Courseiva
Tools and DocumentationhardMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project has a budget at completion (BAC) of $500,000. After 3 months, the earned value (EV) is $200,000, the actual cost (AC) is $250,000, and the planned value (PV) is $180,000. What is the cost performance index (CPI) and what does it indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

CPI = 0.8, over budget

CPI = EV/AC = 200,000/250,000 = 0.8. A CPI less than 1 indicates the project is over budget.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • CPI = 0.8, over budget

    Why this is correct

    Correct. CPI of 0.8 means for every dollar spent, only $0.80 of work is earned.

  • CPI = 1.11, under budget

    Why it's wrong here

    1.11 would be AC/EV (250k/200k), not the correct formula.

  • CPI = 0.8, behind schedule

    Why it's wrong here

    CPI measures cost efficiency, not schedule. Schedule performance is measured by SPI.

  • CPI = 1.25, over budget

    Why it's wrong here

    1.25 is EV/PV (200k/180k), which is SPI, not CPI.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.