Question 43 of 500
Project Management ConceptsmediumMultiple SelectObjective-mapped

Quick Answer

The answer is high-level project risks and project purpose or justification. These are correct because the project charter is the formal authorization document that grants the project manager authority to use organizational resources, and the PMBOK Guide mandates that it must include the business case for why the project exists along with a preliminary identification of major uncertainties. On the CompTIA Project+ PK0-005 exam, this question tests your understanding of the Initiating process group and the charter’s role in defining scope boundaries before detailed planning begins. A common trap is confusing detailed risk responses with high-level risks, which are broad and identified early. To remember, think of the charter as the project’s “birth certificate” that answers “why” and “what could go wrong” at a high level, not the “how.” A useful memory tip is the mnemonic “PURPOSE and PERIL” — purpose equals justification, peril equals high-level risks.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which TWO of the following are components of a project charter?

Question 1mediummulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project purpose or justification

The project charter is a formal document that authorizes the project and provides the project manager with the authority to apply organizational resources. It must include the project purpose or justification to explain why the project is being undertaken, and high-level risks to identify major uncertainties at the outset. These are foundational components defined by the PMBOK Guide for the Initiating process group.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Work breakdown structure

    Why it's wrong here

    Created after charter.

  • Resource calendars

    Why it's wrong here

    Created during planning.

  • Project purpose or justification

    Why this is correct

    Core component.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Detailed project budget

    Why it's wrong here

    Developed during planning.

  • High-level project risks

    Why this is correct

    Included in charter.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

CompTIA often tests the distinction between components created during Initiating (project charter) versus Planning (WBS, detailed budget, resource calendars), tempting candidates to include detailed planning artifacts as charter components.

Detailed technical explanation

How to think about this question

Under the hood, the project charter serves as the contract between the project sponsor and the project manager, formally recognizing the project's existence. High-level risks in the charter are typically identified using techniques like brainstorming or SWOT analysis, and they are documented in a simple list without detailed response plans. In real-world scenarios, a missing project justification in the charter can lead to scope creep or project cancellation because the business need is not formally agreed upon by stakeholders.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Project purpose or justification — The project charter is a formal document that authorizes the project and provides the project manager with the authority to apply organizational resources. It must include the project purpose or justification to explain why the project is being undertaken, and high-level risks to identify major uncertainties at the outset. These are foundational components defined by the PMBOK Guide for the Initiating process group.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

2 more ways this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. A project manager is developing a project charter. Which of the following is typically included in the project charter?

medium
  • A.High-level project description and product description
  • B.Detailed work breakdown structure (WBS)
  • C.Communication plan with stakeholder details
  • D.Risk register with identified risks and responses

Why A: The project charter is a high-level document that authorizes the project and provides a summary of its purpose and key elements. A high-level project description and product description are core components of the charter, as they define the project's scope and deliverables without going into execution-level detail.

Variation 2. A project manager is preparing a project charter. Which of the following should be included in the charter?

medium
  • A.A complete work breakdown structure (WBS).
  • B.The business case and high-level project description.
  • C.A detailed project schedule with milestones.
  • D.A comprehensive risk register.

Why B: The project charter is a high-level document that authorizes the project and provides the project manager with the authority to apply organizational resources. It must include the business case and a high-level project description to justify the project and define its scope at a strategic level, as specified in the PMBOK Guide.

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.