Courseiva
mediumMultiple SelectObjective-mapped

PK0-005 Practice Question: A project manager is creating a project charter

A project manager is creating a project charter. Which TWO components are typically included in a project charter? (Choose two.)

⚠ Common exam trap

The PK0-005 exam often tests the distinction between high-level and detailed components, so the trap here is that candidates confuse the project charter with the project management plan, selecting detailed items like budget or communication plan that belong to later phases.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Business need

The project charter is a high-level document that authorizes the project and provides the project manager with the authority to apply organizational resources. The business need (option B) is a core component because it justifies why the project is being undertaken, linking it to organizational strategy. High-level risks (option E) are also included to identify potential uncertainties at the outset, without requiring detailed analysis, which aligns with the charter's purpose of providing a broad overview.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Detailed budget

    Why it's wrong here

    Detailed budget is developed later in planning.

  • Business need

    Why this is correct

    Business need justifies the project and is included in the charter.

  • Task assignments

    Why it's wrong here

    Task assignments are defined in the project plan.

  • Communication plan

    Why it's wrong here

    Communication plan is a separate document.

  • High-level risks

    Why this is correct

    High-level risks are identified in the charter.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.