Courseiva
easyMultiple ChoiceObjective-mapped

PK0-005 A project team is creating a WBS Practice Question

A project team is creating a WBS. They ensure that every deliverable and work package is included and that the sum of the work at the lower levels equals the total work at the higher levels. Which principle are they applying?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

100% rule

The 100% rule states that the WBS includes all work defined by the scope and that the sum of lower-level work equals the total work at higher levels.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Rolling wave planning

    Why it's wrong here

    Rolling wave planning involves progressive elaboration, not the completeness rule.

  • 100% rule

    Why this is correct

    The 100% rule ensures the WBS captures all project work.

  • Decomposition

    Why it's wrong here

    Decomposition is the process of breaking down deliverables, but the 100% rule ensures completeness.

  • Scope verification

    Why it's wrong here

    Scope verification is about formal acceptance, not WBS creation.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.