Which document formally authorizes the project and assigns the project manager?
Trap 1: Business case
A business case justifies the project’s existence by outlining costs, benefits, and risks, but it does not formally authorise work or assign a project manager. The correct document—the project charter—grants that formal authority and names the project manager. The business case is tempting because it precedes the charter in the project lifecycle and often contains the initial recommendation, yet it lacks the binding approval signature that triggers resource allocation.
Trap 2: Project scope statement
The project scope statement defines deliverables, boundaries, and acceptance criteria, but it does not contain the formal approval to commit organisational resources or assign the project manager. It is tempting because it is a foundational document created early in planning, yet it lacks the authorisation signature that a project charter provides. In a scenario where the question asked which document defines the work to be done, the scope statement would be correct.
Trap 3: Project plan
A project plan describes scope, schedule and execution approach; it grants no authority. The project charter is the document that formally authorises the project and names the project manager. The plan is tempting because it is the central artefact the manager owns and maintains throughout delivery, but it is created after authorisation.
- A
Business case
Why it fails: A business case justifies the project’s existence by outlining costs, benefits, and risks, but it does not formally authorise work or assign a project manager. The correct document—the project charter—grants that formal authority and names the project manager. The business case is tempting because it precedes the charter in the project lifecycle and often contains the initial recommendation, yet it lacks the binding approval signature that triggers resource allocation.
- B
Project charter
The project charter is the document that formally authorises the project and names the project manager, granting them authority to apply organisational resources. It satisfies the stem's requirement for both authorisation and assignment in a single artefact.
- C
Project scope statement
Why it fails: The project scope statement defines deliverables, boundaries, and acceptance criteria, but it does not contain the formal approval to commit organisational resources or assign the project manager. It is tempting because it is a foundational document created early in planning, yet it lacks the authorisation signature that a project charter provides. In a scenario where the question asked which document defines the work to be done, the scope statement would be correct.
- D
Project plan
Why it fails: A project plan describes scope, schedule and execution approach; it grants no authority. The project charter is the document that formally authorises the project and names the project manager. The plan is tempting because it is the central artefact the manager owns and maintains throughout delivery, but it is created after authorisation.