PK0-005 Project Life Cycle Practice Question
A project team is entering the Storming stage of Tuckman's model. Which TWO characteristics are typical of this stage?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Disagreements and competition among team members arise.
Storming is characterized by conflict, competition, and challenges to authority as team members express differing opinions.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Team members are polite and avoid conflict.
Why it's wrong here
This is typical of Forming.
- ✓
Disagreements and competition among team members arise.
Why this is correct
Correct: Storming involves disagreements and competition.
- ✗
Team members work together efficiently and effectively.
Why it's wrong here
This is typical of Performing.
- ✗
Team members establish norms and ground rules.
Why it's wrong here
This is typical of Norming.
- ✓
Team members may challenge the project manager's authority.
Why this is correct
Correct: conflict and challenges to authority occur in Storming.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.