A project manager is in the process of formally authorizing a new project. Which document should be created during the initiation phase?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project charter

The project charter formally authorizes the project and gives the project manager authority. Option B is incorrect because the scope statement is created during planning. Option C is incorrect because the WBS is developed in the planning phase. Option D is incorrect because the risk register is part of planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Project charter

    Why this is correct

    Formally authorizes the project.

  • Project scope statement

    Why it's wrong here

    Created during planning phase.

  • Work breakdown structure (WBS)

    Why it's wrong here

    Developed in planning phase.

  • Risk register

    Why it's wrong here

    Part of planning phase.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.