Courseiva
Project Life CyclehardMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

During project execution, a team member proposes a change that will affect the scope baseline. What is the first step the project manager should take?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request

The first step in change control is to submit a change request, which then undergoes impact analysis.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Inform the change control board

    Why it's wrong here

    The CCB reviews the change request after impact analysis.

  • Submit a change request

    Why this is correct

    A formal change request initiates the change control process.

  • Update the project management plan

    Why it's wrong here

    Updates occur only after approval.

  • Deny the change

    Why it's wrong here

    Changes should be formally evaluated, not immediately denied.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.