Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is estimating costs for a new project using a top-down approach based on historical data from a similar project. Which estimation technique is being used?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analogous estimation

Analogous estimation uses historical data from similar projects as a basis.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Three-point estimation

    Why it's wrong here

    Three-point uses optimistic, pessimistic, most likely.

  • Analogous estimation

    Why this is correct

    Analogous uses historical data from similar projects.

  • Bottom-up estimation

    Why it's wrong here

    Bottom-up estimates from individual work packages.

  • Parametric estimation

    Why it's wrong here

    Parametric uses statistical relationship between variables.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.