Finish-to-Start (FS)
Finish-to-Start (FS) is the most common dependency where the successor cannot start until the predecessor finishes.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Finish-to-Finish (FF)
Why it's wrong here
FF means the successor cannot finish until the predecessor finishes.
- ✗
Start-to-Start (SS)
Why it's wrong here
SS means the successor can start when the predecessor starts.
- ✓
Finish-to-Start (FS)
Why this is correct
FS means the successor cannot start until the predecessor finishes.
- ✗
Start-to-Finish (SF)
Why it's wrong here
SF means the successor cannot finish until the predecessor starts.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.