PK0-005 Project Management Concepts Practice Question
A company is implementing a new HR system. The project manager wants to ensure that all requirements are gathered up front and the scope is fixed. Which project management methodology is MOST appropriate?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Predictive (waterfall)
Predictive/waterfall works well when requirements are clear and scope is fixed from the start. Agile is for changing requirements; hybrid is a mix; Kanban is for flow.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Predictive (waterfall)
Why this is correct
Correct. Predictive is best for fixed scope and stable requirements.
- ✗
Hybrid
Why it's wrong here
Hybrid is mixed, but not needed if requirements are stable.
- ✗
Kanban
Why it's wrong here
Kanban is an agile method for continuous delivery, not fixed scope.
- ✗
Agile
Why it's wrong here
Agile expects changing requirements, not fixed scope.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.