mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project team is decomposing the project scope…

A project team is decomposing the project scope into smaller, manageable components. Which rule ensures that the WBS includes 100% of the work defined in the scope?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

100% rule

The 100% rule states that the WBS captures all deliverables and work.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Rolling wave planning

    Why it's wrong here

    Rolling wave plans progressively elaborate.

  • Scope verification

    Why it's wrong here

    Verification is acceptance, not inclusion.

  • Decomposition rule

    Why it's wrong here

    Decomposition is the process, not the rule.

  • 100% rule

    Why this is correct

    Correct rule.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.