Courseiva
Tools and DocumentationhardMultiple SelectObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project is experiencing cost overruns. The project manager wants to calculate key earned value metrics. Which THREE metrics are needed to compute the cost performance index (CPI) and schedule performance index (SPI)? (Select three.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Actual cost (AC)

CPI = EV/AC, SPI = EV/PV. So EV, AC, and PV are required.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Budget at completion (BAC)

    Why it's wrong here

    BAC is not needed for CPI or SPI directly.

  • Estimate at completion (EAC)

    Why it's wrong here

    EAC is derived from CPI, not used to compute it.

  • Actual cost (AC)

    Why this is correct

    Correct. AC is used in CPI.

  • Planned value (PV)

    Why this is correct

    Correct. PV is used in SPI.

  • Earned value (EV)

    Why this is correct

    Correct. EV is used in both CPI and SPI.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.