Courseiva
hardMultiple ChoiceObjective-mapped

PK0-005 Practice Question: A project is in execution, and the project…

A project is in execution, and the project manager discovers that a key resource is overallocated. Which of the following actions should the project manager take to resolve this?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Apply resource leveling

Resource leveling is a technique to address resource overallocation by delaying tasks within their float.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Add more resources

    Why it's wrong here

    Adding resources may increase cost and is not always feasible; resource leveling is typically preferred.

  • Outsource the work

    Why it's wrong here

    Outsourcing may be an option but is not the first action to resolve overallocation.

  • Apply resource leveling

    Why this is correct

    Resource leveling adjusts the schedule to resolve overallocation without adding resources.

  • Reduce project scope

    Why it's wrong here

    Reducing scope is a drastic measure and should be considered only after other options.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on PK0-005

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which TWO of the following are examples of resource leveling techniques?

hard
  • A.Fast tracking
  • B.Splitting tasks
  • C.Crashing
  • D.Delaying tasks
  • E.Adding resources

Why B: Resource leveling adjusts the schedule to resolve over-allocation. Delaying tasks and splitting tasks are common leveling techniques. Fast tracking and crashing are schedule compression techniques. Adding resources does not level; it may overload further.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.