Courseiva
Project Life CyclemediumMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager is decomposing the project scope into smaller components. Which output is produced?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Work Breakdown Structure (WBS)

Decomposition of scope results in a Work Breakdown Structure (WBS), which breaks down deliverables into work packages.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk breakdown structure

    Why it's wrong here

    Risk breakdown structure organizes risks.

  • Scope statement

    Why it's wrong here

    Scope statement defines scope, not decomposition.

  • Network diagram

    Why it's wrong here

    Network diagram shows activity sequences.

  • Work Breakdown Structure (WBS)

    Why this is correct

    Correct: WBS is the output of decomposition.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.