Courseiva
Project Management ConceptshardMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

A project sponsor is reviewing a project that has a Net Present Value (NPV) of -$15,000. What should the sponsor recommend?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Reject the project because NPV is negative

A negative NPV indicates the project is not expected to be profitable; it should be rejected. Positive NPV is profitable. IRR and payback period are different metrics.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Proceed with the project because NPV is negative

    Why it's wrong here

    Negative NPV indicates loss.

  • Reject the project because NPV is negative

    Why this is correct

    Negative NPV means the project is not financially viable.

  • Proceed if the IRR is positive

    Why it's wrong here

    IRR may be positive, but NPV is the primary decision criterion.

  • Reject only if the payback period is too long

    Why it's wrong here

    Negative NPV is sufficient to reject.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.