A project manager is analyzing stakeholders and categorizes a key executive who has high power and high interest. According to the power/interest grid, how should the project manager engage this stakeholder?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Manage closely

Stakeholders with high power and high interest should be managed closely, as they are key players.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Keep informed

    Why it's wrong here

    Keep informed is for low power, high interest.

  • Monitor

    Why it's wrong here

    Monitoring is for low power and low interest.

  • Manage closely

    Why this is correct

    High power and high interest stakeholders require active management.

  • Keep satisfied

    Why it's wrong here

    Keep satisfied is for high power, low interest.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.