During project execution, the project manager notices that the team is adding extra features that were not requested by the customer. This is an example of which common project constraint issue?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Gold plating

Gold plating is when the project team adds extra features beyond the requirements without authorization, increasing scope without corresponding value.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Gold plating

    Why this is correct

    Gold plating is adding extra features beyond requirements.

  • Quality assurance

    Why it's wrong here

    Quality assurance is about meeting quality standards.

  • Triple constraint

    Why it's wrong here

    Triple constraint refers to scope, cost, and schedule.

  • Scope creep

    Why it's wrong here

    Scope creep is uncontrolled changes to the scope, but gold plating is adding extra features.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.