Project Life Cycle →easyMultiple Choice

PK0-005 Project Life Cycle Practice Question

A project manager is creating a document that formally authorizes the project and assigns the project manager. This document includes the business case, high-level scope, and budget constraints. What is this document called?

⚠ Common exam trap

PK0-005 often tests the distinction between the charter (authorizes, names PM) and the business case (justifies) or scope statement (details deliverables), catching candidates who pick the document that 'sounds most strategic.'

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project charter

The project charter is the document that formally authorizes the project, names the project manager, and captures the business case, high-level scope, and budget constraints. It is issued by the sponsor (or PMO) and gives the PM authority to apply organizational resources. This matches the question's description exactly.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Project scope statement

    Why it's wrong here

    The scope statement details deliverables, acceptance criteria and exclusions, but it does not formally authorise the project or name the project manager. It is tempting because scope is included in the charter, and it would be correct when elaborating the approved scope after the charter has been signed.

  • ✗

    Project management plan

    Why it's wrong here

    The project management plan describes how the project will be executed, monitored and closed; it is produced after authorisation, not to grant it. It is tempting because it also contains scope and budget baselines, and would be correct when documenting the approved approach for managing an already-authorised project.

  • ✗

    Business case

    Why it's wrong here

    The business case justifies the investment and compares options, but it neither authorises the project nor assigns the project manager. It is tempting because it is an input to the charter, and it would be the correct deliverable when an organisation needs to decide whether a proposed project is worth funding.

  • ✓

    Project charter

    Why this is correct

    The project charter formally authorises the project and names the project manager. It contains the business case, high-level scope and budget constraints, exactly the elements described, distinguishing it from subsidiary documents such as the scope statement.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.