Courseiva
hardMultiple ChoiceObjective-mapped

PK0-005 Practice Question: During the planning phase, a team identifies a…

During the planning phase, a team identifies a risk that could cause a 10% increase in project cost if it occurs, with a 20% probability. What is the expected monetary value (EMV) of this risk?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

2% of project cost

EMV = Probability × Impact = 0.20 × 0.10 = 0.02, or 2% of the project cost.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 2% of project cost

    Why this is correct

    EMV = 0.20 × 0.10 = 0.02 = 2%.

  • 20% of project cost

    Why it's wrong here

    That is the probability percentage, not the EMV.

  • 10% of project cost

    Why it's wrong here

    That is the impact, not the EMV.

  • 30% of project cost

    Why it's wrong here

    Incorrect calculation.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.