easyMultiple ChoiceObjective-mapped
PK0-005 Practice Question: Which document formally records the deliverables,…
Which document formally records the deliverables, acceptance criteria, exclusions, assumptions, and constraints of a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Scope statement
The scope statement is the document that defines all these elements, establishing the baseline for what is included and excluded from the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Work breakdown structure (WBS)
Why it's wrong here
The WBS decomposes deliverables but does not include acceptance criteria or exclusions.
- ✗
Risk register
Why it's wrong here
The risk register documents risks, not scope details.
- ✗
Project charter
Why it's wrong here
The project charter authorizes the project but does not detail scope elements at this level.
- ✓
Scope statement
Why this is correct
Correct. The scope statement includes all listed components.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.