A project team is decomposing the project scope into smaller, manageable components. Which rule ensures that the WBS includes 100% of the work defined in the scope?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
100% rule
The 100% rule states that the WBS captures all deliverables and work.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Rolling wave planning
Why it's wrong here
Rolling wave plans progressively elaborate.
- ✗
Scope verification
Why it's wrong here
Verification is acceptance, not inclusion.
- ✗
Decomposition rule
Why it's wrong here
Decomposition is the process, not the rule.
- ✓
100% rule
Why this is correct
Correct rule.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.