Courseiva
Tools and Documentation →easyMultiple Choice

PK0-005 Tools and Documentation Practice Question

Which document contains the subsidiary plans for scope, schedule, cost, quality, resources, communication, risk, and procurement?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project management plan

The project management plan is the comprehensive document that includes all subsidiary management plans.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project charter

    Why it's wrong here

    The project charter authorises the project and names the project manager; it does not contain subsidiary management plans. It is tempting because it is the founding document that precedes planning, and would be the right answer if the question asked which document formally initiates the project or grants authority.

  • ✓

    Project management plan

    Why this is correct

    The project management plan is the overarching document that integrates all subsidiary plans — scope, schedule, cost, quality, resources, communications, risk and procurement — into a single consolidated baseline, satisfying the stem's requirement for the document containing them.

  • ✗

    WBS

    Why it's wrong here

    The WBS decomposes scope into deliverables and work packages; it holds no schedule, cost, quality, resource, communication, risk or procurement plans. It is tempting because it is a core scope artefact, and would be correct if the question asked how project scope is hierarchically decomposed.

  • ✗

    Risk register

    Why it's wrong here

    The risk register records identified risks, owners, triggers and responses; it is one output of risk planning, not a container for the other subsidiary plans. It is tempting because it is a familiar planning document, and would be correct if the question asked where risk response details are documented.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.