mediumMultiple SelectObjective-mapped
PK0-005 Practice Question: Which TWO of the following are components of the…
Which TWO of the following are components of the project management plan?
⚠ Common exam trap
Test-takers frequently confuse project documents (risk register, issue log, stakeholder register) with formal components of the project management plan, which are the baselines and subsidiary plans.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Scope baseline
The scope baseline and schedule baseline are formal, approved components of the project management plan. The scope baseline consists of the scope statement, Work Breakdown Structure (WBS), and WBS dictionary, while the schedule baseline is the approved version of the project schedule. Both are essential for measuring and controlling project performance.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risk register
Why it's wrong here
The risk register is a project document, not a component of the plan.
- ✗
Issue log
Why it's wrong here
The issue log is a project document.
- ✗
Stakeholder register
Why it's wrong here
The stakeholder register is a project document.
- ✓
Scope baseline
Why this is correct
The scope baseline is a component of the project management plan.
- ✓
Schedule baseline
Why this is correct
The schedule baseline is a component of the project management plan.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.