Courseiva
hardMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project manager is using a schedule compression…

A project manager is using a schedule compression technique that adds resources to critical path activities to shorten the project duration. Which technique is being used?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Crashing

Crashing adds resources to critical path tasks, typically increasing cost.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Fast-tracking

    Why it's wrong here

    Fast-tracking overlaps sequential activities, increasing risk.

  • Monte Carlo simulation

    Why it's wrong here

    Monte Carlo simulates outcomes, not compression.

  • Crashing

    Why this is correct

    Correct definition.

  • Resource leveling

    Why it's wrong here

    Resource leveling adjusts schedule to avoid over-allocation.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.