PK0-005 · topic practice

Project Life Cycle practice questions

Practise CompTIA Project+ PK0-005 Project Life Cycle practice questions — original exam-style scenarios with answer choices, explanations, and analysis of common mistakes.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Reviewed byJohnson Ajibi· MSc IT Security
20 questionsDomain: Project Life Cycle

What the exam tests

What to know about Project Life Cycle

Project Life Cycle questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Watch out for

Common Project Life Cycle exam traps

  • Answering from memory before reading the full scenario.
  • Missing a constraint such as cost, availability, security, scope or command context.
  • Choosing a broad answer when the question asks for the most specific fix.
  • Ignoring why the wrong options are tempting.

Practice set

Project Life Cycle questions

20 questions · select your answer, then reveal the explanation

During which project phase is the project charter typically created and approved?

A project manager is developing a network diagram and needs to represent an activity that can start only after its predecessor has finished. Which dependency type does this describe?

A project manager is using the power/interest grid to classify stakeholders. Which group should be managed most closely because they have high power and high interest?

A project has an Earned Value (EV) of $50,000, Actual Cost (AC) of $60,000, and Planned Value (PV) of $55,000. What is the Cost Performance Index (CPI), and what does it indicate?

Which risk response strategy involves taking action to reduce the probability or impact of a risk?

A project manager is estimating the cost of a new software development project. She uses the actual cost of a similar past project and adjusts for differences in size and complexity. Which estimation technique is she using?

During which stage of Tuckman's team development model do team members begin to resolve conflicts and establish norms?

A project manager is calculating the Expected Monetary Value (EMV) for a risk event. The probability of the risk occurring is 20%, and the impact if it occurs is $50,000. What is the EMV?

Which document formally authorizes the project and assigns the project manager?

Question 10mediummultiple choice
Read the full Project Life Cycle explanation →

A project manager is creating a Work Breakdown Structure (WBS). Which technique is used to break down deliverables into smaller, manageable components?

In a project, the critical path has a duration of 100 days. Activity X on the critical path has a duration of 10 days and can be crashed to 7 days at an additional cost of $3,000. What is the crash cost per day for Activity X?

Question 12mediummultiple choice
Read the full Project Life Cycle explanation →

A vendor is hired to provide a service with a fixed price of $100,000, regardless of actual costs incurred. Which contract type is this?

A project team is entering the Storming stage of Tuckman's model. Which TWO characteristics are typical of this stage?

A project manager is planning risk responses for identified risks. Which THREE are valid risk response strategies?

During project closing, which TWO activities are typically performed?

A project manager is developing the project charter. Which of the following should be included as a key element of the project charter?

Question 17mediummultiple choice
Read the full Project Life Cycle explanation →

During project planning, the project manager creates a network diagram. Activity A has a duration of 5 days, Activity B has a duration of 3 days, and Activity C has a duration of 4 days. Activities A and B can start immediately. Activity C can start only after Activity A is complete. Activity B has no dependency on others. What is the duration of the critical path?

A project is in the monitoring and controlling phase. The project manager is reviewing the earned value metrics: EV = $50,000, PV = $60,000, AC = $55,000. Which of the following statements is correct?

Question 19mediummultiple choice
Read the full Project Life Cycle explanation →

A project team is experiencing conflicts and power struggles among members. According to Tuckman's stages of group development, which stage is the team likely in?

Question 20mediummultiple choice
Read the full Project Life Cycle explanation →

A project manager is evaluating risk responses. For a risk with high probability and high impact, which risk response strategy is most appropriate to eliminate the threat?

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Project Life Cycle sessions

Start a Project Life Cycle only practice session

Every question in these sessions is drawn from the Project Life Cycle domain — nothing else.

Related practice questions

Related PK0-005 topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the PK0-005 exam test about Project Life Cycle?
Project Life Cycle questions test whether you can apply the concept in context, not just recognise a definition.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Project Life Cycle questions in a focused session?
Yes — the session launcher on this page draws every question from the Project Life Cycle domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other PK0-005 topics?
Use the topic links above to move to related areas, or go back to the PK0-005 question bank to see all topics.
Are these real exam questions or dumps?
These are original practice questions written to test the same concepts the PK0-005 exam covers. They are not copied from any real exam or dump site.