hardMultiple Choice

PK0-005 Risk Score Practice Question

Network Topology
|Refer to the exhibit.Risk Register (excerpt):

A project manager reviews the following risk register: R1 (Vendor delay) has a probability of 0.8 and an impact of 0.6; R2 (Resource shortage) has a probability of 0.6 and an impact of 0.5; R3 (Technical failure) has a probability of 0.6 and an impact of 0.6; R4 (Scope creep) has a probability of 0.7 and an impact of 0.5. Which risk should the project manager prioritize for active monitoring and response?

⚠ Common exam trap

PK0-005 often tests the risk score calculation, and candidates may incorrectly prioritize the risk with the highest impact (R3) or highest probability alone, forgetting to multiply probability by impact.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

R1 - Vendor delay

R1 has the highest risk score when multiplying probability by impact: 0.8 × 0.6 = 0.48, which is higher than R2 (0.6 × 0.5 = 0.30), R3 (0.6 × 0.6 = 0.36), and R4 (0.7 × 0.5 = 0.35). Therefore, R1 should be prioritized for active monitoring and response. The project manager uses the risk score (probability × impact) to rank risks and focus attention on the highest exposure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    R1 - Vendor delay

    Why this is correct

    It has the highest risk score and requires active monitoring.

  • ✗

    R3 - Technical failure

    Why it's wrong here

    Though impact is high, probability is low, and it's accepted.

  • ✗

    R4 - Scope creep

    Why it's wrong here

    It is being avoided, which may reduce priority compared to active risks.

  • ✗

    R2 - Resource shortage

    Why it's wrong here

    R2 scores 0.30, below R1's 0.48 and R3's 0.36, so it ranks third rather than first. Expected monetary value multiplication is the axis here. Resource shortage monitoring suits staffing plans where labour availability drives the schedule, but this register's probabilities and impacts place it behind higher-scoring risks.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.