PK0-005 Project Life Cycle Practice Question
During the initiating phase of a project, a project charter is created. Which of the following is typically included in a project charter?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project purpose and high-level scope
The project charter includes the project purpose, objectives, high-level scope, budget, schedule, assumptions, constraints, and the authority of the project manager.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Project purpose and high-level scope
Why this is correct
The project charter defines the high-level scope and purpose of the project.
- ✗
Detailed work breakdown structure
Why it's wrong here
A detailed WBS is developed during the planning phase, not initiating.
- ✗
Risk register with identified risks
Why it's wrong here
The risk register is created during risk management planning in the planning phase.
- ✗
Earned value metrics
Why it's wrong here
Earned value management is used during monitoring and controlling, not initiating.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.