PK0-005 Project Management Concepts Practice Question
Which TWO of the following are examples of project constraints? (Select TWO).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Cost
Scope and cost are classic project constraints (triple constraint). Team morale and customer satisfaction are not typically considered constraints in the traditional sense.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Cost
Why this is correct
Cost is a key constraint.
- ✗
Project manager experience
Why it's wrong here
Experience is not a constraint.
- ✗
Team morale
Why it's wrong here
Morale is a factor but not a constraint.
- ✗
Customer satisfaction
Why it's wrong here
Satisfaction is a goal, not a constraint.
- ✓
Scope
Why this is correct
Scope is a key constraint.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.