Courseiva
Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project manager is estimating costs for a new project using a top-down approach based on historical data from a similar project. Which estimation technique is being used?

⚠ Common exam trap

PK0-005 often tests the confusion between analogous (historical analogy) and parametric (unit-rate model) estimation, so candidates must identify whether the basis is a similar project or a statistical relationship.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Analogous estimation

Analogous estimation uses historical data from a similar past project to estimate the current project's cost or duration, typically at a high level (top-down). Because the question specifies a top-down approach based on historical data from a similar project, analogous estimation is the exact match. It is fast and useful early when detailed information is scarce, though less precise than bottom-up methods.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Three-point estimation

    Why it's wrong here

    Three-point estimation averages optimistic, pessimistic and most likely values to model uncertainty; it does not rely on historical analogues. The stem describes analogous estimating, which uses actual costs from a comparable past project as the basis for the new estimate, typically at a top-down level of detail.

  • ✓

    Analogous estimation

    Why this is correct

    Analogous estimation uses historical cost data from a comparable past project to derive the new estimate, which directly matches the top-down approach described. It satisfies the stem's constraint of relying on a similar project's actuals rather than decomposing deliverables, making it fast and inexpensive, though less precise than bottom-up methods.

  • ✗

    Bottom-up estimation

    Why it's wrong here

    Bottom-up estimation aggregates individual work-package costs upward, so it cannot use historical data from a similar project at summary level. It is tempting because it delivers the greatest accuracy when detailed task-level estimates exist, making it the right choice once a WBS has been decomposed.

  • ✗

    Parametric estimation

    Why it's wrong here

    Parametric estimation multiplies a unit rate by a quantity, such as cost per square metre, using a statistical relationship. The stem describes analogous estimating, which scales actual costs from a similar completed project; parametric would apply if a measurable driver and rate were used instead.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.