PK0-005 Tools and Documentation Practice Question
Which document describes the roles and responsibilities in a project using the categories Responsible, Accountable, Consulted, and Informed?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
RACI matrix
A RACI matrix defines roles and responsibilities for each task or deliverable using the four categories.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Work breakdown structure
Why it's wrong here
The WBS breaks down work, but does not assign roles.
- ✗
Communication plan
Why it's wrong here
The communication plan outlines how and when information is shared, not roles.
- ✓
RACI matrix
Why this is correct
Correct. A RACI matrix defines Responsible, Accountable, Consulted, Informed.
- ✗
Stakeholder register
Why it's wrong here
The stakeholder register lists stakeholders and their interest, not responsibilities.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.