Courseiva
hardMultiple Choice

PK0-005 Practice Question: A project is in execution when a critical vendor…

A project is in execution when a critical vendor fails to deliver a key component. The project manager determines this will push the project past the deadline. After submitting a change request, what should the project manager do next?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Communicate the impact to stakeholders

After submitting a change request, the project manager should communicate the potential impact to stakeholders to manage expectations. Updating the risk register is important but not the immediate next step; fast tracking and requesting resources may be considered after approval.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Fast track the remaining tasks

    Why it's wrong here

    Fast tracking overlaps activities that were previously sequenced, which compresses schedule only where dependencies allow parallel work; it does nothing to recover the missing vendor component that is blocking progress. Fast tracking suits schedule compression when tasks can safely overlap.

  • ✓

    Communicate the impact to stakeholders

    Why this is correct

    Once the change request documents the schedule impact, stakeholders must be informed so they can decide on acceptance, re-planning or escalation. Communication satisfies the need to surface the vendor-driven delay before any baseline or timeline adjustment is approved.

  • ✗

    Request additional resources

    Why it's wrong here

    Additional resources address effort-driven duration, but the delay stems from a missing vendor component, so extra staff cannot install what has not arrived. Resource augmentation suits schedule compression when critical-path tasks are resource-constrained rather than blocked by undelivered materials.

  • ✗

    Update the risk register

    Why it's wrong here

    Updating the risk register records the issue and its attributes, but the change request has already been submitted, so the next step is to route that request through the integrated change control process for approval. Risk register updates suit ongoing risk identification, not post-submission change handling.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.