Which project management process group involves obtaining formal acceptance of the project deliverables and archiving project documents?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Closing

Closing includes formal acceptance, lessons learned, and archiving project documents.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Executing

    Why it's wrong here

    Executing covers carrying out the work defined in the project management plan, not formal deliverable acceptance or document archiving. It tempts because acceptance often occurs alongside delivery activities. Closing is the process group that obtains formal acceptance and archives project documents and lessons learned.

  • ✓

    Closing

    Why this is correct

    Closing is the process group where the project manager obtains formal sign-off that deliverables meet acceptance criteria, then archives project documentation and releases resources. It directly satisfies the stem's requirement for formal acceptance and document archiving, which no other process group performs.

  • ✗

    Planning

    Why it's wrong here

    Planning produces baselines and the project plan; it never obtains formal acceptance or archives records. Acceptance and archiving occur in Closing, where the product is handed over and documentation is retained. Planning is tempting because it defines how acceptance criteria will be met, but it does not execute the acceptance itself.

  • ✗

    Initiating

    Why it's wrong here

    Initiating authorises the project and defines its high-level scope and stakeholders; it neither obtains deliverable acceptance nor archives records. It tempts because acceptance formally ends the effort, but that happens at the close. Closing handles formal acceptance, final reporting and archiving of project documents.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.