PK0-005 Practice Question: Which document contains the deliverables,…

Which document contains the deliverables, acceptance criteria, exclusions, assumptions, and constraints for a project?

⚠ Common exam trap

PK0-005 often tests the confusion between the project charter and scope statement, but the charter is high-level authorization while the scope statement contains detailed deliverables, acceptance criteria, and exclusions.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Scope statement

The scope statement is the document that formally defines what is included and excluded from the project, including deliverables, acceptance criteria, exclusions, assumptions, and constraints. It serves as the baseline for scope control and helps prevent scope creep by clearly documenting boundaries.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Work breakdown structure (WBS)

    Why it's wrong here

    A WBS decomposes scope into work packages but records no acceptance criteria, exclusions, assumptions or constraints, so it cannot satisfy this stem. It is tempting because it does capture deliverables hierarchically, and would be correct when the task is breaking down project scope into manageable, assignable components for estimating and scheduling.

  • ✓

    Scope statement

    Why this is correct

    The scope statement defines deliverables, acceptance criteria, exclusions, assumptions and constraints, directly satisfying the stem's requirement for a single document covering all five elements. Unlike the charter, which authorises the project at a high level, the scope statement records this detailed baseline, making it the precise match here.

  • ✗

    Project charter

    Why it's wrong here

    The charter authorises the project and names the project manager; it summarises high-level scope but does not formally document acceptance criteria, exclusions, assumptions and constraints. It tempts as the founding document, yet those details sit in the scope statement.

  • ✗

    Requirements traceability matrix

    Why it's wrong here

    A traceability matrix links requirements to their sources, tests and deliverables; it does not define acceptance criteria, exclusions, assumptions or constraints. It tempts because it tracks requirements, but the scope statement is the document that records those elements.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.