Courseiva
Tools and DocumentationhardMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project has a BAC of $500,000 and a CPI of 0.8. What is the estimate at completion (EAC) assuming the current cost performance will continue?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

$625,000

EAC = BAC / CPI = $500,000 / 0.8 = $625,000.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • $500,000

    Why it's wrong here

    That's BAC, not EAC.

  • $625,000

    Why this is correct

    Correct formula.

  • $1,000,000

    Why it's wrong here

    Incorrect calculation.

  • $400,000

    Why it's wrong here

    That would be multiplying, not dividing.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.