Which TWO of the following are examples of project constraints? (Select TWO).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Cost

Scope and cost are classic project constraints (triple constraint). Team morale and customer satisfaction are not typically considered constraints in the traditional sense.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Cost

    Why this is correct

    Cost is a key constraint.

  • Project manager experience

    Why it's wrong here

    Experience is not a constraint.

  • Team morale

    Why it's wrong here

    Morale is a factor but not a constraint.

  • Customer satisfaction

    Why it's wrong here

    Satisfaction is a goal, not a constraint.

  • Scope

    Why this is correct

    Scope is a key constraint.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.