Domain 3 of CompTIA Project+ PK0-005 covers the project life cycle: initiating, planning, executing, monitoring/controlling, and closing. Expect situational questions on Tuckman's team stages, change control steps, risk response strategies, and phase gates. Questions test judgment about sequencing, authority, and documentation rather than tool-specific commands.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Editorial oversight:Johnson Ajibi· MSc IT Security, IEEE Senior Member
20 questionsDomain: Project Life Cycle

What the exam tests

What to know about Project Life Cycle

Map team behavior to the correct Tuckman stage, follow change control in order (analyze impact, get CCB approval, then update plans and communicate), and pick valid risk responses. The key is sequencing: never act on a change before impact analysis and approval.

Tuckman's stages: forming, storming, norming, performing, and adjourning team behavior

Change control workflow: request, impact analysis, CCB decision, implementation, communication

Risk response strategies: avoid, transfer, mitigate, accept, escalate, and exploit

Phase gate and life cycle types: predictive, iterative, incremental, agile, hybrid delivery

Watch out for

Common Project Life Cycle exam traps

  • ▸Confusing storming with forming: conflict and authority challenges signal storming, not the polite orientation of forming.
  • ▸Jumping to implement an approved change before updating the change log, baseline, and stakeholders.
  • ▸Treating 'accept' as doing nothing; acceptance may require a contingency reserve or documented acknowledgment.

Practice set

Project Life Cycle questions

20 questions · select your answer, then reveal the explanation

Which document formally authorizes the project and assigns the project manager?

During the executing phase, a vendor delivers a product that does not meet the specifications outlined in the SOW. Which document should the project manager reference first to address this issue?

Which of the following is a key input to the change control process when a change request is submitted?

Which document is used to formally accept the project deliverables and signify project closure?

A project manager is reviewing the project schedule. Activity A has an early start (ES) of day 1 and an early finish (EF) of day 5. Activity B has an ES of day 6 and an EF of day 10. Activity C has a duration of 2 days and depends on both A and B. What is the total float of Activity B if the project must be completed by day 12?

A project manager is analyzing the network diagram and identifies that Activity X has a late start (LS) of day 10 and an early start (ES) of day 8. Which TWO statements are true about Activity X? (Select two.)

During project execution, a stakeholder requests a change to the project scope. What is the first step the project manager should take?

Which TWO of the following are outputs of the monitoring and controlling process group? (Select two.)

A project has the following activities and dependencies: A (5 days), B (3 days, after A), C (4 days, after A), D (2 days, after B), E (6 days, after C), F (1 day, after D and E). What is the total float of activity C?

During the planning phase, a project team is selecting risk response strategies for identified risks. Which THREE are valid risk response strategies?

Question 11mediummultiple choice
Read the full Project Life Cycle explanation →

A project team is in the storming stage of Tuckman's model. Which behavior is most likely observed?

Which contract type places the most cost risk on the seller?

A project has three activities on the critical path: A (5 days), B (10 days), C (5 days). Activity D (8 days) has a total float of 3 days. If activity B is delayed by 2 days, what is the new project duration?

A project manager is identifying response strategies for a risk that could impact the project schedule. Which TWO options are risk response strategies? (Select TWO.)

A project has a cost performance index (CPI) of 1.2 and a schedule performance index (SPI) of 0.9. Which of the following is true?

A project manager is updating the risk register and plans to respond to a high-priority risk. Which THREE are examples of proactive risk response strategies?

A project manager is creating a project schedule. Which THREE items are typically included in a schedule baseline?

A project team is in the Performing stage of Tuckman's model. Which TWO behaviors are characteristic of this stage?

A project manager is identifying stakeholders for a new product launch. She uses a power/interest grid to categorize stakeholders. For which ONE quadrant should the project manager apply the strategy of 'Manage Closely'?

During project executing, the team is developing a communication plan. Which THREE factors should the project manager consider when determining the communication needs of stakeholders?

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Project Life Cycle sessions

Start a Project Life Cycle only practice session

Every question in these sessions is drawn from the Project Life Cycle domain — nothing else.

Related practice questions

Related PK0-005 topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the PK0-005 exam test about Project Life Cycle?
Map team behavior to the correct Tuckman stage, follow change control in order (analyze impact, get CCB approval, then update plans and communicate), and pick valid risk responses. The key is sequencing: never act on a change before impact analysis and approval.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Project Life Cycle questions in a focused session?
Yes — the session launcher on this page draws every question from the Project Life Cycle domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other PK0-005 topics?
Use the topic links above to move to related areas, or go back to the PK0-005 question bank to see all topics.