PK0-005 Project Management Concepts Practice Question
During project execution, the project manager notices that the team is adding extra features that were not requested by the customer. This is an example of which common project constraint issue?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Gold plating
Gold plating is when the project team adds extra features beyond the requirements without authorization, increasing scope without corresponding value.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Gold plating
Why this is correct
Gold plating is adding extra features beyond requirements.
- ✗
Quality assurance
Why it's wrong here
Quality assurance is about meeting quality standards.
- ✗
Triple constraint
Why it's wrong here
Triple constraint refers to scope, cost, and schedule.
- ✗
Scope creep
Why it's wrong here
Scope creep is uncontrolled changes to the scope, but gold plating is adding extra features.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.