PK0-005 Practice Question: A project manager is leading an IT infrastructure…

A project manager is leading an IT infrastructure upgrade project that follows a phased life cycle. During the planning phase, the project team is divided on the estimation approach for the migration tasks. Some members insist on using expert judgment, while others prefer parametric estimating based on historical data from similar projects. The project manager needs to decide on a method to ensure accurate estimates and team consensus. What should the project manager do?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Facilitate a meeting to combine both methods, using parametric estimates as a baseline and expert judgment to adjust.

The correct action is to facilitate a meeting to combine both methods, using parametric estimates as a baseline and expert judgment to adjust for unique project factors. Option C is correct because it leverages the strengths of both approaches and builds consensus. Option A is wrong because averaging results from different methods may not yield accurate estimates and does not resolve the underlying disagreement. Option B is wrong as it imposes one method without team buy-in, potentially reducing commitment and accuracy. Option D is wrong because postponing estimation delays the project unnecessarily and may not lead to better data.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Let the team members use their preferred method and average the results.

    Why it's wrong here

    Inconsistent methods may produce conflicting estimates.

  • Override the disagreement and mandate the use of expert judgment.

    Why it's wrong here

    May reduce team morale and accuracy.

  • Facilitate a meeting to combine both methods, using parametric estimates as a baseline and expert judgment to adjust.

    Why this is correct

    Combines both approaches effectively.

  • Postpone estimation until more data is available from other projects.

    Why it's wrong here

    Unnecessary delay; data exists.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.