PK0-005 Practice Question: A project manager is in the process of formally…
A project manager is in the process of formally authorizing a new project. Which document should be created during the initiation phase?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project charter
The project charter formally authorizes the project and gives the project manager authority. Option B is incorrect because the scope statement is created during planning. Option C is incorrect because the WBS is developed in the planning phase. Option D is incorrect because the risk register is part of planning.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project charter
Why this is correct
Formally authorizes the project.
- ✗
Project scope statement
Why it's wrong here
Created during planning phase.
- ✗
Work breakdown structure (WBS)
Why it's wrong here
Developed in planning phase.
- ✗
Risk register
Why it's wrong here
Part of planning phase.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.