PK0-005 Practice Question: Arrange the phases of the project life cycle in…
Arrange the phases of the project life cycle in the correct order.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Initiating, Planning, Executing, Monitoring and Controlling, Closing
The standard project life cycle phases are Initiating, Planning, Executing, Monitoring and Controlling, and Closing.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Initiating, Planning, Executing, Monitoring and Controlling, Closing
Why this is correct
This is the correct order as per PMBOK Guide. Initiating starts the project, Planning defines scope and objectives, Executing performs the work, Monitoring and Controlling tracks progress, and Closing formally ends the project.
- ✗
Planning, Initiating, Executing, Monitoring and Controlling, Closing
Why it's wrong here
This is incorrect because planning cannot occur before the project is initiated. Initiating must come first to authorize the project.
- ✗
Initiating, Planning, Executing, Closing, Monitoring and Controlling
Why it's wrong here
This is incorrect because monitoring and controlling occurs throughout the project, including during executing, and closing is the final phase after all work is done.
- ✗
Executing, Initiating, Planning, Monitoring and Controlling, Closing
Why it's wrong here
This is incorrect because executing cannot start before initiating and planning. The project must be initiated and planned before work can be executed.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.