hardMultiple ChoiceObjective-mapped
PK0-005 Practice Question: A project manager is using a schedule compression…
A project manager is using a schedule compression technique that adds resources to critical path activities to shorten the project duration. Which technique is being used?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Crashing
Crashing adds resources to critical path tasks, typically increasing cost.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Fast-tracking
Why it's wrong here
Fast-tracking overlaps sequential activities, increasing risk.
- ✗
Monte Carlo simulation
Why it's wrong here
Monte Carlo simulates outcomes, not compression.
- ✓
Crashing
Why this is correct
Correct definition.
- ✗
Resource leveling
Why it's wrong here
Resource leveling adjusts schedule to avoid over-allocation.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.