to capture requirements. Which of the following is the correct format for a user story?
Medium847Refer to the exhibit. Which element of the project charter is missing from this exhibit?
Hard848In a fixed-price contract, which party bears the risk of cost overruns?
Easy849A project team is using a tool to manage user stories, sprints, and backlog items in an Agile project. Which tool is most appropriate?
Medium850A project manager is reviewing a control chart for a manufacturing process. Several data points fall outside the upper control limit (UCL). What type of variation do these points indicate?
Hard851During the executing phase, a project manager observes that team members are starting to collaborate and share ideas openly. According to Tuckman's stages of team development, which stage is the team likely in?
Medium852An agile team uses story points to estimate user stories. During planning poker, one developer consistently gives much higher estimates than the rest of the team. What is the best action for the team?
Medium853A project manager is estimating the cost of a new software development project. They use historical data from a similar project to derive the cost per function point and multiply it by the expected number of function points. Which estimation technique is being used?
Medium854During project execution, a critical team member is assigned to another project and is no longer available full-time. The project manager updates the issue log and tries to negotiate with the functional manager for an alternative. However, the issue cannot be resolved at this level. What is the next step according to issue management best practices?
Medium855A project manager wants to identify the most significant causes of delays in a software development project. Which quality tool should she use to prioritize the causes based on the Pareto principle?
Medium856A project manager is developing the project charter. Which of the following should be included as a key element of the project charter?
Easy857A project is in the Monitoring and Controlling phase. A change request has been submitted to add a new feature. The change control board (CCB) has approved the change. Which THREE actions should the project manager take next?
Hard858Which THREE are common types of project organizational structures? (Choose three.)
Hard859During a sprint review, the team shows that they completed 30 story points this sprint, which is consistent with their average velocity. The product owner asks how much work the team can likely complete in the next two sprints. Using velocity, what is the best estimate?
Medium860A project manager is managing a project to develop a new medical device. The project is subject to strict regulatory compliance. Halfway through the project, an audit reveals that several design documents were not properly reviewed and approved as required by the quality management plan. The project manager must address this noncompliance. The project is already behind schedule. What should the project manager do FIRST?
Hard861Which THREE items are typically included in a project status report?
Hard862During a project, the team adds extra features to a deliverable because they believe it will increase customer satisfaction, even though the features were not specified in the requirements. This is an example of:
Medium863A large software development project is using a waterfall life cycle. The project has just completed the design phase, and the project manager is scheduled to conduct a phase gate review before proceeding to coding. The project sponsor, under pressure from upper management to deliver faster, asks the project manager to skip the gate review to save one week and move directly to coding. The sponsor argues that the design is sound and the review is a formality. What should the project manager do?
Hard864Which document formally authorizes a project and provides the project manager with the authority to apply organizational resources?
Easy865During project planning, the project manager wants to ensure that all work is defined and that no work is omitted. Which tool or technique should be used?
Medium866A project team is estimating costs for a new software development project. They use data from a similar previous project and adjust for size differences. Which estimating technique is being used?
Medium867A project manager is leading a software upgrade project. The project is using an agile methodology with two-week sprints. After three sprints, the team has not completed all planned user stories, and the product owner is frustrated. The project manager reviews the velocity and finds it is 30% lower than estimated. The team cites unforeseen technical debt. What should the project manager do?
Medium868During project execution, a team member reports that a critical deliverable is behind schedule due to an unexpected dependency. The project manager needs to update the project schedule and communicate the impact. Which tool should the project manager use first to assess the impact on the critical path?
Hard869A project manager is developing a stakeholder engagement plan. Which THREE items should be included in this plan? (Choose three.)
Easy870A project manager is identifying stakeholders for a new product launch. She uses a power/interest grid to categorize stakeholders. For which ONE quadrant should the project manager apply the strategy of 'Manage Closely'?
Medium871A project manager is preparing a project charter. Which of the following should be included in the charter?
Medium872Put the steps for creating a work breakdown structure (WBS) in the correct order.
Medium873You are the project manager for a large infrastructure project that involves upgrading the network switches across five regional offices. The project has a budget of $500,000 and a deadline of six months. During the third month, you receive a report that the vendor has encountered a manufacturing defect in the switches, causing a two-month delay. Additionally, the cost to replace the defective switches will be $100,000 over budget. The project sponsor is concerned about the impact on the business and wants to know the best way to move forward. There is a possibility that the vendor can expedite shipping for an additional $50,000, but it will only save one month. Alternatively, you can switch to a different vendor, but that would require renegotiating contracts and retesting, adding three months to the schedule. Another option is to descope one of the regional offices to reduce costs and time. However, that office is critical for an upcoming product launch. What is the BEST course of action for the project manager?
Hard874Which cost estimation technique uses historical data from similar projects to estimate the current project?
Easy875During a software development project, the team estimates story points using planning poker. A story is estimated at 8 points, while a similar story was previously estimated at 5 points. What is the primary reason for using relative sizing with story points?
Medium876A project is in execution when a critical vendor fails to deliver a key component. The project manager determines this will push the project past the deadline. After submitting a change request, what should the project manager do next?
Hard877Refer to the exhibit. Based on the risk register, which risk has the HIGHEST priority?
Hard878During a project's executing phase, a key team member requests a change to the project scope. What should the project manager do first?
Easy879A project manager is evaluating two project proposals. Proposal A has an NPV of $50,000 and a payback period of 2 years. Proposal B has an NPV of $30,000 and a payback period of 1.5 years. Which proposal is more financially beneficial based on NPV?
Medium880During scope verification, the project manager requests formal acceptance of a deliverable from the customer. The customer refuses to sign, stating the deliverable does not meet acceptance criteria. What should the project manager do next?
Medium881In a manufacturing project, the team uses a Pareto chart to analyze defects. The chart shows that 80% of defects come from 20% of the causes. Which principle does this illustrate?
Medium882A project manager wants to document knowledge gained during the project to help future projects. Which document should be used?
Easy883A project is deploying a new virtualized server environment. The project manager receives a report that resource pooling is inefficient. Which technology can best improve resource utilization across the virtual hosts?
Hard884A project is in execution, and the project manager discovers that a key resource is overallocated. Which of the following actions should the project manager take to resolve this?
Hard885A project manager is creating a document that defines the project's objectives, key stakeholders, high-level requirements, and initial budget. Which document is this?
Easy886A project manager is assigned to a new software development project with clearly defined requirements and minimal expected changes. Which project management methodology is most appropriate for this scenario?
Easy887A project schedule is displayed as a bar chart showing tasks against a calendar. Which tool is being used?
Easy888A project is in the execution phase. The project manager discovers that the actual cost performance index (CPI) is 0.8 and the schedule performance index (SPI) is 0.9. What does this indicate about the project?
Hard889Which TWO of the following are characteristics of a project? (Choose two.)
Easy890Which TWO of the following are key components of IT infrastructure that a project manager should consider when planning a new software deployment? (Choose two.)
Medium891In a construction project, the foundation must be completed before the framing can begin. This is an example of which type of dependency?
Medium892During project execution, a key stakeholder requests a change that would require additional funding. The project manager should:
Medium893What is the primary purpose of a Work Breakdown Structure (WBS) in project planning?
Easy894A project manager is reviewing the communication plan. Which THREE elements must be included to ensure effective project communications? (Choose three.)
Hard895A project manager is estimating the cost of a new software development project. Since the project is similar to a previous one, the manager uses the cost of the previous project as a basis, adjusting for known differences. Which cost estimation technique is being used?
Medium896A small consulting firm is considering taking on a new project to develop a custom software application for a client. The firm has limited resources, and the owner, who is also the project manager, must decide whether to accept the project. The client has offered a fixed price of $50,000 with a six-month deadline. The firm estimates that the project will require 800 hours of work from a senior developer and a junior developer. The senior developer is currently assigned to another project that will last another four months, while the junior developer is available full-time. The owner has a decent cash reserve but is concerned about overextending the team. What should the owner do FIRST?
Easy897During project planning, the team creates a hierarchical decomposition of the total scope of work to be carried out by the project team. Each descending level represents an increasingly detailed definition of the project work. What is this called?
Medium898A project team is facing a critical issue that the project manager cannot resolve. According to best practices, what should the project manager do?
Medium899A project manager is leading a team that uses a shared network drive for storing project documents. Multiple team members have accidentally overwritten each other's work, causing confusion. Which tool should the project manager implement to prevent this issue?
Medium900A project team is developing a mobile app. The project manager notices that the team is frequently interrupted by requests from other departments. The team members are matrixed, and their functional managers assign other tasks. The project manager wants to improve focus. Which of the following actions is MOST appropriate?
Easy901A project manager is creating the project management plan. Which TWO subsidiary plans should be included? (Select TWO.)
Medium902A project manager notices that the actual cost (AC) is $50,000, the earned value (EV) is $45,000, and the planned value (PV) is $55,000. Which statement is true regarding schedule and cost performance?
Medium903In an agile project using Jira, the product owner wants to prioritize the work for the next iteration. Which document or artefact should they refer to?
Easy904A project team is in the process of obtaining seller responses, evaluating proposals, and awarding a contract. Which procurement document is used to formally request a proposal from potential sellers?
Medium905In an agile project using Jira, the team creates a board that visualizes the workflow with columns such as 'To Do', 'In Progress', and 'Done'. Which type of board is this?
Medium906A project manager is creating the project charter and needs to identify the project's key stakeholders. Which of the following is the most reliable source for identifying stakeholders?
Easy907You are managing a software development project with a fixed deadline. The project team consists of 10 developers and 2 testers. The project is currently in the execution phase. During a status review, you find that one of the critical path tasks is two weeks behind schedule due to a key developer being reassigned to another project. The product owner is unwilling to reduce scope. The project sponsor has instructed you to bring the schedule back on track without increasing the budget. The project plan does not include any contingency time. Which of the following is the best course of action?
Hard908A project manager is developing a network diagram and needs to represent an activity that can start only after its predecessor has finished. Which dependency type does this describe?
Medium909A project manager notices that a task is taking longer than planned and the project is falling behind schedule. The project manager wants to identify the root cause of the delay. Which quality tool would be most appropriate?
Medium910Which THREE of the following are project management knowledge areas as defined in the PMBOK Guide?
Hard911During project execution, a stakeholder requests a change to the project scope. What is the first step the project manager should take?
Medium912During project execution, a critical team member resigns. The project manager must reassign tasks. The project has a tight deadline and no backup resources. Which technique best minimizes schedule impact?
Hard913A project manager is closing a project. Which THREE activities are part of the project closure process? (Select THREE).
Medium914During the initiating phase of a project, a project charter is created. Which of the following is typically included in a project charter?
Easy915A project manager is evaluating risk responses. For a risk with high probability and high impact, which risk response strategy is most appropriate to eliminate the threat?
Medium916Which document formally authorizes a project and assigns the project manager?
Easy917A project is behind schedule due to underestimation of task durations. The project manager needs to compress the schedule without increasing costs. Which technique should the project manager consider?
Hard918A project manager is planning a marketing campaign for a new product launch. The campaign has a tight budget and strict deadline. During execution, the marketing team proposes adding a social media component that was not in the original scope. The project manager is concerned about scope creep. Which TWO actions should the project manager take to manage this situation?
Medium919Which TWO tools are used for quality management in a project?
Easy920A project manager is developing a project charter. Which of the following is typically included in the project charter?
Medium921During a server migration project, the team discovers that the new servers have a different CPU architecture than the old ones. The project manager must decide the best course of action. What should the project manager do first?
Medium922A project team is developing a new software product. The product owner frequently changes priorities based on customer feedback. The team needs to adapt quickly and deliver value incrementally. Which project management methodology is most suitable?
Medium923A project involves integrating an on-premises IT infrastructure with a public cloud provider. The project team must ensure secure connectivity. Which of the following should be implemented?
Hard924Refer to the exhibit. Which risk should the project manager address first?
Medium925Which of the following best defines a project?
Easy926A project manager is working on a project to upgrade the company's email system from an on-premises Exchange server to Microsoft 365. The project has completed the planning phase and is now in execution. During a weekly status meeting, the lead engineer reports that the initial migration batch of 100 users experienced significant delays due to unexpected compatibility issues with custom email add-ins used by the finance department. Additionally, the migration tool failed to synchronize some mailbox items, causing data loss for three users. The project timeline is tight, and the sponsor is concerned about meeting the go-live date in four weeks. There are still 900 users to migrate. The project manager needs to take action. Which of the following is the BEST course of action?
Hard927A collection of projects and programs managed together to achieve strategic objectives is known as a:
Easy928Which THREE of the following are outputs of the project initiation process? (Choose three.)
Medium929A project manager is updating the issue log for a new issue: a critical supplier has gone out of business, causing a shortage of materials. Which TWO fields are essential to include in the issue log entry?
Medium930A project sponsor has requested a document that provides a high-level overview of the project, including business need, key assumptions, constraints, and initial risks. Which document should the project manager provide?
Medium931A project team is estimating the duration of a task. The optimistic estimate is 4 days, the pessimistic is 12 days, and the most likely is 6 days. Using the three-point estimating technique (PERT), what is the expected duration?
Easy932Put the steps for closing a project in the correct order.
Medium933A project team is in the execution phase and the project manager notices that the actual cost is consistently higher than planned. Which process should be used to address this?
Easy934A project manager is reviewing the key components of a project management plan. Which THREE of the following are typically included in a project management plan?
Hard935During a sprint planning meeting, the development team estimates user stories using story points. They each have a set of cards with values like 1, 2, 3, 5, 8, 13. After discussing a story, all team members simultaneously reveal their chosen card. What technique are they using?
Medium936A project manager is creating the WBS. Which THREE of the following are characteristics of a well-constructed WBS?
Medium937A project manager is leading a team for a new product launch. The team members are from different departments and have conflicting priorities. The project is still in the planning phase. Which of the following is the BEST course of action for the project manager?
Medium938A project team is experiencing conflicts and power struggles among members. According to Tuckman's stages of group development, which stage is the team likely in?
Medium939In which organizational structure does a project manager have the highest level of authority?
Easy940A project manager is performing schedule compression because the project is behind schedule. The team decides to start a follow-on activity before its predecessor is fully completed. This approach increases the risk of rework. Which schedule compression technique is being used?
Medium941A project manager is evaluating two potential projects. Project A has an NPV of $50,000, while Project B has an NPV of -$10,000. Which project should the organization select based solely on NPV?
Hard942A construction project is in the execution phase. The project manager receives a report that the concrete supplier has delivered substandard material that does not meet specifications. The project is on a tight schedule, and rejecting the material will cause a two-week delay. The supplier is the only one available within the required timeframe. What should the project manager do FIRST?
Medium943A project manager is updating the risk register after a risk event occurred. The risk response plan included a contingency reserve, but the actual impact was higher than expected. What should the project manager do next?
Hard944Which TWO tools are commonly used for risk identification in a project?
Easy945A project manager has identified a risk with a probability of 0.4 and an impact of $50,000. What is the risk score?
Medium946You are a project manager for a construction project. During the monitoring and controlling phase, you review the project performance and find that the earned value (EV) is $50,000, the actual cost (AC) is $60,000, and the planned value (PV) is $55,000. The project is behind schedule and over budget. The project team is demotivated due to the delays. The customer has expressed concerns about project progress. The project contract includes a penalty clause for missed milestones. Which of the following actions should you take first?
Hard947A project manager is reviewing project selection methods. Which method calculates the present value of future cash flows minus the initial investment?
Medium948A project manager is reviewing the project's earned value data. The cost performance index (CPI) is 0.85, and the schedule performance index (SPI) is 1.05. What does this indicate about the project?
Hard949What is the primary difference between a risk and an issue in project management?
Easy950A project manager is selecting a project management tool for a hybrid project that requires both a Gantt chart view for waterfall tasks and a Kanban board for agile tasks. Which TWO tools would best meet these requirements?
Medium951Which THREE are examples of direct costs in a project? (Select THREE.)
Hard952A project has a BAC of $200,000. After three months, the earned value (EV) is $80,000 and the actual cost (AC) is $90,000. What is the cost variance (CV) and what does it indicate?
Medium953Which document is used to track and manage changes to the project baseline?
Easy954Refer to the exhibit. A project manager is monitoring server performance for a web application deployment. Based on the exhibit, what is the status of the web server?
Easy955Which TWO of the following are outputs of the monitoring and controlling process group? (Select two.)
Easy956Which TWO of the following are methods of schedule compression? (Select TWO).
Easy957Match each project management methodology or framework to its key characteristic.
Medium958A project manager is preparing a procurement document that asks vendors to provide a price for a specific product. Which type of document is this?
Easy959A project manager is reviewing a change request that has been approved. The change will affect the project scope, schedule, and budget. Which document should the project manager update first to ensure all changes are captured and communicated?
Hard960A project manager is reviewing the schedule performance and finds that the earned value (EV) is $50,000 and the planned value (PV) is $60,000. What does this indicate?
Medium961A project manager is using a control chart to monitor quality. The data points fall within the control limits but show a run of seven points above the mean. What does this indicate?
Hard962During project execution, a stakeholder requests an additional feature. The project manager documents the request and evaluates its impact on the triple constraint. Which process is being performed?
Medium963A project manager is assigned to a program that includes multiple projects aimed at digital transformation. Which TWO statements correctly describe the relationship between projects, programs, and portfolios? (Select TWO).
Hard964A project manager is planning a software development project and needs to determine the sequence of activities. The team will first gather requirements, then design the architecture, then develop the code, then test, and finally deploy. Which project life cycle model is being used?
Easy965A company is implementing a new backup solution for its mixed environment of legacy and modern servers. The backup server is connected to the same network segment as production traffic. During initial testing, some backups fail intermittently, especially during peak hours. The backup logs show timeouts. The project manager is asked to identify the most likely cause and recommend a solution. Which of the following is the best course of action?
Easy966Which TWO documents are typically created during project initiation?
Easy967You are the project manager for a software upgrade project at a mid-sized company. The project has a budget of $500,000 and a timeline of 12 months. The team consists of 10 members, including developers, testers, and a business analyst. The project is in month 8, and the team has completed 60% of the work but has spent $400,000. The sponsor is concerned about the budget overrun and asks for a recovery plan. The original estimate at completion (EAC) was $500,000. Using earned value management, you calculate the cost performance index (CPI) is 0.75 and the schedule performance index (SPI) is 0.90. The team is demoralized due to scope creep and unclear requirements. The business analyst recently left, and the replacement is not yet fully onboarded. Which of the following is the BEST course of action to bring the project back on track?
Hard968A project manager is leading a construction project. The project sponsor has requested that the project be completed one month earlier than originally planned. Which THREE actions should the project manager take to assess the feasibility of this request? (Choose three.)
Hard969A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following statements is TRUE?
Hard970A project manager receives a status report showing that the project is behind schedule. The report uses a red-yellow-green status indicator. What does the red indicator typically signify?
Hard971Which document contains the subsidiary plans for scope, schedule, cost, quality, resources, communication, risk, and procurement?
Easy972During the planning phase, a project manager conducts a stakeholder analysis. Which of the following is the primary purpose of this activity?
Medium973A project manager is selecting tools for agile project management. Which TWO tools are specifically designed for agile methodologies?
Medium974Which TWO documents are typically found in a project's procurement management plan?
Medium975Which document defines the roles and responsibilities of stakeholders in a project and is often presented as a matrix?
Medium976A project manager is using a quality tool that displays data points over time with upper and lower control limits. The tool helps distinguish between common cause and special cause variation. Which tool is this?
Medium977During project closing, a project manager must complete several activities. Which TWO are appropriate for project closure?
Easy978A project manager is identifying stakeholders and documenting their interests and influence. In which project life cycle phase is this activity performed?
Easy979A vendor is hired to provide a service with a fixed price of $100,000, regardless of actual costs incurred. Which contract type is this?
Medium980A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?
HardOther domains
All PK0-005 exam domains
Frequently asked questions
- What does the scenario questions domain cover on the PK0-005 exam?
- scenario questions questions test whether you can apply the concept in context, not just recognise a definition.
- How many questions are in this domain?
- This page lists all 980 scenario questions questions in the PK0-005 question bank. The actual exam draws from this domain proportionally to its weighting in the official exam blueprint.
- What is the best way to practise this domain?
- Start with a short focused session (10 questions) to identify gaps, then work through explanations. Repeat with a longer session once the weak areas feel solid.
- Can I practise only scenario questions questions?
- Yes — the session launcher on this page filters questions to this domain only. Choose any session length for inline explanations and scoring.