easyMultiple ChoiceObjective-mapped
PK0-005 Practice Question: A project team is conducting a lessons learned…
A project team is conducting a lessons learned session. In which project life cycle phase does this typically occur?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Closure
Lessons learned are conducted during project closure to capture knowledge for future projects. Option A is incorrect because planning focuses on detailed planning. Option C is incorrect because execution focuses on performing the work. Option D is incorrect because initiation focuses on authorizing the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Planning
Why it's wrong here
Planning phase.
- ✓
Closure
Why this is correct
Lessons learned captured at closure.
- ✗
Execution
Why it's wrong here
Execution phase.
- ✗
Initiation
Why it's wrong here
Authorization phase.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.