A project manager uses a control chart to monitor the number of defects found during testing. The chart shows one data point above the upper control limit (UCL). What action should the project manager take?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Investigate the cause of the outlier

A point above the UCL indicates a special cause variation, which requires investigation to identify and address the root cause.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ignore it, as it is within expected variation

    Why it's wrong here

    Above UCL is not expected; it's special cause.

  • Recalculate the control limits

    Why it's wrong here

    Control limits are based on historical data; don't recalculate for one point.

  • Reduce the sample size

    Why it's wrong here

    Sample size not relevant to this action.

  • Investigate the cause of the outlier

    Why this is correct

    Special cause needs investigation.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.