PK0-005 Practice Question: During project planning, the project manager…

During project planning, the project manager wants to ensure that all work is defined and that no work is omitted. Which tool or technique should be used?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Work breakdown structure (WBS)

The work breakdown structure is the primary tool for ensuring all work is identified and organized.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Responsibility assignment matrix

    Why it's wrong here

    The RAM assigns roles and responsibilities but does not define the work itself.

  • Gantt chart

    Why it's wrong here

    A Gantt chart displays schedule but does not define all work.

  • Network diagram

    Why it's wrong here

    A network diagram shows dependencies, not the complete definition of work.

  • Work breakdown structure (WBS)

    Why this is correct

    The WBS decomposes the project scope into manageable work packages and ensures all work is captured.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.