Courseiva
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

A company is implementing a new HR system. The project manager wants to ensure that all requirements are gathered up front and the scope is fixed. Which project management methodology is MOST appropriate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Predictive (waterfall)

Predictive/waterfall works well when requirements are clear and scope is fixed from the start. Agile is for changing requirements; hybrid is a mix; Kanban is for flow.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Predictive (waterfall)

    Why this is correct

    Correct. Predictive is best for fixed scope and stable requirements.

  • Hybrid

    Why it's wrong here

    Hybrid is mixed, but not needed if requirements are stable.

  • Kanban

    Why it's wrong here

    Kanban is an agile method for continuous delivery, not fixed scope.

  • Agile

    Why it's wrong here

    Agile expects changing requirements, not fixed scope.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.