In the stakeholder power/interest grid, stakeholders with high power and low interest should be managed using which strategy?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Keep satisfied

According to the power/interest grid, stakeholders with high power and low interest should be kept satisfied to maintain their support.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Keep informed

    Why it's wrong here

    Keep informed is for low power, high interest stakeholders.

  • Manage closely

    Why it's wrong here

    Manage closely is for high power, high interest stakeholders.

  • Monitor

    Why it's wrong here

    Monitor is for low power, low interest stakeholders.

  • Keep satisfied

    Why this is correct

    High power, low interest stakeholders should be kept satisfied.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.