Courseiva
easyMultiple Choice

PK0-005 Practice Question: Refer to the exhibit

Exhibit

Change Request
ID: CR-001
Date: 2024-09-15
Description: Add a new feature to the mobile app.
Priority: High
Status: Submitted
Impact: Scope increase of 2 weeks and $5,000.
Submitted by: Stakeholder A

Refer to the exhibit. What should the project manager do first?

⚠ Common exam trap

PK0-005 often tests the sequence of change control by presenting plausible-sounding actions like 'inform the sponsor' or 'update the plan' as distractors, catching candidates who forget that impact assessment must always precede any decision or communication.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Review and assess the impact of the change

When a change is proposed or identified, the project manager must first evaluate how it affects scope, schedule, cost, risk, and quality before deciding on any action. Reviewing and assessing the impact of the change is the foundational step in the integrated change control process, ensuring decisions are made with full information. Only after impact analysis should the PM update plans, inform the sponsor, or authorize implementation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Update the project management plan

    Why it's wrong here

    Updating the project management plan would be premature because the exhibit shows a critical path variance that requires immediate root-cause analysis and corrective action planning; the plan is a living document that should reflect approved changes, not initiate them. This option tempts because updating the plan is a standard response to approved scope or schedule changes, and would be correct after the project manager has assessed the variance and obtained change control board approval for a specific corrective action.

  • ✗

    Inform the sponsor

    Why it's wrong here

    Escalating to the sponsor bypasses the first step: assessing the exhibit's actual variance and confirming facts before any communication. Informing the sponsor suits governance escalation once analysis shows the issue exceeds the project manager's authority, but here it pre-empts diagnosis and may relay inaccurate information.

  • ✗

    Implement the change immediately

    Why it's wrong here

    Implementing immediately skips the integrated change control step of evaluating impact on scope, schedule, cost and risk before approval. Immediate implementation suits an approved emergency change or pre-authorised contingency response, but here no assessment or authorisation has occurred, so the change may break baselined commitments.

  • ✓

    Review and assess the impact of the change

    Why this is correct

    Assessing the change's impact on scope, schedule, cost and risk must precede any approval decision or baseline update. This satisfies the stem's requirement to act first, ensuring the change control board receives evidence before authorising or rejecting the request.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.