Courseiva
Project Life Cycle →mediumMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project manager is analyzing stakeholders and categorizes a key executive who has high power and high interest. According to the power/interest grid, how should the project manager engage this stakeholder?

⚠ Common exam trap

PK0-005 often tests the power/interest grid by swapping the strategies for the high-power quadrants — candidates confuse 'Manage Closely' (high power + high interest) with 'Keep Satisfied' (high power + low interest).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Manage closely

In the power/interest grid, a stakeholder with both high power and high interest falls into the 'Manage Closely' quadrant. These stakeholders have the authority to influence project decisions and are deeply invested in outcomes, so they require active, ongoing engagement and collaboration. The PM should involve them in decision-making and keep a close working relationship.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Keep informed

    Why it's wrong here

    High power and high interest demands manage closely, with active involvement in decisions. Keep informed suits low power and low interest stakeholders who need only status updates. Here the executive's authority and stake require engagement throughout, not one-way communication.

  • ✗

    Monitor

    Why it's wrong here

    Monitor applies to low power and low interest stakeholders, requiring minimal effort. A high-power, high-interest executive needs active, ongoing engagement and involvement in decisions, so monitoring would leave a critical stakeholder uninformed and unsupportive of the project.

  • ✓

    Manage closely

    Why this is correct

    High power combined with high interest places this executive in the quadrant demanding the closest engagement, so the project manager must manage closely. This satisfies the grid's requirement for regular, detailed communication and active involvement, ensuring their significant authority and stake are addressed throughout the project.

  • ✗

    Keep satisfied

    Why it's wrong here

    Keep satisfied targets high power but low interest stakeholders, who need enough communication to remain supportive without overloading them. This executive also has high interest, so the correct approach is manage closely, involving them directly in decisions and delivery.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.