Courseiva
Project Life Cycle →hardMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project has a budget at completion (BAC) of $200,000. The actual cost (AC) is $80,000, earned value (EV) is $60,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the same cost efficiency?

⚠ Common exam trap

The trap is picking the wrong EAC formula — candidates often use EAC = AC + (BAC − EV) = 80,000 + 140,000 = $220,000 (option A) instead of the CPI-based formula, because they miss the phrase 'same cost efficiency' which mandates EAC = BAC / CPI.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

$266,667

The estimate at completion (EAC) when the project continues at the same cost efficiency is calculated as EAC = BAC / CPI. First compute CPI = EV / AC = 60,000 / 80,000 = 0.75. Then EAC = 200,000 / 0.75 = $266,667. This matches option D.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    $220,000

    Why it's wrong here

    $220,000 comes from AC + (BAC − EV), which assumes all remaining work is performed at the budgeted rate. That is the atypical-variance formula; the stem specifies the current cost efficiency continues, requiring BAC ÷ CPI instead.

  • ✗

    $250,000

    Why it's wrong here

    $250,000 applies EAC = BAC ÷ CPI only if CPI were 0.8, but CPI here is 60,000 ÷ 80,000 = 0.75, giving $266,667. The figure is tempting because dividing BAC by a rounded CPI is the standard formula when cost efficiency is expected to persist.

  • ✗

    $200,000

    Why it's wrong here

    $200,000 simply restates the budget at completion, ignoring the cost overrun already incurred. It would be the answer only if the question asked for EAC assuming remaining work proceeds at the original planned rate, i.e. EAC = AC + (BAC − EV).

  • ✓

    $266,667

    Why this is correct

    Using the cost performance index (CPI) to extrapolate future spending satisfies the stem's constraint that the project continues at the same cost efficiency. CPI is EV ÷ AC = 60,000 ÷ 80,000 = 0.75, so EAC = BAC ÷ CPI = 200,000 ÷ 0.75 = $266,667.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.