PK0-005 Project Life Cycle Practice Question
A project has a budget at completion (BAC) of $200,000. The actual cost (AC) is $80,000, earned value (EV) is $60,000, and planned value (PV) is $90,000. What is the estimate at completion (EAC) if the project will continue to perform at the same cost efficiency?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
$266,667
CPI = EV/AC = 60,000/80,000 = 0.75. EAC = BAC/CPI = 200,000/0.75 = $266,667.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
$220,000
Why it's wrong here
Incorrect calculation.
- ✗
$250,000
Why it's wrong here
Incorrect calculation.
- ✗
$200,000
Why it's wrong here
That is the BAC, not adjusted for cost performance.
- ✓
$266,667
Why this is correct
EAC = BAC/CPI = 200,000 / 0.75 = 266,667.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.