A project manager is assigned to a project in a matrix organization where the functional managers have significant control over team members. The PM has limited authority. This describes which type of matrix?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Weak matrix
In a weak matrix, the functional manager has more authority than the project manager.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Balanced matrix
Why it's wrong here
In balanced matrix, authority is shared equally.
- ✓
Weak matrix
Why this is correct
Functional manager has more authority.
- ✗
Strong matrix
Why it's wrong here
In strong matrix, the PM has more authority.
- ✗
Projectized
Why it's wrong here
In projectized, PM has full authority.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.