During project execution, a team discovers that the actual cost of work performed is $45,000, the planned value is $50,000, and the earned value is $40,000. Which statement is correct?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is behind schedule and over budget.

SV = EV - PV = $40,000 - $50,000 = -$10,000 (behind schedule). CV = EV - AC = $40,000 - $45,000 = -$5,000 (over budget).

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is behind schedule and under budget.

    Why it's wrong here

    CV is negative, so over budget.

  • The project is ahead of schedule and under budget.

    Why it's wrong here

    Both variances are negative, so opposite.

  • The project is behind schedule and over budget.

    Why this is correct

    SV negative = behind; CV negative = over budget.

  • The project is ahead of schedule and over budget.

    Why it's wrong here

    SV is negative, so behind schedule.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.