Courseiva
Tools and Documentation →hardMultiple Choice

PK0-005 Tools and Documentation Practice Question

A project has a budget at completion (BAC) of $500,000. After 3 months, the earned value (EV) is $200,000, the actual cost (AC) is $250,000, and the planned value (PV) is $180,000. What is the cost performance index (CPI) and what does it indicate?

⚠ Common exam trap

PK0-005 often tests the confusion between CPI (cost) and SPI (schedule), causing candidates to interpret a low CPI as a schedule delay rather than a cost overrun.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

CPI = 0.8, over budget

CPI is calculated as EV / AC = $200,000 / $250,000 = 0.8. A CPI less than 1.0 indicates that the project is over budget, because the value earned is less than the cost incurred. Therefore, CPI = 0.8, over budget is correct.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    CPI = 0.8, over budget

    Why this is correct

    CPI is calculated as EV ÷ AC, giving $200,000 ÷ $250,000 = 0.8. A value below 1.0 means each dollar spent delivers only 80 cents of earned value, so the project is over budget. This directly satisfies the stem's request for both the CPI figure and its cost implication.

  • ✗

    CPI = 1.11, under budget

    Why it's wrong here

    CPI is EV divided by AC, giving 200,000/250,000 = 0.80, indicating cost overrun. Dividing EV by PV yields the schedule index, and 1.11 would only arise from inverting the ratio, so the stated figure and its under-budget conclusion are both wrong.

  • ✗

    CPI = 0.8, behind schedule

    Why it's wrong here

    CPI is EV divided by AC, giving 200,000/250,000 = 0.8, yet 0.8 indicates cost overrun, not schedule slippage; schedule status comes from SPI (EV/PV = 1.11). It tempts because CPI below 1.0 is often loosely described as 'behind', conflating cost and schedule indices.

  • ✗

    CPI = 1.25, over budget

    Why it's wrong here

    CPI is EV/AC = 200,000/250,000 = 0.8, not 1.25; 1.25 is AC/EV inverted, and a CPI below 1.0 signals over budget, not the stated value. It tempts because inverting the ratio produces a familiar-looking number.

About these practice questions

One of 954 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.