- A
$240,000
EAC = BAC/CPI = $200,000 / (100,000/120,000) = $200,000 / 0.8333 = $240,000.
- B
$200,000
Why wrong: This is the original BAC, not adjusted for cost overrun.
- C
$220,000
Why wrong: This value might come from AC + (BAC - EV) = $120,000 + $100,000 = $220,000, but that formula is for EAC when future work is at planned rate, not when cost performance continues.
- D
$180,000
Why wrong: This does not match any standard EAC formula.
Quick Answer
The answer is $240,000 because the estimate at completion (EAC) formula for a continued cost performance assumption is EAC = BAC / CPI. Since the cost performance is expected to continue at the same rate, you first calculate the cost performance index (CPI) as EV divided by AC, which is $100,000 / $120,000 = 0.8333, then divide the BAC of $200,000 by that CPI to arrive at $240,000. On the CompTIA Project+ PK0-005 exam, this scenario tests your ability to distinguish between EAC formulas; a common trap is mistakenly using the formula for atypical variances (EAC = AC + (BAC - EV)) when the question explicitly states cost performance will continue. Remember the mnemonic "Continue CPI" — if the problem says performance will persist, you always divide BAC by CPI.
PK0-005 Tools and Documentation Practice Question
This PK0-005 practice question tests your understanding of tools and documentation. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project has a budget at completion (BAC) of $200,000. The earned value (EV) is $100,000 and the actual cost (AC) is $120,000. If the cost performance is expected to continue, what is the estimate at completion (EAC)?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
$240,000
The estimate at completion (EAC) when cost performance is expected to continue is calculated using the formula EAC = BAC / CPI, where CPI = EV / AC. Here, CPI = $100,000 / $120,000 = 0.8333, so EAC = $200,000 / 0.8333 = $240,000. This formula assumes the same cost efficiency will persist for the remainder of the project.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
$240,000
Why this is correct
EAC = BAC/CPI = $200,000 / (100,000/120,000) = $200,000 / 0.8333 = $240,000.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
$200,000
Why it's wrong here
This is the original BAC, not adjusted for cost overrun.
- ✗
$220,000
Why it's wrong here
This value might come from AC + (BAC - EV) = $120,000 + $100,000 = $220,000, but that formula is for EAC when future work is at planned rate, not when cost performance continues.
- ✗
$180,000
Why it's wrong here
This does not match any standard EAC formula.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates often confuse the EAC formula for continued cost performance with the formula for atypical variances (EAC = AC + (BAC - EV)), leading them to incorrectly select $220,000.
Detailed technical explanation
How to think about this question
The EAC formula used here (EAC = BAC / CPI) is the most common when the cost variance is expected to continue at the same rate, as it extrapolates the current cost efficiency index. In earned value management (EVM), CPI is a key metric; a CPI below 1.0 indicates cost overrun, and using BAC / CPI projects the total cost if that inefficiency persists. Real-world scenarios, such as long-term construction projects, often use this formula when the root cause of cost overruns (e.g., material price increases) is unlikely to change.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Tools and Documentation — study guide chapter
Learn the concepts, then practise the questions
- →
Tools and Documentation practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Tools and Documentation — This question tests Tools and Documentation — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: $240,000 — The estimate at completion (EAC) when cost performance is expected to continue is calculated using the formula EAC = BAC / CPI, where CPI = EV / AC. Here, CPI = $100,000 / $120,000 = 0.8333, so EAC = $200,000 / 0.8333 = $240,000. This formula assumes the same cost efficiency will persist for the remainder of the project.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.