Which document describes the roles and responsibilities in a project using the categories Responsible, Accountable, Consulted, and Informed?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

RACI matrix

A RACI matrix defines roles and responsibilities for each task or deliverable using the four categories.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Work breakdown structure

    Why it's wrong here

    The WBS breaks down work, but does not assign roles.

  • Communication plan

    Why it's wrong here

    The communication plan outlines how and when information is shared, not roles.

  • RACI matrix

    Why this is correct

    Correct. A RACI matrix defines Responsible, Accountable, Consulted, Informed.

  • Stakeholder register

    Why it's wrong here

    The stakeholder register lists stakeholders and their interest, not responsibilities.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.