Courseiva
mediumMultiple ChoiceObjective-mapped

PK0-005 Practice Question: The project manager receives a defect report for…

Exhibit

Refer to the exhibit.

Exhibit: Configuration Item Status
Item ID  | Version | Status      | Last Modified
CI-101   | 1.2     | Approved    | 2023-10-15
CI-102   | 2.0     | Under Review| 2023-10-20
CI-103   | 1.0     | Approved    | 2023-09-01

The project manager receives a defect report for CI-103. The team identifies that a new requirement necessitates updating CI-103. According to the configuration management process, what should the project manager do FIRST?

⚠ Common exam trap

Watch out — candidates often assume a defect report automatically triggers a fix, but in configuration management, any change to a baselined CI must first go through the formal change control process, not directly to development or deployment.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Submit a change request to the change control board.

When a defect report indicates that a new requirement necessitates updating a configuration item (CI-103), the first step in the configuration management process is to submit a change request to the change control board (CCB). This ensures that any modification to a baselined CI is formally evaluated, approved, and tracked before implementation, preventing unauthorized changes that could destabilize the project.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Ignore the defect because CI-103 is approved.

    Why it's wrong here

    Approved status does not mean defects should be ignored.

  • Update CI-103 to version 1.1 and deploy the fix.

    Why it's wrong here

    Version update should follow change approval.

  • Assign the defect to a developer to fix immediately.

    Why it's wrong here

    Fixing without change control bypasses process.

  • Submit a change request to the change control board.

    Why this is correct

    Any change to a configuration item should go through change control.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.