Project Management Concepts →mediumMultiple Choice

PK0-005 Project Management Concepts Practice Question

A company is implementing a new HR system. The project manager wants to ensure that all requirements are gathered up front and the scope is fixed. Which project management methodology is MOST appropriate?

⚠ Common exam trap

PK0-005 often tests the misconception that Agile is always the 'modern' or 'best' choice — candidates must match methodology to the stated constraints (fixed scope, up-front requirements) rather than defaulting to Agile.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Predictive (waterfall)

A predictive (waterfall) methodology is appropriate when requirements are well understood up front, scope is fixed, and changes are expected to be minimal — exactly the scenario described. Waterfall's sequential phases (requirements, design, build, test, deploy) and formal change control align with the project manager's goal of gathering all requirements up front and locking scope. This is the classic choice for stable, compliance-heavy, or contract-driven projects like HR system implementations with fixed deliverables.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Predictive (waterfall)

    Why this is correct

    Predictive methodology fixes scope, schedule and cost baselines early, with requirements fully elicited before build begins. That matches the stated constraint of gathering all requirements up front and locking scope, whereas adaptive approaches deliberately welcome late change.

  • ✗

    Hybrid

    Why it's wrong here

    Hybrid blends predictive and adaptive delivery, so parts of the work remain iterative and scope is not fully fixed up front. It is tempting because it suits mixed portfolios, but the stem requires all requirements gathered and scope frozen before build, which pure waterfall delivers.

  • ✗

    Kanban

    Why it's wrong here

    Kanban manages continuous flow with no fixed scope or up-front requirements phase, so it cannot satisfy the stem's demand for gathered requirements and locked scope. It is tempting because it visualises work well for operational or support teams, but predictive waterfall is correct when scope is fixed before delivery.

  • ✗

    Agile

    Why it's wrong here

    Agile welcomes changing requirements throughout delivery, directly contradicting the stem's fixed-scope, up-front-gathering requirement. It is tempting because it handles uncertainty well on evolving products, but waterfall is correct when scope is defined and baselined before execution begins.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.