PK0-005 Project Life Cycle Practice Question
A project manager has identified a risk that could cause a $50,000 loss with a 20% probability. What is the Expected Monetary Value (EMV) of this risk?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
$10,000
EMV = Probability × Impact = 20% × $50,000 = $10,000. This is a quantitative risk analysis technique.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
$50,000
Why it's wrong here
This is the impact, not the EMV.
- ✓
$10,000
Why this is correct
Correct calculation: 0.20 × $50,000 = $10,000.
- ✗
$40,000
Why it's wrong here
Incorrect calculation.
- ✗
$25,000
Why it's wrong here
Incorrect calculation.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.