Courseiva
Project Management Concepts →mediumMultiple Select

PK0-005 Project Management Concepts Practice Question

A project manager is closing out a customer relationship management implementation. The sponsor asks which activities are part of the closing phase rather than the execution phase. (Choose two.)

⚠ Common exam trap

Candidates often confuse ongoing execution rituals like stand-ups and schedule monitoring with closing activities, which focus on acceptance and administrative closure.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Obtaining formal acceptance of the final deliverables from the customer

Closing centers on confirming the customer accepts the deliverables and on administrative closure such as releasing resources and capturing lessons learned. Monitoring the critical path, negotiating future contracts, and running daily stand-ups are executing or initiating activities. Recognizing the boundary between producing deliverables and formally ending the project is the key distinction the sponsor is asking about.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Obtaining formal acceptance of the final deliverables from the customer

    Why this is correct

    Formal acceptance is a closing activity because it confirms the customer agrees the deliverables meet requirements and marks the point at which the product transitions to the customer. It is documented in the final acceptance record and often triggers final payment. Performing acceptance during execution would leave the project without a defined endpoint and could expose the seller to unresolved scope disputes.

  • ✗

    Monitoring the critical path and updating the schedule baseline weekly

    Why it's wrong here

    Schedule monitoring and baseline updates are execution and monitoring activities. During closing, the schedule is finalized and archived, not actively adjusted week by week. If a PM were still updating the schedule baseline during closing, it would indicate the project had not truly reached completion. This activity belongs to the executing and monitoring and controlling processes.

  • ✗

    Negotiating contract terms with the vendor for the next phase of work

    Why it's wrong here

    Negotiating future contract terms is a procurement activity associated with initiating or planning a new project or phase, not closing the current one. Closing focuses on settling existing agreements, verifying deliverables, and archiving records. Starting new negotiations during closing would blur the boundary between this project and the next and could confuse contract closure documentation.

  • ✓

    Releasing project resources and completing the lessons learned register

    Why this is correct

    Releasing team members and capturing lessons learned are classic closing activities. Resource release returns people to the pool or to other assignments, and lessons learned preserve knowledge for future projects. Both occur after deliverables are accepted and the final performance report is prepared. Doing them during execution would prematurely dismantle the team before remaining work and knowledge transfer are complete.

  • ✗

    Conducting daily stand-up meetings to remove team impediments

    Why it's wrong here

    Daily stand-ups are an execution cadence used to coordinate work and remove impediments while deliverables are being produced. In closing, the emphasis shifts to acceptance, transition, and administrative closure. Continuing stand-ups as a closing activity would suggest incomplete work, and it does not produce the acceptance records or archived documents that closing requires.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.