A project manager is creating a document that identifies all project stakeholders and their influence, interest, and impact on the project. Which document is being created?

⚠ Common exam trap

CompTIA often tests the distinction between the stakeholder register (which lists stakeholders and their attributes) and the communication plan (which details the methods and frequency of engagement), tempting candidates to confuse the two.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Stakeholder register

The stakeholder register is the document that captures all stakeholders along with their influence, interest, and impact on the project. This register serves as the foundational input for stakeholder analysis and engagement planning, directly matching the description in the question.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Stakeholder register

    Why this is correct

    The stakeholder register is the document that records identified stakeholders alongside their interest, influence and impact, which is exactly the analysis artefact described. It satisfies the requirement to capture influence, interest and impact in one place.

  • ✗

    Project scope statement

    Why it's wrong here

    The project scope statement defines deliverables, boundaries and acceptance criteria; it does not catalogue stakeholders or assess their influence and interest. A stakeholder register is the correct artefact when the goal is identifying stakeholders and rating their impact.

  • ✗

    Communication plan

    Why it's wrong here

    A communication plan defines what information each stakeholder receives, when, and through which channel; it presumes stakeholders are already identified. It is tempting because it references stakeholders and their needs, but the stem requires the artefact that first records influence, interest and impact — the stakeholder register.

  • ✗

    Risk register

    Why it's wrong here

    A risk register catalogues identified risks, their probability, impact and owners — not stakeholders. It is tempting because impact and influence are also risk attributes, and the register is a core project document, but the stem asks for a stakeholder identification artefact, which is the stakeholder register.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.