Question 253 of 500
Project Management ConceptshardMultiple SelectObjective-mapped

Quick Answer

The answer is the scope baseline, cost baseline, and schedule baseline, as these three approved baselines are the core components of a project management plan. In project management, the plan serves as the master document that dictates how the project will be executed, monitored, and controlled, and each baseline represents the approved version of a key constraint—scope, cost, and schedule—against which actual performance is measured. On the CompTIA Project+ PK0-005 exam, this concept tests your understanding that the project management plan is not just a schedule or budget, but an integrated set of baselines and subsidiary plans; a common trap is confusing a single deliverable, like the project charter or a risk register, with these foundational baselines. To remember, think of the three-legged stool of project control: scope, schedule, and cost—without all three, the plan cannot stand.

PK0-005 Project Management Concepts Practice Question

This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Which THREE of the following are typically included in a project management plan? (Select THREE.)

Question 1hardmulti select
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Cost baseline

The project management plan is the formal, approved document that defines how the project is executed, monitored, and controlled. The cost baseline, schedule baseline, and scope baseline are all fundamental components of the project management plan, as they represent the approved versions of the project budget, schedule, and scope against which performance is measured.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Issue log

    Why it's wrong here

    The issue log is a project document used to track issues.

  • Cost baseline

    Why this is correct

    The cost baseline is an approved time-phased budget.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Schedule baseline

    Why this is correct

    The schedule baseline is an approved version of the project schedule.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Scope baseline

    Why this is correct

    The scope baseline includes the scope statement, WBS, and WBS dictionary.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Stakeholder register

    Why it's wrong here

    The stakeholder register is a project document, not a component of the project management plan.

Common exam traps

Common exam trap: answer the scenario, not the keyword

CompTIA often tests the distinction between 'components of the project management plan' (baselines and subsidiary plans) and 'project documents' (logs, registers, and other artifacts), leading candidates to mistakenly select items like the issue log or stakeholder register as part of the plan.

Detailed technical explanation

How to think about this question

The project management plan is composed of subsidiary plans (e.g., scope, schedule, cost, risk, quality) and baselines (scope, schedule, cost). Baselines are frozen versions of the scope, schedule, and cost that are used for earned value management (EVM) and variance analysis; any change to a baseline requires a formal change request and approval through the integrated change control process. In practice, the cost baseline is typically the time-phased budget, while the schedule baseline is the approved project schedule, and the scope baseline includes the scope statement, WBS, and WBS dictionary.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the PK0-005 exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related PK0-005 practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free PK0-005 practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this PK0-005 question test?

Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Cost baseline — The project management plan is the formal, approved document that defines how the project is executed, monitored, and controlled. The cost baseline, schedule baseline, and scope baseline are all fundamental components of the project management plan, as they represent the approved versions of the project budget, schedule, and scope against which performance is measured.

What should I do if I get this PK0-005 question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.