Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: During the monitoring and controlling phase, a…

During the monitoring and controlling phase, a project manager receives a status report indicating the CPI is 0.8 and SPI is 0.9. Which action should the project manager take next?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the variances and determine corrective actions

A CPI of 0.8 means the project is over budget, and an SPI of 0.9 means it is behind schedule. The project manager should analyze the root cause of these variances and consider corrective actions.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Celebrate because both indices are above 0.7

    Why it's wrong here

    Indices below 1 indicate unfavorable performance; celebration is not warranted.

  • Update the project management plan to reflect the variances

    Why it's wrong here

    The plan should be updated only after decisions are made; analysis comes first.

  • Analyze the variances and determine corrective actions

    Why this is correct

    Variance analysis is the first step to understand and address the issues.

  • Immediately request more budget from the sponsor

    Why it's wrong here

    Analysis should precede any budget requests; the cause of over-budget must be understood.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.