Courseiva
easyMultiple Choice

PK0-005 Practice Question: A project team is conducting a lessons learned…

A project team is conducting a lessons learned session. In which project life cycle phase does this typically occur?

⚠ Common exam trap

PK0-005 often tests the distinction between when lessons learned are captured versus when they are applied, causing candidates to confuse the Closure phase with Planning or Execution.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Closure

Lessons learned sessions are typically conducted during the Closure phase of a project life cycle. This is when the project is formally completed, and the team reflects on what went well, what didn't, and how future projects can be improved. The Closure phase includes finalizing all activities, archiving documents, releasing resources, and capturing knowledge for organizational process assets. Conducting lessons learned at closure ensures that the entire project experience is fresh and comprehensive, allowing for accurate documentation of successes and failures.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Planning

    Why it's wrong here

    Planning precedes delivery, so there is no executed performance, variance or stakeholder feedback to analyse. It is tempting because prior lessons shape the plan, but the session examining this project's own results belongs to closure.

  • ✓

    Closure

    Why this is correct

    Lessons learned sessions occur during Closure, after deliverables are accepted and the product is transitioned. This timing lets the team capture what worked and what did not across the whole life cycle, feeding organisational process assets for future projects while the experience is still fresh.

  • ✗

    Execution

    Why it's wrong here

    Execution is where work is delivered, so outcomes and issues are still unfolding and cannot be assessed conclusively. It is tempting because interim reviews capture in-flight adjustments, yet the formal lessons learned session is held once the project closes.

  • ✗

    Initiation

    Why it's wrong here

    Initiation covers authorising the project and defining its initial scope, so no delivery experience exists yet to review. It is tempting because lessons from prior projects inform the charter, but the session reviewing this project's own performance occurs at closure.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.